* Your assessment is very important for improving the workof artificial intelligence, which forms the content of this project
Download `Open Access` in Electricity - Central Electricity Regulatory Commission
Survey
Document related concepts
Transcript
Presentation to Honourable Central Electricity Regulatory Commission on Views/Suggestions on CERCs’ Discussion Paper on Terms and Condition of Tariff November 12, 2003 1 Content • Backdrop for Tariff Fixation • Goals for Tariff Setting • Part I: Broader Issues of Tariff Setting • Part II: Views/Recommendations on Specific Issues • Summary 2 Backdrop for Tariff Setting 3 Capacity Addition Required and past performance • Estimated investment in all sectors: Rs. 900,000 Crs 45000 100% 40000 90% 35000 80% 30000 70% 25000 60% 20000 50% 15000 % Achievement Huge capacity Addition Required to realize the vision of power for all by 2012: 100,000 MW MW • Target Achievement Achievement % 40% 7th Plan 8th Plan 9th Plan • The Achievement % in 9th Plan is lowest for all plans • The need based targets for 8th and 9th Plan were 44,000 MW and 57,735 MW respectively. The Planning Commission reduced the target considering feasibility/resources constraints etc. • The Xth Plan target for utilities is fixed at 41,110 MW. • Considering the status of various projects identified for commissioning in this period, it is unlikely that this target would be achieved, even to a reasonable extent • Accordingly, the shortages are likely to increase substantially 4 Changing Structure GENERATION TRANSMISSION GENCOs CPSU TRANSCO IPPs PGCIL Pvt. Licensees Excess Captive ? Pvt. Utilities TRANSCOs (eg. Delhi Transco) (Intra-State Transmission, Bulk Power Purchase for Licensees) Structure Before Electricity Act- 03 (Post Reforms) DISTRIBUTION CONSUMER Discom 1 (Licensee 1) Licence Area 1 Discom 2 (Licensee 2) Licence Area 2 Discom n (Licensee n) Licence Area n Regulator’s Role No Choice to Generating Co./Consumer, Limited Competition 5 Changing Structure: Emerging Structure: Post EA 03 Generating Companies Own Generation Captive Generation Facilities Transmission Network (Immediate Open Access) Distribution Licensee 1 Distribution Licensee 2 Distribution Network (Gradual Open Access) Own Distribution System Consumers Power Traders would also be involved in some of the transactions Competitive, Flexible Structure enabling Choice to Consumer 6 Goals for Tariff Setting 7 Goals of Tariff Setting • Huge investment required (Rs. 900,000 Crs) to realize the vision of ‘Power for All by 2012’ • Investment in Power Sector to compete for investment in other sectors in terms of – Returns offered – Climate for investment: Stable policies, regulatory and fiscal framework • The policy of allowing an attractive return profile may be adopted for say the next 9-12 years and when the critical mass of investments which can meet the 2012 vision is achieved, Govt. may review it – This has happened in this country as well as abroad whenever Govts want to attract investments in certain sector. • Thus tariff-setting principles need to distinguish between two stages - Stage I is the immediate period for the next 9 – 12 years when large investments would be required to meet the capacity requirements of the sector and Stage II would be the period thereafter. Contd… 8 Goals of Tariff Setting (contd.) • The need for attracting investments in Stage I is more acute compared to Stage II and at the same time more difficult – State of the sector today, from investment point of view, is less favourable due to the various ills affecting the sector. – Conditions likely to improve in the next 9 – 12 years as reforms are accomplished and critical mass is achieved • Case for more favourable returns in Stage I to attract investments. – Normalized returns in Stage II • Even in Stage I, a staggered approach to returns should be followed i.e., keeping in view the immediate need of funds, a higher return should be allowed for the next say 5 year period. The returns may then decrease in subsequent 5 year period and further decrease thereafter. Contd… 9 Goals of Tariff Setting (contd.) • Stable tariff policy framework in various stages and in inter-stages intervals, keeping in account large gestation period of power projects – Clearances have a long lead time (for ex. MoEF clearance itself requires anywhere from 18 – 24 months). • Apart from ensuring the basic function of adequate cost recovery, it should ensure that there is enough revenue generation in the sector itself to partly meet the funds requirement. • Ultimately, tariff setting should aim at helping the sector in its journey of reforms & restructuring and should facilitate the emergence of a financially strong, vibrant, competitive and investor & consumer friendly sector. 10 Part I Tariff Setting: Broader Issue 11 Tariff Setting: Broader Issues • Existing Practice: Cost plus System – Discourages efficiencies • Financials • Technological • Operating – Micro Management • Detailed scrutiny of technology • Technology/Equipment selection vetting – Many time even capacities of sub-systems are analyzed • Highly time consuming, taking lot of Commission's time and resources – Not tuned to changing/dynamic structure • Enhanced participation of private sector players • Faster approvals (tariff etc.) Pressing Need to move away from ‘Cost plus System’ 12 Tariff Setting Across the Chain: Transition Existing: All independently determined Generation Regulated on Cost Plus basis Transmission Regulate d on Cost Plus basis Distribution Regulated on Cost Plus basis Input Power Cost is taken as ‘given input’ Ultimately desired Generation Unregula ted, due to competiti on 1. 