Download A survey of methods and techniques used for Seismic retrofitting of

Survey
yes no Was this document useful for you?
   Thank you for your participation!

* Your assessment is very important for improving the workof artificial intelligence, which forms the content of this project

Document related concepts

Kashiwazaki-Kariwa Nuclear Power Plant wikipedia , lookup

2009 L'Aquila earthquake wikipedia , lookup

1570 Ferrara earthquake wikipedia , lookup

1880 Luzon earthquakes wikipedia , lookup

1985 Mexico City earthquake wikipedia , lookup

Earthquake engineering wikipedia , lookup

Seismic retrofit wikipedia , lookup

Transcript
INTERNATIONAL JOURNAL OF CIVIL AND STRUCTURAL ENGINEERING
Volume 2, No 1, 2011
© Copyright 2010 All rights reserved Integrated Publishing services
Research article
ISSN 0976 – 4399
A survey of methods and techniques used for Seismic retrofitting of
RC buildings
Vijayakumar. A1, Venkatesh Babu. D.L2
1- Assistant Professor, Department of Civil Engineering, Jansons Institute of technology,
Coimbatore, Tamilnadu, India.
2- Principal, United Institute of Technology, Coimbatore, Tamilnadu, India.
[email protected]
doi:10.6088/ijcser.00202010093
ABSTRACT
It is a known fact that the Globe is facing a threat of natural disasters from time to time.
With particular records based on earthquake occurrence, the consequences are loss of
human lives and destruction of properties, which ultimately affects the natural economy.
The occurrence of an earthquake cannot be predicted and prevented but the preparedness
of the structures to resist earthquake forces become more important. Keeping the view of
constant revision of the seismic zones in India, lack of proper design and detailing of
structures against earthquake. Initiatives are being taken by a number of agencies in
country towards reduction of seismic risk in existing building. In the past few decades,
significant research effort, work over, have been dedicated to retrofitting of existing
building and number of research papers and reports have been published. Still, the subject
is in development stages and standardization of practice is a distant goal. In this paper
comprehensive review of methods and techniques used for seismic retrofitting of RC
buildings are discussed briefly. Finally, general concluding remarks are made along with
possible future direction of research.
Keywords: RC Building, Seismic zone, Earthquake, Retrofitting, Strengthening.
1. Introduction
A large number of existing buildings (Yogendra Singh, 2003) in India are severely
deficient against earthquake forces and the number of such buildings is growing very
rapidly. This has been highlighted in the past earthquake. Retrofitting of any existing
building is a complex task and requires skill, retrofitting of RC buildings is particularly
challenging due to complex behavior of the RC composite material. The behavior of the
buildings during earthquake depends not only on the size of the members and amount of
reinforcement, but to a great extent on the placing and detailing of the reinforcement. The
construction practices in India result in severe construction defects, which make the task
of retrofitting even more difficult.
There are three sources of deficiencies in a building, which have to be accounted for by
the retrofitting engineer: (i) inadequate design and detailing, (ii) degradation of material
with time and use, and (iii) damage due to earthquake or other catastrophe. The retrofit
engineer is expected to estimate the deficiency resulting from all the three sources,
suggest a retrofit scheme to make up for the deficiencies and demonstrate that the
Received on July 2011 published on September 2011
56
A survey of methods and techniques used for Seismic retrofitting of RC buildings
Vijayakumar. A, Venkatesh Babu. D.L
retrofitted structure will be able to safety resist the future earthquake forces expected
during the lifetime of the structure. This paper presents a brief review of the available
methods and techniques for retrofitting of RC building.
The report Applied Technology
Council, (1996) highlights the nonlinear static
pushover analysis. It is an efficient method for the performance evaluation of a structure
subjected to seismic loads. The step by step procedure of the pushover analysis is to
determine the capacity curve, capacity spectrum method and displacement coefficient
method. By using these procedures this report is detailed with modeling aspects of the
hinge behavior, acceptance criteria and locate the performance point. The present
guidelines (Dr Durgesh C Rai., 2005) are intended to provide a systematic procedure for
the seismic evaluation of buildings, which can be applied consistently to a rather wide
range of buildings. This document also discusses some cost effective strengthening
schemes for existing older buildings where identified as seismically deficient during the
evaluation process.
