Survey
* Your assessment is very important for improving the workof artificial intelligence, which forms the content of this project
* Your assessment is very important for improving the workof artificial intelligence, which forms the content of this project
Construction Research Congress 2014 ©ASCE 2014 A Mathematical Structure for Modeling Uncertainty in Cost, Schedule, and Escalation Factor in a Portfolio of Projects Ali TOURAN, Ph.D., P.E., F. ASCE1 1 Professor, Northeastern University, Department of Civil and Environmental Engineering, 400SN, 360 Huntington Avenue, Boston, MA 02115. Phone: (617) 3735508; Fax: (617) 373-4419; email: [email protected] ABSTRACT The past decade has witnessed a surge in the application of formal probabilistic risk assessment on cost, schedule, or both in major capital projects. Depending on the level of detailed information required the sophistication of risk assessment approach ranges from simply considering some important variables to fully integrated cost/schedule risk models. The most common modeling approach is to model cost components as random variables and calculate total cost distribution. For projects or portfolios spanning several years, the effect of cost escalation on budget is profound. Because of this, the variability of the escalation factor should be considered in the conduct of the risk assessment. This paper provides a mathematical framework for modeling of cost uncertainty in a portfolio of large infrastructure projects with a multi-year duration. This framework considers the randomness of cost and escalation factor at the project level. Relevant equations are presented that consider various degrees of probabilistic modeling from basic to complex. The paper can be used for understanding major drivers of uncertainty in portfolio budget and to evaluate the effect of escalation variability on project costs. The concepts and the suggested approach are explained using a numerical example. INTRODUCTION This paper provides an overview of a mathematical framework for modeling of uncertainty in a portfolio of projects. A portfolio is defined as a collection of multiple projects managed by a single management team or organization. The projects can be interrelated and part of a program, or independent from each other but under the supervision of a single organization. The proposed overview is intended for large infrastructure portfolios (such as transportation) where project development can take several years. Under this scenario, the uncertainty may be considered and modeled in three areas: cost, schedule, and escalation factor. Table 1 gives an overview of probabilistic modeling of these three factors. Table 1. Various modeling levels for probabilistic estimating Factors modeled as General approach and input needed random variables (1) Cost, schedule, escalation factor Joint density function of the three variables; or marginals and correlations (2) Cost, schedule Joints density function of the two variables; or 1743 Construction Research Congress 2014 ©ASCE 2014 marginals and correlations (3) Cost, esc. factor Joints density function of the two variables; or marginals and correlations (4) Cost Distribution of cost components (5) Schedule Distribution of schedule elements or activities In the most general case, cost, schedule, and escalation factor are all modeled as random variables (Case (1) in Table 1). Because there is interaction between the values of these variables, the only way to model these correctly is to develop the joint density for these variables, something that is not achievable under general conditions and given the limited available data. With some simplifying assumptions, a multinormal distribution can be considered for modeling the factors however, correlations among these variables would be required. In Case (2) the problem is somewhat simpler but still the joint density function of cost and schedule is not necessarily obtainable. The cost and duration variability is quite interactive; longer delays increase the cost, and larger overruns are usually an indication of project delays. Simpler approaches can be used where the cost can be modeled as the sum of direct and indirect costs and then assumed that indirect costs are a linear function of duration. From there, distributions of total cost given various durations could be obtained. Another common simplification is to ignore the correlation among these variables and model these as independent random variables. Case (3) considers the randomness of cost and the escalation factor. The current paper treats this case under the special condition that cost and escalation factor are assumed to be independent. The last two cases are the traditional cases of probabilistic cost estimating and probabilistic scheduling (for example PERT). Each of these cases would need to be aggregated at the portfolio level when dealing with multiple projects. In this paper, the effect of cost escalation will be explicitly considered because in large construction programs that span several years, cost escalation can be a major source of uncertainty. In this paper, distributions of cost and escalation factor are assumed to be statistically independent. Cost estimate components are costs of materials and labor at present time given a specified scope of work. The uncertainty in cost is a function of variations in this scope and the increase in labor and material costs due to inflation. Escalation factor measures the movement of material and labor costs in the future. In order to assure the separation of these two elements, the process of risk assessment should consider risk factors such as productivity issues, ground conditions, probability of permits and funding approvals for cost risk analysis. The risks associated with