2. Transmission Regulate d on Cost Plus Basis Distribution Regulated on Price Cap Managing Input Power Cost is left to Discoms Existing Structure: Takes Time, lacks drivers to improve efficiencies Desired Structure would ‘take time’ to evolve Need for interim Structure to cut down the time and promote efficiencies 13 Tariff Setting: Interim Structure (Generation) Existing Regulated on Cost Plus basis Interim Regulated on Normative Basis Steps Involved (in each case) Steps Involved (one time activity) 1. Cost Scrutiny/approval 2. Financing Plan scrutiny/approval 3. Scrutiny of interest rates 1. Determination of Normative Cost 2. Arriving at Normative Financing Plan 3. Fixing Normative O&M Cost 4. Arriving at Normative Operating parameters Take time and Leads to separate tariff for similar type of projects Faster approval process, uniform tariff for similar projects Promotes efficiencies Interim Structure to realize the Vision and promote efficiency 14 Part II Views/Recommendations on Specific Issues 15 1. Rate of Return: Approach • Views – Tariff setting needs to move from a cost-plus approach to a normative performance based approach. • Cost-Plus approach requires detailed analysis of the different loans, their repayment schedules and other terms & conditions. • It does not provide incentive to utility to lower cost of borrowings as even higher rates are passed through in tariff. – Adoption of a Return on Capital Employed (ROCE) approach would incentivise utilities to adopt more efficient means of financing so as to reduce its cost. • The ROCE may be calculated each year with normative cost of equity, debt and the debt-equity ratio. • Recommendation ROCE Approach to be Adopted 16 2. Rate of Return: ROCE- Cost of Debt • Views – The interest rate may be taken as lending rates for “A” rated borrower (minimum investment grade rating below which Banks/FIs generally do not lend). – This may work out to a spread of 3% to 3.5% over the base PLR, which for simplicity, may be taken as SBI’s Long Term PLR for Infrastructure Projects. • A provision also need to be made for factoring in other costs of raising debtfinance viz. upfront fees, etc. – Generally, lenders stipulate a call option in the loans which entitles them to review the rates of interest at regular period of time after disbursement of the loan (say every 5 years). No corresponding put option to the borrower. – If interest rates in the economy go up, lenders may enhancement of the interest rate applicable to the loan also. require • It would pose significant interest rate risk for the borrower which no borrower is in a position to take. – Accordingly, there should be a provision for a mid-term review of tariff should the interest rates in the economy rise by say more than 3%. • Recommendation SBI PLR + 3.5% (on pre-tax basis), with provision for Mid-Term Review to be Adopted 17 3. Rate of Return: ROCE- Cost of Equity • Views – Pressing need to attract investments in the sector and generate internal resources for huge capacity additions – Returns, adjusted for Risk profile, to be attractive vis-à-vis competitive sectors for investments of the desired amount to flow in. – The returns available to the investors should therefore be the opportunity cost of funds to the investor and not linked to interest rates in the economy. – Against competing investment avenues, a cost of equity lesser than 16% would be definitely unattractive. – In developed economies where there is no acute investment program, returns are linked to interest rates. – Taking 16% as the base minimum ROE required, CAPM model may be used to see if a higher equity return is justifiable. – The higher of ROE derived through the CAPM model and 16% should be used as the cost of equity. • Recommendation ROE of 16% (post-tax) to be continued … at least for Xth and XIth Plan Period 18 4. ROCE- Debt: Equity Ratio • Views – The generally followed a debt-equity norm of 70:30 in the past needs to be relooked in view of changing structure. • From long-term assured off-take arrangements and elaborate payment security structures to liberalized & competitive market place • Less possibility of payment security structures and even if it is, experience of IPPs under operation shows how ineffective they are in actual practice. – This would have the effect of slightly raising the risk profile of the investments. Additionally, the amount of investments required in the sector in the next 8-9 years also has to be seen. – Considering the above, lenders may not be willing to lend at the same 70:30 debt-equity ratio and may insist on a better debt-equity ratio. – Moreover, credit profile of the borrower would also determine the debtequity ratio being offered to him. For a majority of SEBs with poor financial health and a track-record of defaults on debt obligations, lenders may definitely like to insist on better equity cushion. • Having determined these norms and approved tariff based on these norms, Commission should not look into what is the actual debt-equity ratio or the cost of borrowings for the company and the same should be left to the investors. • Recommendation For Calculation