DRAFT OF PROPOSED NFPA 70® 2014 Edition National Electrical
... OF PROPOSED NFPA 70® 2014 Edition National Electrical Code® Note: Copies of proposals are published in the NEC ROP for the 2013 Annual Revision Cycle. ...
... OF PROPOSED NFPA 70® 2014 Edition National Electrical Code® Note: Copies of proposals are published in the NEC ROP for the 2013 Annual Revision Cycle. ...
Service and Metering Guide
... A “Job Site” copy of either the Electrical Contractor Authorization & Declaration of Compliance form or a Certificate of Electrical Inspection must also be on display at the work site. The “Job Site” copy of the form must be affixed to the structure receiving the electrical service. This form must b ...
... A “Job Site” copy of either the Electrical Contractor Authorization & Declaration of Compliance form or a Certificate of Electrical Inspection must also be on display at the work site. The “Job Site” copy of the form must be affixed to the structure receiving the electrical service. This form must b ...
technical specification for isolators
... design for connection to earth terminal. These braids shall have the same short time current carrying capacity as the earth blade. f) The plane of movement and final position of the earth blades shall be such that adequate electrical clearances are obtained from adjacent live parts in the course of ...
... design for connection to earth terminal. These braids shall have the same short time current carrying capacity as the earth blade. f) The plane of movement and final position of the earth blades shall be such that adequate electrical clearances are obtained from adjacent live parts in the course of ...
ES3 Metering Installation Requirements Part A
... As Ausgrid’s standards are subject to ongoing review, the information contained in this document may be amended by Ausgrid at any time. It is possible that conflict may exist between standard documents. In this event, the most recent standard shall prevail. This document has been developed using inf ...
... As Ausgrid’s standards are subject to ongoing review, the information contained in this document may be amended by Ausgrid at any time. It is possible that conflict may exist between standard documents. In this event, the most recent standard shall prevail. This document has been developed using inf ...
technical specification for erection, testing
... certification from State Electrical Inspector, Municipal corporation department, Fire officer, Horticulture department etc. and handing over to the Owner after satisfactory commissioning of complete 66/11 KV substation of BSES Rajdhani Power Ltd. at Fatehpur Beri, New Delhi. The scope includes all m ...
... certification from State Electrical Inspector, Municipal corporation department, Fire officer, Horticulture department etc. and handing over to the Owner after satisfactory commissioning of complete 66/11 KV substation of BSES Rajdhani Power Ltd. at Fatehpur Beri, New Delhi. The scope includes all m ...
DRAFT 0400 Installation Standard
... General. This Agreement is the parties’ entire agreement relating to its subject matter. It supersedes all prior or contemporaneous oral or written communications, proposals, conditions, representations and warranties and prevails over any conflicting or additional terms of any quote, order, acknowl ...
... General. This Agreement is the parties’ entire agreement relating to its subject matter. It supersedes all prior or contemporaneous oral or written communications, proposals, conditions, representations and warranties and prevails over any conflicting or additional terms of any quote, order, acknowl ...
SACE Emax 2
... Circuit-breaker connections and connections between circuitbreaker and switchboard....................................................106 Disassembly operations......................................................107 Cleaning and lubrication of the operating mechanism........109 Inspection of elect ...
... Circuit-breaker connections and connections between circuitbreaker and switchboard....................................................106 Disassembly operations......................................................107 Cleaning and lubrication of the operating mechanism........109 Inspection of elect ...
Rexroth MBS Synchronous Kit Spindle Motors
... compression joints do not cause any stress that could negatively effect the running accuracy of the spindle. They also increase the stiffness of the spindle. With axial clamping, the rotor is centered on the spindle with a clearance, then pressed against the spindle shoulder via a terminal board usi ...
... compression joints do not cause any stress that could negatively effect the running accuracy of the spindle. They also increase the stiffness of the spindle. With axial clamping, the rotor is centered on the spindle with a clearance, then pressed against the spindle shoulder via a terminal board usi ...
Geoelectrical Characterization of Sulphate Rocks Ander Guinea Maysounave
... shape, 2 cm in radius. The thicknesses of the cylinders, measured with a vernier caliper, were around 0.5 cm. The pills with higher gypsum purity are too resistive in order to be measured; thus other thinner pills, 3.5 g in weight, were prepared for the purest gypsum samples (70, 80, 90 and 100% of ...
... shape, 2 cm in radius. The thicknesses of the cylinders, measured with a vernier caliper, were around 0.5 cm. The pills with higher gypsum purity are too resistive in order to be measured; thus other thinner pills, 3.5 g in weight, were prepared for the purest gypsum samples (70, 80, 90 and 100% of ...
Florida Department of Transportation
... 781-3.1.2 Sign Housing: Ensure that the external skin of the DMSsign housing is constructed of aluminum alloy 5052 H32 that is a minimum of 0.125 inch thick. Ensure that the sign housing design and appearance is approved by the Engineer. If cable attachments are used in the sign housing, the cables ...
... 781-3.1.2 Sign Housing: Ensure that the external skin of the DMSsign housing is constructed of aluminum alloy 5052 H32 that is a minimum of 0.125 inch thick. Ensure that the sign housing design and appearance is approved by the Engineer. If cable attachments are used in the sign housing, the cables ...