The document (Dr Durgesh C Rai., 2005) highlights a higher degree of damage in a
building is expected during an earthquake, if the seismic resistance of the building is
inadequate. The decision to strengthen it before an earthquake occurs depends on the
building’s seismic résistance. The structural system of deficient building should be
adequately strengthened, in order to attain the desired level of seismic resistance. This
publication (FEMA156, 1994) presents a methodology to estimate the costs of seismic
rehabilitation projects at various locations in the United States. The above edition is
based on a sample of almost 2,100 projects, with data collected by using a standard
protocol, strict quality control verification, and a reliability rating. A sophisticated
statistical methodology applied to this database yields cost estimates of increasing quality
and reliability as more and more detailed information on the building inventory is used in
the estimation process.
This handbook (FEMA172,1992) describes techniques that engineers can use to solve a
variety of seismic rehabilitation problems in existing buildings, a broad spectrum of
building types and building components (both structural and nonstructural). Techniques
are illustrated with sketches, and the relative merits of the techniques are also discussed.
This handbook and its supporting report (FEMA173, 1989), (FEMA174, 1989)
documents information need to develop a seismic rehabilitation program and establish
priorities for rehabilitation. Through the presentation of nationally applicable guidelines,
it helps local jurisdictions to make informed decisions about rehabilitating seismically
hazardous existing buildings, and it includes a review of the relevant technical and
societal issues and a procedure to resolve the issues. This report (FEMA237, 1992)
assists in the preparation of guidelines for the seismic rehabilitation of existing buildings.
It identifies and analyses issues that might impact the preparation of the guidelines and
offers alternative and recommended solutions to facilitate their development and
implementation. It also discusses issues related to the scope, implementation, and format
of the guidelines, as well as coordination efforts and legal, political, social, and economic
aspects. Issues related to historic buildings, research and new technology, seismicity and
mapping, and engineering philosophy and goals are also discussed. The report concludes
with a presentation of issues related to the development of specific provisions for major
International Journal of Civil and Structural Engineering
Volume 2 Issue 1 2011
57
A survey of methods and techniques used for Seismic retrofitting of RC buildings
Vijayakumar. A, Venkatesh Babu. D.L
structural and nonstructural elements. This document (FEMA308, 1999) consists
practical guidance for the repair, upgrade of earthquake damaged concrete and masonry
wall buildings. Target audiences are design engineers, building owners, officials,
insurance adjusters, and government agencies. The publication contains sections on
performance based repair design, repair technologies, categories of repair, and
nonstructural considerations. The last section includes repair guides, which provides
outline specifications for typical repair procedures. This publication (FEMA315, 1998)
discusses the mission, history, and results of FEMA are Existing Building Program (EBP)
and provide four objectives and 25 tasks to be carried out through the EBP. The four
objectives are:
1. Promote seismic rehabilitation and advance the implementation of previously
developed materials
2. Monitor the use of and refine existing materials
3. Develop new seismic rehabilitation tools, and
4. Consider new program directions for the EBP. Estimated costs for the next ten to
fifteen years and guidelines for plan implementation are also included.
These publications (FEMA395-399, 2003-04) describe administrators with information to
assess the seismic vulnerability of school buildings, hospital building, office building,
apartment building, retail building and to implement a program of incremental seismic
rehabilitation. Increase in the number of seismically resistant buildings in all areas of
identified earthquake risk.
2. Methods of Seismically Deficient Building
Existing buildings (Murty CVR, 2002) can become seismically deficient when (a)
seismic design code requirements are upgraded since the design of these buildings with
an older version of the code; (b) seismic design codes are deficient, (c) engineering
knowledge makes advances rendering insufficient the previous understanding used in
their design, and (d) designers lack understanding of the seismic behavior of structures.
Indian buildings built over the past two decades are deficient because of items (b), (c),
and (d) above.
3. Seismic Retrofitting of Deficient RC Buildings
Concept of pushover analysis (Sudhir K. Jain et at., 2002) that is becoming a popular tool
in the profession for design of new buildings, seismic evaluation of existing buildings and
developing appropriate strategy for seismic retrofitting of buildings. It is shown how this
analytical technique can be useful in deciding seismic retrofitting strategy and techniques.
