Download SECTION 16010

Survey
yes no Was this document useful for you?
   Thank you for your participation!

* Your assessment is very important for improving the workof artificial intelligence, which forms the content of this project

Document related concepts

Mechanical-electrical analogies wikipedia , lookup

Ground loop (electricity) wikipedia , lookup

History of electric power transmission wikipedia , lookup

Electronic engineering wikipedia , lookup

Switched-mode power supply wikipedia , lookup

Power engineering wikipedia , lookup

Alternating current wikipedia , lookup

Electrical engineering wikipedia , lookup

Distribution management system wikipedia , lookup

Metadyne wikipedia , lookup

Stray voltage wikipedia , lookup

Voltage optimisation wikipedia , lookup

Earthing system wikipedia , lookup

Electrical substation wikipedia , lookup

Electrician wikipedia , lookup

Ground (electricity) wikipedia , lookup

Telecommunications engineering wikipedia , lookup

Electrical wiring in the United Kingdom wikipedia , lookup

Electromagnetic compatibility wikipedia , lookup

Mains electricity wikipedia , lookup

Portable appliance testing wikipedia , lookup

Transcript
SECTION 16010
ELECTRICAL - GENERAL PROVISIONS
10.01
POWER OUTAGES
Power outages may be required on electrical equipment or circuits, however, no
power outage shall occur without the prior consent and coordination through the
Field Construction Manager.
10.02
CUTTING AND PATCHING
The Contractor shall perform cutting activities on structural parts of buildings and
structures required for the installation of his work and shall replace, fill, patch and
paint to match the existing surface(s) around such openings. The contractor shall
employ craftsmen skilled and regularly employed in the respective crafts involved.
Lintels, frames or reinforcement required for openings shall be provided by the
Contractor.
10.03
10.04
SHORING AND EQUIPMENT SUPPORTS
A.
The Contractor shall provide permanent and temporary shoring, anchoring, and
bracing required to make installations absolutely stable and rigid; even when
such shoring, anchoring and bracing not explicitly called out for.
B.
The Contractor shall adequately support free-standing panels, motor control
centers, enclosures, and other equipment requiring seismic support. This shall
include bolting to the floor, solid structural steel and permanent handrails to
prevent tipping. Under no conditions shall equipment be fastened to nonrigid
building steel (i.e., removable platform steel gratings, handrails, etc.).
TOUCH-UP PAINTING
A.
The touch-up painting of cabinets, panelboards and other electrical apparatus
shall be by the Contractor and shall be limited to touching up any surface
scratched or marred during shipment or installation. The materials used shall
match the surfaces being touched up, and be acceptable to the Owner's
representative.
B.
Architectural and industrial maintenance coatings used in this job must meet
Bay Area Quality Management District (AAQMD) regulations as they pertain to
Architectural Coatings (Regulation 8, Rule 3) and Industrial Maintenance
Coatings (Regulation 8, Rule 48). In addition, coating clean-up operations must
comply with these reference regulations (i.e., closed containers must be used
for storage of fresh and spent clean-up solvents; closed containers must be
used for the storage or disposal of clean-up cloths, paper, etc.; and clean-up of
spray equipment must not utilize organic chemicals unless equipment is used to
collect the solvent and minimize evaporation to the atmosphere).
In addition, a letter from the Contractor certifying compliance with this requirement
shall be forwarded to the Field Construction Coordinator.
16010-rev1
16010 - 1
September 2011
SECTION 16010
ELECTRICAL - GENERAL PROVISIONS
10.05
10.06
10.07
16010-rev1
CLEANING
A.
Exposed work shall be thoroughly cleaned. No dirt, debris, or liquid shall be
permitted in the conduit or electrical equipment during progress of the work; and
the Contractor shall clean conduit and electrical equipment, prior to installation.
B.
The Contractor shall maintain good housekeeping practices throughout the
progress of the work to maintain the work area in a neat, safe condition; and
shall, at least daily, dispose of trash.
EQUIPMENT INSTALLATION
A.
Equipment shall be installed plumb and without distortion of the enclosure or
structure.
B.
The Contractor shall check the tightness and tighten all connections as required.
C.
The Contractor shall follow manufacturer's recommendations.
D.
The Contractor shall correctly assemble equipment not factory installed.
E.
Work performed shall maintain fire ratings and cleanroom classifications. Any
work done that destroys cleanroom classifications shall be rectified, at no