of ROCE, Debt:Equity Ratio of 50:50 to be adopted 19 5. ROCE to be fixed or dynamic and fixed every year? • Views – The investment decision is taken based on principles of ROCE allowed at the approval stage – Changing principles of ROCE every year would lead to regulatory etc. uncertainties, which needs to be avoided – If principles of ROCE norms is required to be changed, the revised norm should not be made applicable for fully developed/under construction or operation projects. – In competitively bid project, the tariff offered by the bidder remains the same through the project life irrespective of change in tariff norms thereafter • Recommendation It principles should be fixed for project life 20 6. Tax: ROE to be Pre or Post Tax or increase ROE by 0.5% to avoid pass through of Income Tax? • Views – In order to attract investment in the sector etc. 16% ROE to be on Post Tax Basis. – However, to avoid regular/yearly scrutiny, ROE can be specified on pre tax basis by suitably grossing it by effective tax rate over the project life • Effective Tax rate to be computed by considering Section 80 IA benefit and MAT rate and initial depreciation shield. • At current tax laws, the effective tax rate for a coal based power plant with a life of 25 years is 21.13% and that for a gas based station is 16.41%. – The ROCE would thus need to be enhanced by the above effective tax rates to make it on a pre-tax basis. • To be adjusted for change in law/rate rates • Recommendation ROE to be Post Tax or to make it pre-tax, suitably grossed up to effective tax rate 21 7. Whether Additional Capitalization to be allowed? • Views – Capital costs for stations various type of power plants should be based on laid down norms i.e, a fixed amount for various type of projects and considering the size of plant, economies of scale, etc. Thus for a gas based project, a normative cost of Rs. 3 crores/MW may be approved whereas for a coal based station, Rs. 4 crores per MW may be stipulated as the norm for capital cost. – Once these norms are set, all cost components in tariff should be calculated w.r.t. these norms and there should be no linkage with the actual capital cost of the plant. – All cost over-runs/savings w.r.t. this normative cost should be to the account of the developer • Recommendation Provision for mid-term review, if during construction stage, there is significant variation in tax laws impacting project cost 22 8. Rate Base to be from assets side or liability side? • Views – The calculation of rate base should ensure that the tariff allows a return component which covers both ROE as well as interest cost of debt. – There are various options for calculating the rate base from the asset side & liability side. – The most prudent option would be one which allows flexibility to the developer, adequately covers his returns & interest cost of debt and at the same time does not lead to a sharp increase in retail tariffs. – As suggested earlier, Normative Approach should be adopted in this case also. – The rate base, should take into account its reduction due to repayment of loan etc. • Recommendation 1. Initial Rate Base Should be Normative Capital Cost 2. This may be decreased by 5% p.a., up to 50% of original, in view of debt-equity ratio of 50:50 23 9. Basis of Capital Cost: Normative or Actual • Views – Taking actual cost as on COD would lead to different tariffs for similar projects – Further, it would increase the steps required to fix the tariffs • Recommendations 1. It should be on normative basis (due consideration to type of project, technology, economies of scale etc.) 2. There should be provision for mid-term review to account for any change in law/tax rates 24 10. Treatment of Initial Spares in Project Cost • Views – In the existing tariff-setting methodology, initial spares are included as a part of the project cost. – Further, there calculation of is a linkage maintenance between spares initial for spares working and capital purposes) • Recommendations 1. Existing practice of including cost of initial spares in project cost to be continued. Normative project cost to be suitably adjusted for initial spares 2. There should not be any linkage between initial spares and calculation of maintenance spares 25 11. Foreign Exchange Variation • Views – In a normative based tariff setting methodology, actual mode and mix of financing would not be of any issue • Developer to optimize the financing package • Recommendation In view of suggestion for normative parameters for tariff fixation and return on ROCE, this issue does not arise 26 12. Working Capital Issues • Views – Existing norms are based on prudent principles and well accepted – Giving Interest on Working Capital along with ROCE would lead to its under recovery due to reduction in capital base over the period – Interest rate needs to be uniform (charged to “A” rated borrower) • Recommendations 1. Existing Norms to be retained 2. Interest on Work. Cap to be separate component of tariff 3. Interest Rate to be SBI PLR + 3% 27 13. O&M Expenses (Normative/Actual? & escalation) • Views – O&M cost should be on a normative basis as a given percentage of the normative project cost. – Linking O&M expenses to actual project cost/expenses leads to wide variation for similar type of projects. – The actual O&M expenses (including Insurance) are found be more than allowed in existing norms, particularly