Pushover analysis of the structures (Lakshmanan D, 2006) using SAP 2000 evaluating
the various repair strategies for use in the improvement of the seismic performance of RC
structures are highlighted. The behaviors of repaired beams of beam column joints are
discussed. It is observed that inherent deficiencies in the detailing of the beam-column
joints get reflect even after repair, though the performance factors indicate significant
International Journal of Civil and Structural Engineering
Volume 2 Issue 1 2011
58
A survey of methods and techniques used for Seismic retrofitting of RC buildings
Vijayakumar. A, Venkatesh Babu. D.L
improvement. Two of the logical extensions show that the repair would not be as
effective in these cases. The nonlinear static analysis of RC building (Shailesh Kr.
Agrawal et al., 2003) is performed using pushover approach before and after retrofitting.
The comparison of strength parameters and pushover curve indicates that there is increase
in ductility. As regards to stiffness of the building, it is seen that it remains more or less
same up to linear stage, while in nonlinear stage every point increase after retrofitting.
The strength of the building is correlated with base shear, the net enhancement in strength
after retrofitting. This paper (Abhijit Mukherjee et al., 2004) introduces a method of
design of structural upgradation using FRC and discusses the design of enhancement of
RCC elements with FRC, a strategy of upgradation of RCC frames and use of the
developed strategy of upgradation for retrofitting of RCC frames based on Capacity
Spectrum Method.
Evaluation (Richard N. White) procedures and retrofit strategies for existing reinforced
concrete framed buildings are designed primarily for gravity loads. Selected evaluation
and rehabilitation methods are reviewed, including portions of the 1996 NEHRP
guidelines for seismic rehabilitation of buildings. New research results for predicting the
behavior of masonry infilled frames are presented, and general research issues are
suggested. The seismic evaluation and retrofitting procedures of reinforced concrete
buildings (Seki M et al., 2007) within JICA technical cooperation project in Romania.
The content of the paper covers i) an outline of the seismic evaluation; history and
comparison of Romanian seismic design codes with the Japanese seismic evaluation
guidelines, ii) an outline of the retrofitting techniques which are transferred from Japan to
Romania and structural tests for retrofitting techniques employed in Romania and iii)
retrofitting details that were used by JICA/NCSRR in the retrofitting design of two
vulnerable buildings in Bucharest.
Case studies (Chandrasekaran S et al., 2003) are conducted in the 150 year old building
Ganga Mahal located in Assi Ghat and Sanskrit University of Kashi. The buildings are
mathematically modeled and analyzed for its structural behavior. The suggested measures
of structural strengthening for these heritage structures are based on the understanding of
the detailed studies conduct by the authors on the failure pattern of various structures
during earthquakes in India. The typical (Suneja BP, 2003) features of seismic retrofitting
strategy for historic monuments and the various structural control methods, effectiveness
of control methods, as compared to the existing conventional techniques and the issues
related with the adaptability of such innovative techniques are addressed. A case study
(Ryanj Williams et al., 2009) is conducted to find the impact of a modest retrofit strategy
applied to the identical buildings in Memphis and San Francisco. The probabilities of
failure and generalized reliability indices are calculated for the retrofitted building in both
locations and compared to the corresponding values for the original buildings. The results
of the parametric analysis and case study are used to determine the effects of building
location on retrofit feasibility.
The traditional methods of seismic retrofitting (Giusepe Oliveto et al., 2005) are reviewed
and their weak points are identified. Modern methods and philosophies of seismic
retrofitting, including base isolation and energy dissipation devices, are reviewed. The
presentation is illustrated by case studies of actual buildings, where traditional and
International Journal of Civil and Structural Engineering
Volume 2 Issue 1 2011
59
A survey of methods and techniques used for Seismic retrofitting of RC buildings
Vijayakumar. A, Venkatesh Babu. D.L
innovative retrofitting methods are applied. An overview of analysis methodologies (Leo
Panian et al., 1999) are used for a seismic rehabilitation of an historic high rise building is
presented. The use, in the design process, of nonlinear soil structure interaction
foundation analyses and three dimensional finite element analyses of the towers are
highlighted. Finally, the impacts of the results of the analyses on the construction details
are discussed.