expense to the Owner, and any of the Owner's property damaged shall be
replaced, at no expense to the Owner.
EQUIPMENT IDENTIFICATION
A.
Each item of electrical equipment, including enclosures, service equipment,
motor control, control/push-button stations, and other equipment shall be
provided with a nameplate showing equipment number, function and location of
power source. The nameplates shall be laminated plastic, with white letters
engraved on a black background as shown on the drawings.
B.
Nameplates for enclosures shall be permanently attached to the enclosure with
silicone adhesive, or approved equal. Pressure sensitive backing shall not be
considered an adequate substitute.
16010 - 2
September 2011
SECTION 16010
ELECTRICAL - GENERAL PROVISIONS
10.08
TESTING
A.
Electrical Tests
The Contractor shall test the entire installation upon completion to determine its
compliance with the specifications.
Design engineer/ contractor will perform ‘coordination calculation’ between new
device breaker and the supply power breaker. Establish whether new protective
breaker for device exceeds supply power breaker’s “instantaneous trip setting”.
In the event new device breaker exceeds supply power breaker instantaneous
trip setting, new device breaker‘s setting will be adjusted to well below the
settings of the supply breaker but adjusted properly to avoid nuisance tripping
of the new device.
If the new device breaker cannot be adjusted, then an adjustable type breaker
will be installed in lieu of non adjustable type.
The Contractor shall check wiring for shorts, continuity, grounds, and improper
connections. 120 VAC convenience receptacles shall be checked for ground
impedance using an ECOS Model 1023 tester or a digital volt-ohm meter
capable of reading to the nearest hundredth of an ohm. Refer to Section
16906.03 (E).
Ground fault interrupt devices shall be tested individually. Test equipment shall
be provided by the Contractor, who shall make the required tests in accordance
with the Owner's test procedures, and shall make any additional tests necessary
to assure a defect-free system.
B.
System Tests
The Electrical Contractor shall operate electrical equipment, in conjunction with
the mechanical equipment tests, to demonstrate successful operation. These
tests shall be made in the presence of the Owner's representative.
C.
Correction
Defective workmanship or material disclosed by any test shall be removed by
the Contractor, replaced with new material at his expense and retested to verify
compliance with these specifications.
16010-rev1
16010 - 3
September 2011
SECTION 16010
ELECTRICAL - GENERAL PROVISIONS
D.
Instruction
The Electrical Contractor shall instruct the Owner's operating engineer in
operation and maintenance of the electrical equipment, and provide HGST with
four (4) copies of "Instruction and Operation" manuals from the manufacturer for
equipment furnished and installed by the Contractor, after the installation is
tested and accepted by the Owner.
E.
10.09
Tests on power centers and 12 KV systems shall be conducted by a qualified
electrical testing Contractor. Written test reports shall be submitted to the
Owner.
SAFETY PROCEDURES
Special precautions must be taken on power centers, electrical distribution,
machines, or processes which can cause injuries to personnel or facilities during
installation and energizing of equipment.
A . Electrical circuits shall be de-energized during installation.
B.
General Requirements
1.
Requirement that employees not work alone when exposed to hazardous
voltages, and that each employee engaged in the work knows how to:


Remove power from the circuit or equipment
Operate the equipment associated with the task, including implementing emergency
measures.
2.
Required Personal Protective Equipment (PPE) available and utilized.
3.
All portable equipment, measurement equipment, and hand tools inspected
prior to use.

The device is to be removed from service if a defect or contamination that could affect
insulating, mechanical, or grounding integrity is verified. Appropriate testing and inspection
must be completed before returning such equipment to service.
4.
Electrical protective equipment used, stored, maintained, inspected and
tested in accordance with applicable national standards and regulations,
and include, as a minimum:


Inspection of insulating apparel for scratches, punctures, cracks, or cuts before each use.
Rubber gloves marked with their rated voltage, and never used with voltages which exceed
this rating.
5.
16010-rev1
Maintenance of adequate clearances for safe access.
16010 - 4
September 2011
SECTION 16010
ELECTRICAL - GENERAL PROVISIONS
6.
An uninterrupted path to ground for equipment and systems having
exposed metallic parts if hazardous energy levels may be present.