for gas based projects. – As regards year-on-year escalation factor, a suitable weighted average of WPI and CPI may be used (say 60% WPI and 40% CPI). • Recommendation O&M expenses (first year) allowed should be 4.25% for Gas Stations and 3% for Coal Stations of Normative Project Cost 28 14. Depreciation Rate • Views – Depreciation does not serve the purpose of loan repayment only. It also serves to generate additional resources which can be used for future creation of capacity. – Realizing this, Govt. of India had also increased rates of depreciation in March, 1994. – However, in a normative ROCE model, linking of depreciation rates to loan repayment exactly may not also be possible as there is no concept of actual equity or debt separation in the capital base. • Recommendation Retain Depreciation Rates as notified by MOP in 1994 (7.84% for coal & 8.24% for gas stations, at least for Xth and XIth Plan period 29 15. Depreciation – Other Issues • Views – The calculation of depreciation amount every year should be done on the basis of historic normative project cost (Not on economic/replacement cost). – Further, sector needs huge investment for capacity addition. – Internal resource is key source of investment financing • Recommendation Depreciation to be calculated on normative cost and should generate some surplus (over loan repayment) for further investment 30 16. Operational Norms for Thermal Stations • Views – The fixation of operational norms (station heat rate, secondary fuel consumption and auxiliary consumption) should take into account the relative performance of a wide cross-section of utilities in the country from both central & state sector as well as the private sector so that the norms are achievable by all utilities which put in reasonably efficient efforts. – The norms so fixed should also act as reasonable benchmarks for utilities to improve whose performance is below the norms. – The existing practice of comparing norms against actuals and allowing the lower of the two discourages efficiency improvement measures. – During stabilization period, norms should be relaxed. • Recommendation Norms to be based on performance of wide-section of utilities and tariff to be based on normative parameters only 31 17. Norms for Target Availability • Views – The norms should take into account the relative performance of a wide cross-section of utilities. – The average operating PLF/availability for all generating stations put together in the country stands at about 72%, against stipulated norm of 80%. • Wide-gap between the norms and the actual ground level performance – The norms for target availability should thus be fixed at the national average plus say 2%-3%. – Alternatively, if the threshold availability level is being raised to 80%, then the ROE should also be enhanced from 16% suitably to reflect the higher risk carried by the project company. • Recommendation Target Availability should be 75% for recovery of fixed charges including ROE @ 16% 32 18. Incentive (Linked to availability or PLF? ) • Views – PLF depends on despatch of the plant, which is dictated by customer beneficiaries and not the developer – Maintaining high availability is important for grid stability and should be rewarded – Further, linking of incentives to PLF has a number of other shortcomings. • ‘Non-merit’ operation of grid • Recommendation Incentive should be linked to Availability 33 19. Development Surcharge • Views – Development Surcharge was allowed in tariff to central sector utilities as a means of gathering surplus funds for future capacity additions. – In a competitive market place, there is no reason why Govt. owned utilities should derive an advantage of securing cashflows for future investments by way of statutory levies/surcharge. – If the Govt. so desires, the funds required for setting up new capacity should be given by way of planned budgetary allocations rather than collect the same by way of a surcharge. – The surplus funds for future capacity addition can be generated through a higher rate of depreciation etc. which would then be uniformly available to all utilities and not to central sector utilities only. • Recommendation Development Surcharge should not be specific to fund investment program of Central Generating Stations 34 Transition Period Support – Need for Cess/Surcharge • Distribution Sector: Transition Phase – Need for Support – Low retail tariff elasticity – Need to keep retail tariffs affordable for all consumer categories – This may be ensured by • Reducing losses • Tariff rationalization • Operational/organizational efficiency improvement – However, these measures would take time – During this period sustainability of the utility to be ensured – Therefore support required to bridge the gap – Actual tariff minus regulated tariff • Most State Govts do not have resources to bridge this gap – major constraint to distribution privatization & reforms • CERC requested to recommend to Central Govt. to levy a cess on all power sold in the country to meet transitional period support • Surcharge Collection to be administered by the Excise Machinery. 