4. Improvement of Existing RC Buildings
Three levels of improvement of existing RC frame buildings (Murty CVR, 2002) are
possible, namely (a) repair, (b) restore, and (c) strengthen. The consequence of any
prescribed method of the retrofitting are (a) adding brick masonry walls in all possible
bays in ground storey, (b) jacketing of all RC columns in ground storey only, (c) adding
steel diagonal braces in some bays in ground storey, and (d) infilling existing RC frame
with RC structural walls in some bays in ground storey only. In all cases, foundation
strengthening may be essential. On the seismic capacity of the building should be
quantitatively evaluated its effectiveness from the points of view of strength, stiffness and
ductility are shown in Figure [1.a, 1.b]. Sometimes, a retrofit scheme may have better
performance than the damaged structure, but still may be poor; the retrofit scheme that
assures at least a basic ductility is preferable to the others.
Figure 1: a) Effect of retrofit Strategy on lateral strength, stiffness and ductility,
b) Relative performance of different retrofit strategies. (Murty CVR, 2002)
5. Methods of Seismic Retrofitting
This paper (Murty CVR, 2002) deals with two approaches a) simple approach, and b)
state-of-the-art approach are presented for seismic retrofitting of existing RC frame
buildings. For the retrofit of general RC frame buildings in India, it is technically and
economically the best compromise to adopt the first approach because of the prevalent
dismal practices of seismic structural design and construction in the country. And, in the
International Journal of Civil and Structural Engineering
Volume 2 Issue 1 2011
60
A survey of methods and techniques used for Seismic retrofitting of RC buildings
Vijayakumar. A, Venkatesh Babu. D.L
retrofit of the critical structures and important structures, it is necessary to take up the
state-of-the-art retrofit approach.
This paper (Kaustubh Dasgupta et al.,) concludes that to identify an efficient retrofitting
method for existing open ground storey RC frame buildings. A two dimensional RC
frame is designed with non-ductile. Detailing is subjected to nonlinear static pushover
analysis. The RC frame is retrofitted by three methods. a) Concrete jacketing of columns
in the ground storey, b)Brick masonry infill in the ground storey, and c) RC structural
wall in the ground storey panel of all the methods studied the use of structural wall in the
ground storey panel give the maximum strength and ductility.
The objective of this study (Ashutosh V Mahashabde et al., 2003) is to identify an
efficient retrofitting method for reinforced concrete buildings. Two buildings: One open
ground storey with infills and the other partial open ground storey with infills, which are
damaged in the January 2001 Bhuj earthquake, are subjected to static pushover analysis
with code specified design shear distribution. The observed failure modes conform to the
actual structural damages sustain by the buildings during that earthquake. The selected
methods of retrofitting are a) Jacketing of columns in the ground storey, b) Structural
walls in the ground storey of some selective panels, and c) Structural walls for all the
stories in some panels. These three basic schemes are used in combination for
ascertaining an economical method giving the maximum strength and ductility. Of all the
methods studied, the combination of column jacketing in ground storey and shear wall
throughout the height of the building with selective strengthening of upper storey frame
members, give the most economic and desirable performance.
The objective of this study (Ei-Sokkary H et al., 2009) is to investigate analytically the
effectiveness of different rehabilitation patterns in upgrading the seismic performance of
existing nonductile RC frame structures. The study investigates the performance of two
RC frames (with different heights representing low and high rise buildings) with or
without masonry infill when rehabilitated and subjected to three types of ground motion
records. The ground motion records represent earthquakes with low, medium and high
frequency contents. Three models are considered for the RC frames: bar frame, masonry
infilled frame with soft infill and masonry infilled frame with stiff infill. Four
rehabilitation patterns are studied namely; 1) introducing a RC shear wall, 2) using steel
bracing, 3) using diagonal FRP strips (FRP bracings) in the case of masonry infilled
frames, and 4) wrapping or partially wrapping the frame members (columns and beams)
using FRP composites. Incremental dynamic analysis is conducted for the studied cases.
The seismic performance enhancement of the studied frames is evaluated in terms of the
maximum applied peak ground acceleration resisted by the frames, maximum inter storey
drift ratio, maximum storey shear-to-weight ratio and energy dissipation capacity.