Ground testing conducted at the completion of electric system installations, modifications,
preventive maintenance and repairs.


7.
Means provided to safely disconnect and isolate equipment from its source
of power.
8.
Use of ground-fault circuit-interrupters (GFCIs) on electrical power circuits
when tests are performed using test equipment that is not grounded.
Checking of GFCIs prior to start of testing
Posted warning signs in the are of the ungrounded test equipment
9.
Use of GFCIs on circuits serving outlets in damp, wet, or outdoor locations,
and in any other location where individuals using electrical equipment could
become well grounded.

Permanently installed GFCIs tested according to the manufacturer's recommended
frequency
 Portable GFCIs tested prior to each use
10. Commercial equipment and components listed, labeled, identified or
approved for its intended use by a recognized testing laboratory.
11. Use of extension cords for temporary periods only.
12. Use of power strips (temporary power taps), equipped with a fuse or circuit
protector for office equipment such as personal computers, where allowed
by local governing codes, provided the installation is suitable for the
intended use and the combined electrical load does not exceed the rating of
the circuit.
13. Installation of facility emergency power-off (EPO) switches near each major
exit in data processing equipment rooms and manufacturing areas as
required. Operation of the EPO shall disconnect power to all equipment
(except lighting, HVAC and communication equipment) and electrical
outlets in the room.


EPOs shall be readily accessible, but located or protected to prevent accidental contact
EPOs should also be considered for installation in electrical laboratories, machine tool
rooms, and raised floor installations
 EPOs shall be tested initially following installation, after modifications and periodically
(recommended annually).
 EPOs shall be labeled with the associated panel numbers and their locations which shall be
affected during power outage
C.
16010-rev1
Shutdown Procedure
16010 - 5
September 2011
SECTION 16010
ELECTRICAL - GENERAL PROVISIONS
1.
Definitions
ELECTRICAL SHUTDOWN is defined as the isolation of the circuit(s)
electrically, testing for absence of voltages, lockout/tagout, and applying
properly sized and placed grounds for personnel protection. High voltage
circuits require discharging of all residual voltages.
LOW VOLTAGE is defined as 600VAC or less.
HIGH VOLTAGE is defined as above 600VAC.
16010-rev1
16010 - 6
September 2011
SECTION 16010
ELECTRICAL - GENERAL PROVISIONS
2.
Mandatory Shutdown:
An electrical shutdown is required for all low and high voltage tie-ins and/or
modifications including power centers, motor control centers, 480/277V
lighting and distribution panels, and 208/120V panels with bolt-on circuit
breakers.
“Hot Panel work (Electrical Live Service) may only be implemented on
panels and devices not exceeding 480 Volts and when the following
conditions exist: de-energizing the equipment will introduce additional or
increased hazards, where it is not feasible due to equipment design or
operational limitations and to avoid a significant business impact. It may
not be implemented for convenience or expedience. The criteria identified
in Fed/OSHA 1910.333(a)(1) and in this specification shall be followed. All
others will require a formal electrical shutdown. Removal and installation of
all bolt-on circuit breakers shall be done during a formal electrical
shutdown. The request for hot panel work may be originated by: (a) the
contractor through the assigned engineer responsible for the project which
requires the hot panel work, (b) the construction coordinator through the
engineer responsible for the project which requires the hot panel work, or
(c) the electrical engineer responsible for the building. All requests shall be
approved by the electrical engineer responsible for the building and then
forwarded to the Facilities Engineering Manager for approval. (The
Facilities Engineering Manager may delegate this approval authority to
qualified Facilities Engineers within the Facilities Engineering Department).
The request will include justification, panel number, panel schedule, area
affected, contractor P & C, T & M, or PO number and the scope of work to
be performed."
It will be mandatory that the requester of the work be present during the
performance of the hot panel work. Delegation of this responsibility must
receive additional approval.
a.
A panel is an electrical distribution panel which contains circuit
breakers/switches/fuses and does not include equipment control
panels, terminal panels, junction boxes, etc.
b.
All hot circuits in all types of panels shall be adequately protected with
temporary shields while work is occurring.
c.
The removal of knock outs (KOS), insertion of conduit into boxes,
installation of lock nuts and bushings, and use of non-metallic fish tape
shall be allowed to take place when the temporary shield is in place.
d.
The removal and installation of circuit breakers shall only be performed
with tools having insulated handles.
The connection of wires shall be performed in the order of ground,
neutral and hot.
16010-rev1
16010 - 7
September 2011
SECTION 16010
ELECTRICAL - GENERAL PROVISIONS
e.
Qualified contractors and maintenance personnel shall be permitted to
do Hot Panel work after receiving management approval. The
minimum specific documented training required to be qualified to work
on or near exposed hazardous electrical energy shall be as listed
below:











Electrical hazard recognition
Effects of electricity on the body
Use of personal protective equipment
Restrictions on working alone in hazardous operations or locations
Selection, safe use, and maintenance of tools and test equipment
Lockout/tagout procedures
Use of safe electrical work practices
Procedure and testing of ground continuity
Use and testing of ground fault circuit interrupters (GFCI)
Unique hazards of the equipment being serviced
Skills and techniques required to distinguish exposed live electrical parts, and the nominal
voltage of exposed live parts
 Minimum approach distances associated with hazardous voltages to which the qualified
person will be exposed
 Proper use of precautionary techniques, personal protective equipment, test instruments,
insulating and shielding materials, and insulated tools used or working near or on exposed
energized electrical parts
3.
Shutdowns not required
Installation and/or removal of 120/208V plugable busduct units on 400A or
lower rated busducts. Use Square D plug-in busway.
Load measurements, monitoring, and testing/debugging of low voltage
circuits.
Hot phasing of high voltage cable selector switches. Work to be done by
personnel qualified to work on high voltage equipment.
Connections of conductors to the load side of spare circuit breakers of
120/208 volt panels.
4.
Lockout/Tagout:
The disconnecting means shall be opened and padlocked in the open
position. The disconnect shall de-energize all power and controls to the
component/equipment. The padlock shall be removed by the same person
after he has finished his work inside the component/device. Tag the
disconnect in accordance with Facilities Electrical Standard, SE-50.
D.
16010-rev1
Additional Requirements: High Voltage Power (Above 600V)
16010 - 8
September 2011
SECTION 16010
ELECTRICAL - GENERAL PROVISIONS
1.
Written procedures are required for all work on high voltage circuits.
Switching orders (procedures) written to ensure that all energized circuits
entering equipment, or an area in which work is to be done, are opened at a
location remote from the work area. Each step required to take highvoltage equipment out of service is to be listed and followed sequentially.
Switching orders must contain, as a minimum:
a. Employment of lockout/tagout for each disconnecting device
b. Testing of all exposed terminals, busways, and connections with a "glowtector" or "tic-tracer"
(or equivalent testing device) after the equipment has been de-energized, and before grounds
are applied
c. A list of all tools required for the job
d. Grounding of all exposed circuits with a ground set after the testing device indicates there is
no potential present
e. Isolation from backfeeds from alternate power sources, emergency power supplies, or
electronically coupled signals
f. Notification of personnel potentially affected by the work (but not involved) prior to power
shutdown, and again prior to power restoration
g. Compliance with the location's procedures for control of hazardous energy and electrical
safe work practices by any personnel not involved in the initial performance of the switching
orders