35 Transition Phase – Need for Support (contd.) Subsidy Amount Revenue Gap – Govt. Support ? Without reforms – perpetual drain on Govt. resources With reforms Period Transition Period Reforms to release Govt. funds for priority sectors 36 20. Tariff Norms Review Period • Views – Tariff policy framework should be stable enough for a reasonable period of time • keeping in view the development period of projects – However, periodic review is necessary • Changes in cost levels in economy, technology, equipment prices – Revised norms to be applicable for new projects only • For fully developed/set-up projects, tariff principles once set, should continue for the entire life of the plant. – The investment decision and financing is based on prevalent norms – The apprehension of customers that escalation component (viz. O&M cost) may become very high compared to actuals can be taken care of better by suitably determining the escalation factor with weights linked to various indices of costs in the economy. • Recommendation Tariff norms may be reviewed once in 5 years, to be applicable for new projects only. No change for fully developed/operating projects 37 21. Regional Tariff (i.e. Pooled Tariff for CPSU) • Views – The need for pooled generation tariffs is not clear. – Generation tariffs should be on station-wise basis and not pooled basis. – Pooled tariff concept is generally applicable for distribution utilities when they procure bulk power and not for generation companies. – The pooled tariff concept for generating companies can work specifically in a short-term/spot sales scenario. – In case of long-term contracts, it would become very difficult to implement a provision whereby tariff gets upwardly revised every time a new incremental capacity is set up. • Recommendation Tariffs should be stationwise 38 22. Peak/Off Peak Tariff in Bulk Generation • Views (whether should be introduced?) – The concept is in the right direction. • Compels distribution companies to manage load curves in a more efficient manner • Ensures higher availability of generating capacity during peak hours • reduce congestion on transmission lines to some extent – However for it to be really effective, differential tariffs based on time of day etc. should also be implemented at the downstream level i.e., transmission & distribution business. – If this is not the case, the distribution licensee/supplier would end up getting squeezed by the higher peak bulk tariff rates which he would not be able to pass to the retail consumers. – There should be a clear road-map metering/retail tariff fixing, etc. for appropriate TOD • Recommendation Differential Tariffs should be introduced 39 23. Declared Capacity & Auxiliary Consumption • Views/Basis for Recommendation – Existing definitions are well accepted and understood in the Sector • Recommendation No need to change the definitions 40 Goals for Tariff Setting: Other Issues 41 Need for Intra State ABT • Currently applicable only to Central sector generators and beneficiaries who are directly connected to and are a player on the regional grids (Inter State only). – The advantages not being completely utilized by the entire power sector • On the intra-state level, a significant surplus capacity exists with various generating companies & CPPs which at present is not being optimally utilized. • Moreover, a number of state generating stations still have single part tariff, which is not in line with merit order regime. Such generating stations would be asked to back down even though on a variable-cost based merit order system they would have been fully dispatched. • It is also necessary that the distribution utilities become more accountable in their load management processes by assessing consumer demand more accurately and planning their load shedding schedules judiciously. 42 Need for Intra State ABT • Unbundling of SEBs would increase no. of players managing the load in the system. • Unless a mechanism is put into place at the intra-state level to cover these distribution companies also under ABT, the loop would not be closed and the actual implementation of ABT would not be complete. • Thus, implementation of ABT at the intra-state level would free up idle generating capacity leading to meeting of more consumer demand, ensure better load management by the distribution companies, boost bilateral trading, etc. • ABT with a self contained discipline mechanism would enable better and reliable grid operations 43 Advantages of Intra State ABT • The experience of implementing ABT in the country till date has shows following major advantages: – The UI charge in ABT results in better grid discipline and grid security by limiting grid frequency excursions within a manageable range. – Improvement in grid voltage levels leading to reduction in transmission losses and enhancement of transmission capacity. – Maximization of generation during peak-hours and backing down of generation during off-peak hours as per merit order. ABT facilitates Merit Order Dispatch as the fixed cost payable based on capacity allocated becomes a sunk cost and dispatch of plants is based on variable costs. – The two-part tariff concept of ABT presents an inherent platform for bilateral trading. – Improvement in performance of power plants by reducing trippings and long term damage. – Improvement in commercial dealings with reduction in year-end adhoc adjustments and consequent disputes. 44 Summary 45 Summary: Tariff Setting Goals • Tariff setting to take into account changing structure of power sector • It should lead to faster approval process – Normative cost etc. approach • It should promote efficiencies 46 Thank you 47