An efficient (Binici B et al., 2006) FRP retrofit scheme was developed, in which hallow
clay brick infill walls are utilized as lateral load resisting elements. Based on failure
modes and measured deformation limits obtained from a large database of experiments, a
diagonal compression-strut and tension-tie model are developed. The model is verified
with a number of reinforced concrete frame test results with and without upgrades. The
International Journal of Civil and Structural Engineering
Volume 2 Issue 1 2011
61
A survey of methods and techniques used for Seismic retrofitting of RC buildings
Vijayakumar. A, Venkatesh Babu. D.L
characteristics of various intervention techniques (Jong – Wha Bai, 2003), (Helen Santhi
M et al., 2003) are discussed and the relationship between retrofit and structural
characteristics are also described. In addition, several case study structures for which
retrofit techniques have been applied are presented. This paper (Zou XK et al., 2007)
presents an optimization technique for the performance based seismic FRP retrofit design
of RC building frames. The thickness of FRP jackets used for confinement of columns
are taken as the design variables, and minimizing the volume and hence the material cost
of the FRP jackets are the design objective in the optimization procedure. The pushover
drift is expressed explicitly in terms of the FRP sizing variables using the principle of
virtual work and the Taylor series approximation. The Optimality Criteria (OC) approach
is employed for finding the solution of the nonlinear seismic drift design problem. A
numerical example is presented and discussed to demonstrate the effectiveness of the
proposed procedure. Performance based seismic evaluation of building models (Savitha
V Athani et al., 2009) namely: bare frame, soft storey, retrofitted building with
unreinforced masonry infill and increased stiffness of columns and different locations in
open ground storey for G+2, G+5, G+8. Storey’s located in seismic zone III. The
buildings are designed by gravity loads which are analyzed by equivalent static method
using ETAB and nonlinear version 9 software. The recent (K.G.Bhatia, 2003) Indian
earthquake has clearly demonstrated that maximum suffering during earthquake disaster
is bore by common man. Seismic evaluation of majority of such construction, though
essential, appears to be infeasible. Whereas desired safety can still be expected and
achieved for engineered constructions, its assurance for nonengineered construction
draws a big question mark? The paper dwells upon the real life situation and the likely
impact of the post earthquake scenario on the society.
The present paper (Amar Prakash et al., 2003) deals with the seismic retrofitting of an
existing fourteen storied RC building frame located in seismic zone IV. The study
includes seismic evaluation and retrofitting of RC framed building, by using steel bracing
and infill masonry walls. The seismic performance of two retrofitting techniques such as
steel bracing (V, diamond and cross pattern) and infill walls are relatively compared.
Among three patterns of steel bracing, cross pattern shows better performance than V and
diamond bracing patterns. The structural analysis (Dr. Meher Prasad A et al.,) is
performed using a suitable computer analysis program. The steps involve developing a
computational model of the building, applying the external forces, calculating the internal
forces in the members of the building, calculating the deformations of the members and
building and finally interpreting the results. First deficiencies observed in existing RC
buildings for resisting earthquake identified. It is essential to identify the deficiencies in a
building before undertaking retrofit. Identification of the deficiencies is also expected to
create awareness for future construction. The material for each building (Dr Santhakumar
AR et al.,) is presented under the following topics; rapid visual screening, data collection,
preliminary evaluation, detailed evaluation and retrofit.
6. Conclusion
Many guidelines are reviewed regarding seismic rehabilitation of school, office, hospital
and apartment buildings. Some of the researchers discussed the various seismic
International Journal of Civil and Structural Engineering
Volume 2 Issue 1 2011
62
A survey of methods and techniques used for Seismic retrofitting of RC buildings
Vijayakumar. A, Venkatesh Babu. D.L
retrofitting and strengthening methods for existing building. The following methods are
carried out by most of the researchers which are concrete jacketing of columns of ground
floor, brick masonry infill in the ground floor, X and V bracing, shear wall, FRP of
beams and columns. All these topics require further research, and it is essential for
seismic retrofitting of reinforced concrete structures.
7. References
1.
ATC 40. Seismic evaluation and retrofit of concrete buildings Applied
Technology Council, (1996).
2.
Dr Durgesh C Rai, (2005), guidelines for seismic evaluation and strengthening
of existing building, Provision with commentary and explanatory examples,
Indian Institute of Technology Kanpur, Document no- IITK-GSDMAEarthquake 6, vol. 4.
3.
Dr Durgesh C Rai. Review of documents on seismic strengthening of existing
building, Document no- IITK-GSDMA-Earthquake 7, vol. 1.
4.
FEMA156. Typical costs for seismic rehabilitation of existing buildings.
Volume 1: Summary. Second edition. Hart consultant group Inc. Santa
Monica CA, (1994).
5.
FEMA157. Typical costs for seismic rehabilitation of existing buildings:
Volume 2: Supporting documentation. Second edition. Hart consultant group
Inc. Santa Monica CA, (1995).