JEDEC STANDARD
... ESD-protected workstation: A work position with materials and equipment that limit electrostatic potential. ESD-protective packaging: A packaging system that provides electrostatic protection and limits triboelectric charging to levels that do not result in device damage. ESD-protective worksurface: ...
... ESD-protected workstation: A work position with materials and equipment that limit electrostatic potential. ESD-protective packaging: A packaging system that provides electrostatic protection and limits triboelectric charging to levels that do not result in device damage. ESD-protective worksurface: ...
Electricity Service and Installation rules
... for CONNECTION to the ELECTRICITY DISTRIBUTION NETWORK ...
... for CONNECTION to the ELECTRICITY DISTRIBUTION NETWORK ...
MIL STD 883G
... 1.2.1 Provisions for the use of MIL-STD-883 in conjunction with compliant non-JAN devices. When any manufacturer, contractor, subcontractor, or original equipment manufacturer requires or claims a non-JAN part compliant with MIL-STD-883, all provisions of Appendix A of MIL-PRF-38535 are required to ...
... 1.2.1 Provisions for the use of MIL-STD-883 in conjunction with compliant non-JAN devices. When any manufacturer, contractor, subcontractor, or original equipment manufacturer requires or claims a non-JAN part compliant with MIL-STD-883, all provisions of Appendix A of MIL-PRF-38535 are required to ...
SAO-PAS-RS-00001-A - Comisión Nacional de Actividades
... hours at the unit level prior to SAR Instrument/Service platform installation. ID : L2B_SPARD_33 Information: This requirement can be satisfied by: (a) Operating the hardware at ambient temperature, (b) During environmental test or, (c) Sum of operating time at (a) and (b). ID : L2B_SPARD_34 Require ...
... hours at the unit level prior to SAR Instrument/Service platform installation. ID : L2B_SPARD_33 Information: This requirement can be satisfied by: (a) Operating the hardware at ambient temperature, (b) During environmental test or, (c) Sum of operating time at (a) and (b). ID : L2B_SPARD_34 Require ...
Published SFF Committee documentation may be purchased in hard copy or... SFF specifications are available at
... address any issues of general interest and concern to the storage industry. The SFF Committee became a forum for resolving industry issues that are either not addressed by the standards process or need an immediate solution. Those companies which have agreed to support a specification are identified ...
... address any issues of general interest and concern to the storage industry. The SFF Committee became a forum for resolving industry issues that are either not addressed by the standards process or need an immediate solution. Those companies which have agreed to support a specification are identified ...
Florida Department of Transportation
... MIL-I-46058C Military Standard, United States Department of Defense (USDOD). Ensure that any devices used to secure LEDs do not block air flow to the LED leads or block the LED light output at the required viewing angle. Ensure that all components on the LED side of PCBs are black. Ensure that there ...
... MIL-I-46058C Military Standard, United States Department of Defense (USDOD). Ensure that any devices used to secure LEDs do not block air flow to the LED leads or block the LED light output at the required viewing angle. Ensure that all components on the LED side of PCBs are black. Ensure that there ...
Ozone Generator and Ozone PCB Tests and Fault Troubleshooting
... - If the red LED 7 (LD7) on the Ozone PCB “OZB 2000.1” is on, check and if necessary replace the fuse 3 (F3) on the PCB (see figure 1.1 above and figure 3.1 below). Check the fuse holder and confirm that the fuse holder has a tight and good grip on the fuse. Acknowledge the fault in Operation, Fault ...
... - If the red LED 7 (LD7) on the Ozone PCB “OZB 2000.1” is on, check and if necessary replace the fuse 3 (F3) on the PCB (see figure 1.1 above and figure 3.1 below). Check the fuse holder and confirm that the fuse holder has a tight and good grip on the fuse. Acknowledge the fault in Operation, Fault ...
Portable appliance testing
Portable appliance testing (commonly known as ""PAT"", ""PAT Inspection"" or ""PAT Testing"") is the name of a process in the United Kingdom, the Republic of Ireland, New Zealand and Australia by which electrical appliances are routinely checked for safety. The correct term for the whole process is ""in-service inspection & testing of electrical equipment"".Similar procedures exist in other countries, for example, testing of equipment according to DGUV Vorschrift 3 in Germany.Health and safety regulations require that electrical appliances are safe and maintained to prevent harm to workers. Many equipment manufacturers recommend testing at regular intervals to ensure continual safety; the interval between tests depending on both the type of appliance and the environment in which it is to be used. The European Low Voltage Directive governs the manufacture or importation of electrical appliances. Compliance to this has to be declared and indicated by the display of the CE mark on the product. The responsibility for this lies with the manufacturer or the importer and is policed by Trading Standards.Testing equipment has been specifically developed for PAT inspections, based on the testing equipment used by manufacturers to ensure compliance with the British Standard Code of Practice and European product standards relevant to that type of appliance. This in turn allows testing and the interpretation of results to be de-skilled to a large extent. The inspection of the appliances can largely be carried out in-house in many organisations. This can result in cost savings and more flexibility as to exactly when a PAT is carried out.