Such activities could include, for example, cleaning of high-voltage switchgear or evaluating
and adjusting terminations
2.
Switching orders signed by the originator, and reviewed by the supervising
individual and high-voltage technician.
3.
Restoration of power may be treated as a continuation of the original order, or
as a separate order. The restoration procedure is to list the step-by-step process
to:
a. Verify that all personnel involved have completed their work and have returned to a safe
area
b. Check for removal of all tools, tags, locks, grounds
c. Perform "high-pot" or phasing tests, where applicable
d. Secure panels and covers
e. Implement switching operations
4.
In emergency situations formal switching orders might not be appropriate. In
such situations, switching and repairs may be limited to the minimum necessary
to eliminate any hazard exposure to personnel or property. The high-voltage
technician and the individual supervising must agree on the appropriate actions
before each step is taken. The supervisor should have the authority to make
necessary emergency decisions. Written procedures are required to complete
work beyond the initial response to an emergency.
5.
Grounding Procedures
a. Determination made that equipment is de-energized before grounds are applied
16010-rev1
16010 - 9
September 2011
SECTION 16010
ELECTRICAL - GENERAL PROVISIONS
b. Test equipment approved for high voltage use only should be used on an area which has
been isolated by opening breakers or disconnects between the equipment and all sources of
power
c. Test equipment approved for high voltage use only should be applied to all exposed
terminals and conductors in the equipment to verify de-energization
d. Using a "hot stick," the other end of the grounding set is touched to all exposed terminals
and conductors, after which the ground clamps are to be firmly attached to all phase terminals
or conductors
e. Use of protective grounding equipment capable of conducting the maximum fault current
available at the point of the system being grounded for the time necessary to clear the fault.
Determination of the required ground conductor size must be made by a competent individual.
In no case is the protective grounding equipment to have an amperage capacity less than that
provided by a No. 2 American Wire Gauge (AWG) copper conductor.
6.
Design, installation, modification, or extension of power distribution systems in
compliance with applicable regulatory or national consensus standards or
practices.

Facilities Engineering must ensure that any exceptions are justified, and identify the
protective measures necessary to perform the work safely. Location Safety professionals
should be consulted in such situations
7.


Electrical testing of insulated high voltage rubber gloves prior to initial use, and
every six months thereafter by an approved testing laboratory.
Each high voltage glove is to be stamped with the date of the last electrical test
Visual inspection and air testing of rubber gloves prior to each use
8.
Electrical testing of high voltage rubber insulating blankets, matting, and covers
prior to initial use, and annually thereafter by an approved testing laboratory,
with date of test marked on equipment.
9.
Individuals performing work on high-voltage systems must not wear clothing
that, when exposed to electric arcs or flames, could increase the extent of any
injury. Avoid use of acetate, nylon, polyester and rayon fabric (alone or in
blends)
10. Conduct job briefings prior to the start of high-voltage operations each day or
shift. Additional briefings are required whenever changes occur which affect the
safety of the operations. Briefings are to include:




Sequence of operations for the project
Written operating procedures for each assignment
Test equipment and personal protective equipment to be used
Identification of potential hazards and their potential impact to personnel performing the
work
 Discuss all elements of the job (regardless of the previous experience and training of the
personnel involved)
 Resolve all questions before the work proceeds
16010-rev1
16010 - 10
September 2011
SECTION 16010
ELECTRICAL - GENERAL PROVISIONS
11. All non-emergency work on high-voltage equipment shall be planned in
advance. Written operating procedures shall be prepared by personnel
designated as "qualified" by appropriate location management.
12. A minimum of one qualified worker and one non-working supervisor for each job
of this type is required. The supervisor of the work must be identified prior to
start of work.
13. Individuals entering enclosed electrical spaces such as high-voltage manholes
and vaults shall be in compliance with the HGST safety manual requirements for
confined space entry.
14. Periodic inspection of high-voltage work shall be conducted by someone other
than those engaged in the work to ensure that safe work procedures, practices,
and use of personal protective equipment are being implemented.
Documentation of the inspection should be noted on the switching orders.
15. High-voltage testing includes, as a minimum, the following work practices:


Guarding of permanent test areas with walls, fences, or barriers
Control of access to field test areas through the use of signs, physical barriers or barricades,
or by assigning an observer to monitor the area
 Routine safety checks of the test area by the test operator in charge
 Grounding practices in compliance with applicable national standards or practices
16. All employees working with high voltage will be current in cardiopulmonary
resuscitation (CPR)
10.10
EXISTING CABLES
Existing cables above ceilings, in wall or under raised floors are critical to HGST
operations. Handle them with care. The cost to repair cut cables will be charged to
the contractor.
***END OF SECTION 16010***
16010-rev1
16010 - 11
September 2011