6.
FEMA172. NEHRP handbook of techniques for the seismic rehabilitation of
existing buildings. Building seismic safety council. Washington D.C, (1992).
7.
FEMA173. Establishing programs and priorities for the seismic rehabilitation
of buildings: Supporting report. Building systems development Inc.
Washington, D.C, (1989).
8.
FEMA174. Establishing programs and priorities for the seismic rehabilitation
of buildings: Handbook. Building systems development Inc. Washington.D.C,
989.
9.
FEMA237. Development of guidelines for seismic rehabilitation of buildings
– Phase 1: Issues identification and resolution. Applied Technology Council.
Redwood city CA, (1992).
10.
FEMA308. The repair of earthquake damaged concrete and masonry wall
buildings. Applied Technology Council. Redwood city CA, (1999).
11.
FEMA315. Seismic rehabilitation of buildings: Strategic plan 2005.
Earthquake engineering research institute. Washington, D.C, (1998).
International Journal of Civil and Structural Engineering
Volume 2 Issue 1 2011
63
A survey of methods and techniques used for Seismic retrofitting of RC buildings
Vijayakumar. A, Venkatesh Babu. D.L
12.
FEMA395. Incremental seismic rehabilitation of school buildings K-12,
World institute for disaster risk management, Alexandria VA, (2003).
13.
FEMA396, Incremental seismic rehabilitation of hospital buildings, World
institute for disaster risk management, Alexandria, VA, (2003).
14.
FEMA397, Incremental seismic rehabilitation of office buildings. World
institute for disaster risk management. Alexandria, VA, (2003).
15.
FEMA 398. Incremental seismic rehabilitation of multifamily apartment
buildings. World institute for disaster risk management. Alexandria, (2004).
16.
FEMA399. Incremental seismic rehabilitation of retail buildings. World
institute for disaster risk management. Alexandria, (2004).
17.
Murty CVR, (2002), quantitative approach to seismic strengthening Of RC
frame building, Seminar on seismic assessment and retrofitting buildings, pp
19-27.
18.
Sudhir K. Jain, Srikant T, (2002), analysis for seismic retrofitting of buildings,
The Indian concrete journal, pp 479-484.
19.
Lakshmanan D, (2006), seismic evaluation of retrofitting of building and
structures, ISET journal of earthquake technology, 43(1-2), pp 31-48.
20.
Shailesh Kr. Agrawal, Ajay Chourasia, (2003), “Nonlinear static analysis for
seismic evaluation and retrofit of RC buildings”, Workshop on rertofitting of
structures, pp 116-124.
21.
Abhijit Mukherjee, Amit R. Kalyani, (2004), “Seismic retrofitting of
reinforced concrete frames with fiber reinforced composites”, Workshop on
seismic evaluation and retrofitting of building, pp 74-82.
22.
Richard N. White, Khalid Mosalam. Seismic evaluation and rehabilitation of
concrete buildings, Cornell University, Ithaca NY 14853 USA, pp 177-186.
23.
Seki M, Vacareanu R, Chesca B, Pavel M, Lozinca E, Cotofana D, Georgescu
B, Kaminosono T, (2007), “Overview on seismic evaluation and retrofitting
within JICA technical cooperation project on reduction of seismic risk in
Romania”, International symposium on seismic risk reduction, pp 181-194.
24.
Chandrasekaran S, Saurab lahari, Kumar V, (2003), “Study of seismic
vulnerability and retrofitting techniques for heritage buildings in Banaras”,
Recent trends in concrete technology and structures, Kumaraguru College of
Technology, Coimbatore, pp 699-707.
25.
Suneja BP, (2003), “Structural Control Concept: A possible avenue for
seismic retrofitting of historic monuments”, Recent trends in concrete
International Journal of Civil and Structural Engineering
Volume 2 Issue 1 2011
64
A survey of methods and techniques used for Seismic retrofitting of RC buildings
Vijayakumar. A, Venkatesh Babu. D.L
technology and structures, Kumaraguru College of Technology, Coimbatore,
pp 722-729.
26.
Ryanj Williams, Paolo Gardoni, Joseph M Bracci, (2009), decision analysis
for seismic retrofit of structures, Structural safety, 31, pp 188-196.
27.
