Status of the Nuclotron-NICA
G.Trubnikov
MAC, June 7, 2011
1
1/15
Nuclotron Run 43
21 February - 22 March 2011
KVINTA : 70 hours
Gamma-3: 24 hours
(Belarus, Poland, Czech, Greece, Germany, Bolgaria)
MPD-STRELA (MRPCfor MPD): 72 hours
(Russia, China, Germany)
Delta-LNS: 67 hours
(Russia)
FAZA: 52 hours
(JINR, ITEP)
NIS-GIBS: 10 hours
(JINR)
MPD-STRELA
2
2/15
Nuclotron-M Results
Magnetic field, T
Beam intensity, particles
Estimation of the average vaccum in the Nuclotron ring
measuring circulating deutron beam lifetime at Е=5 MeV/u
corresponds to the vacuum pressure not worse than 4*10-10 Тоrr.
2/15
Nuclotron Run 43
21 February - 22 March 2011
New digital system for on-line beam orbit measurment
Beam signal amplitude evolution from pick-ups (Acceleration. Field rising from 300 to 1000 Gs)
4
3/15
Nuclotron-M Results
4.5÷ 5·1010 (d) at 300 MeV/u
For the first time at
Nuclotron had been
performed
beam slow extraction
3,1 GeV/u
4/15
Nuclotron Run 43
21 February - 22 March 2011
Automatic beam orbit correction system (kit of 28 correctors)
MCP detector
for residual gas
ions
registration
Beam profile evolution
at acceleration
(transverse and
longitudinal)
6/15
Nuclotron-M Results
First 6 turns (about 50 s), deutron beam after orbit correction. Blue injected beam, Red - signal from pick-up.
Circulating beam signals during 1150 ms. Small increasing of the signal
amplitude is connected to beam de-bunching
7
7/15
Nuclotron-M Results
Full-scale reconstruction of the power supply system for whole complex !
8/15
Nuclotron-M Results
9/15
Nuclotron-NICA
foreinjector
Cascade transformer
up to 0,7 MeV
10/15
Nuclotron-NICA
Heavy Ion Source KRION-6T
Assembling of electron/ion optics system:
view from the “ion extraction” side.
Superconducting test coil (L=19 cm, 32
layers of SC wire) : preparation for
testing in a liquid helium.
Magnetic field (T) versus current (A) for SC
solenoids; experimental and expected data.
1) 26 layers (green line, 21 Jan.’11) – 7.41T at
I_crit.=131 A (experimental data);
2) 32 layers (top green line, 25 Apr.’11) – 7.81T at
I_crit=114 A (experimental data);
3) red line: critical current for SC wire according it’s
manufacturer data;
4) blue line: expected for Krion-6T ESIS – 22 layers,
L=120 cm, B=6 T at I_working=118 A . Should be
ready in September 2011.
11/15
Nuclotron-NICA
Source of polarized particles (p, d, H) JINR+INR RAS
We plan to assemble and
TEST SPP at Nuclotron with
d in the end of 2012
12/15
Nuclotron-NICA
Stochastic cooling system prototype at Nuclotron
Vacuum chamber for pick-up
Vacuum chamber for kicker
Slot-coupler structures,
manufactured at IKP FZJ
We plan to assemble and TEST stochastic cooling
system prototype at Nuclotron in the end of 2011
(everything will depend on electronics delivery)
RF ON (h=1), Buncher ON
RF OFF, Buncher OFF
RF ON (h=10), Buncher ON
13/15
Nuclotron-NICA
Moreover:
- dedicated test bench for injection system (inflector plates)
into Booster is in operation;
- dedicated prototype of HV platform (PS 225kV/3A) is under assembly;
- new system of the whole complex synchronization is under design
and construction;
- new thermometry and quench detection system for Nuclotron is in progress;
-…
PLANS:
Next run at Nuclotron with prolonged period (1,5-2 months) is planned
for November-December 2011 and beam will be delivered mainly for physicists.
14/15
Thank you for your attention