Giusepe Oliveto, Massimo Marleta, (2005), seismic retrofitting of reinforced
concrete buildings using traditional and innovative techniques, ISET journal
of earthquake technology, 42(2-3), pp 21-46.
28.
Leo Panian, David Mar, Steven Tiipping, Berkeley. Complete capacity design
of a seismic retrofit for an historic high rise building using practical analytical
methods, SEAOC 1999 convention, pp 277-294.
29.
Kaustubh Dasgupta, Murty CVR. Quantitative seismic retrofitting of open
ground storey RC frame buildings.
30.
Ashutosh V Mahashabde, Kaustubh Dasgupta, Murty CVR, (2003), “Seismic
strengthening of gravity load designed RC frame buildings”, 4th International
conference on earthquake engineering and seismology.
31.
Ei-Sokkary H, Galal K, (2009), analytical investigation of the seismic
performance of RC frames rehabilitated using different rehabilitation
techniques, Engineering structures, 31, pp 1955-1966. `
32.
Binici B, Ozcebe G, (2006), “Seismic evaluation of infilled reinforced
concrete frames strengthened with FRPS”, 8th U.S. national conference on
earthquake engineering, pp 1717.
33.
Dr Alagusundaramoorthy P. Retrofit using fibre reinforced polymer
composite, Handbook on seismic retrofit of building, IIT Madras, pp 13.113.16.
34.
Jong – Wha Bai, (2003), seismic retrofit for reinforced concrete building
structures, Consequence based engineering institute final report, Mid-America
earthquake centre.
35.
Moe Cheung and Simon Foo. Seismic retrofit of existing buildings: innovative
alternatives. Public works and government services, Canada, pp 1-10.
36.
Amlan, Sengupta K, Badari VT Narayanan, Asokan A, (2003), “Seismic
retrofit of existing multistoreyed buildings in India-An overview of the
method and strategies”, Workshop on retrofitting of structures, IIT Roorkee,
pp 17-28.
37.
Yogendra Singh, (2003), “Challenges in retrofitting of RC buildings”,
Workshop on retrofitting of structures, IIT Roorkee, pp 29-44.
International Journal of Civil and Structural Engineering
Volume 2 Issue 1 2011
65
A survey of methods and techniques used for Seismic retrofitting of RC buildings
Vijayakumar. A, Venkatesh Babu. D.L
38.
Dr Amlan K Sengupta. Retrofit of reinforced concrete buildings, Handbook
on seismic retrofit of building, IIT Madras, pp 9.1-9.33.
39.
Parricio Rocha, Pedro Delgado, Anibal Costa, Raimundo Delgado, (2004),
Seismic retrofit of RC frames, Computers and structures, 83, pp 1523-1534.
40.
Helen Santhi M, Samuel Knight GM, Muthumani K, (2003), “Seismic retrofit
of reinforced concrete frames”, National seminar on advances in concrete
technology and concrete structures for the future, pp 223-239.
41.
Zou XK, Teng JG, De Lorenzis I, Xia SH, (2007), optimal performance-based
design of FRP jackets for seismic retrofit of reinforced concrete frames,
Composite part-B, 38, pp 584-597.
42.
Savitha V Athani, Dyavanal SS, Annigeri DVSA, (2009), performance based
seismic evaluation and retrofitted of multistoried buildings, Bulletin of ACCE,
1, pp 21-27.
43.
K.G.Bhatia, (2003), “On the seismic evaluation and retrofitting of common
man’s residential houses”, Workshop on retrofitting of structures, IIT Roorkee,
pp 143-147.
44.
Amar Prakash, Thakkar SK, (2003), “A comparative study of retrofitting of
RC building”, Workshop on retrofitting of structures, IIT Roorkee, pp 159173.
45.
Esra Mete Guneyisi and Gulay Altay, (2005), a study on the seismic behavior
of a retrofitted building based on nonlinear static and dynamic analysis,
Earthquake engineering and engineering vibration, 4(1), pp 173-180.
46.
Dr. Meher Prasad A. Structural analysis for seismic retrofit, Handbook on
seismic retrofit of building, IIT Madras, pp 8.1-8.27.
47.
Dr Santhakumar AR, Dr Amlan K Sengupta. Retrofit case studies, Handbook
on seismic retrofit of building, IIT Madras, pp 16.1-16.46.
International Journal of Civil and Structural Engineering
Volume 2 Issue 1 2011
66