labor rates and material prices should not be considered when identifying cost risk factors. These risks will be considered when modeling escalation factor as a random variable. This way the distribution of cost and escalation factor will remain more or less independent. Figure 1 below shows the components of the construction portfolio. The portfolio consists of n projects each with an estimated construction phase duration of di and an estimated cost of Ci. Ci is the current dollar estimate for Project i. In other words, the estimates are in terms of Year 0 (current) dollars. In the most general case, 1744 Construction Research Congress 2014 ©ASCE 2014 1745 both the durations and costs are modeled as random variables represented by appropriate probability distributions. In this paper, the project cost Ci is assumed to follow a normal distribution and variance (Eq. 1). The project cost is the sum of a number of with mean cost items and the assumption of independent cost components will result in a normal distribution for the total project cost. (1) Also, the time of start of each project is si . ti = si + di/2 (2) ti is the time to the midpoint of project i. In order to consider the effect of escalation, an escalation factor r should be considered. Two cases are assumed: (1) r is a fixed value, and (2) r is a random variable. For the second case, r is modeled as a normal random variable (Touran and Lopez 2005). Mean and standard deviation of rj or escalation factor for period j can be calculated from historical data. These are represented with and in Eq. 3. C1 C2 Projects C3 d3 Cn s3 Time t3 = s3 + d3/2 Figure 1. Portfolio of projects (3) With the above definitions, we can calculate the cost of project i in the year of expenditure (YOE), Ci YOE. Note that each project has a distribution of expenditure which is assumed to be known (Fig. 2). So the current estimate would be: Construction Research Congress 2014 ©ASCE 2014 1746 (4) In Eq (4), the planned expenditure in current dollars for project i for year j of that project is Cij. It is assumed that the expenditure for each year occurs at the start of the year to simplify the calculations. di Cost 2 ci3 ci ci1 cidi Si Time Figure 2. Project planned expenditures (in current dollars) ESCALATED PROJECT COST Escalated project cost for a project as depicted in Fig. (2) will be: (5) In Eq (5), r can be modeled as a fixed value or a random variable. Much work has been done to characterize the shape of the cumulative expenditure curve (S-curve) on construction projects (Perry 1970; Drake 1978; Peer 1982; Miskawi 1989; Bhurisith 2000; Touran et al 2004). Based on research by Bhurisith (2000), it is suggested to use a Beta distribution with shape factors α = 1.70 and β = 1.85 for modeling project expenditure. The beta distribution is presented in Eq (6): a<x<b (6) where B is the beta function, and the start and end point for the duration is a and b, respectively (Ang and Tang 2007). Figure (3) shows a beta distribution with a = 0, b = 1, α = 1.70, and β = 1.85. Construction Research Congress 2014 ©ASCE 2014 1747 f(x) x Figure 3. Beta Distribution with a=0, b=1, α=1.70 and β=1.85 So for example, in a 4-yr project in Fig (3), Ci1would represent the area under the curve between 0 and 0.25, Ci2 would represent the area under the curve between 0.25 and 0.50, and so on. For year j of a project’s duration, and assuming that the beta curve starts at 0, the expenditure can be estimated using Eq.(7): (7) Using Eqs (5) and (7), can be calculated. Note that if any other distribution is deemed superior to what is suggested here, the process of substituting the cost will be similar to what was described. distribution and calculating Midpoint of Project Approach One common approach for simplifying the calculations is to assume that all project expenditures are expensed at the midpoint of the project. This is a common industry practice and will not result in errors as long as project cost expenditures are symmetrical with respect to its midpoint. However, when one is considering uncertainties and using a probabilistic approach, the midpoint of project approach will result in an underestimation of total cost variance. Fixed Escalation Factor If escalation factor is assumed to be a fixed value r, then total project cost expressed in the year of expenditure dollars will be: (8) Construction Research Congress 2014 ©ASCE 2014 1748 Escalation Factor as a Random Variable If escalation factor is modeled as a random variable, then it will be different for different periods and the total project cost expressed in YOE dollars will be: (9) In the above equation, si is the period of the start of project i. If the mid-year of can be calculated from Eq. (10). expenditure approach is used, (10) As was discussed at the beginning of the paper, a normal distribution is used for modeling escalation factor (Eq 3). Furthermore, it is assumed that values of escalation factors are independent of each other in various years. This approach has proved more accurate compared to the approach that incorporated correlations between consecutive periods. Zhang (2013) verified that the correlation coefficient among the escalation rates calculated based on ENR index values was small among consecutive years. Also Zhang (2013) verified that using the independence assumption between values of cost escalation in consecutive years resulted in better accuracy compared to the case where autocorrelations were considered among consecutive years. is the product of several normal Referring to Eq (10), one can see that random variables and so it should follow a lognormal distribution. However, because of the shear magnitude of compared to other multipliers (i.e., (1+rj)’s) , the distribution of remains close to normal. The parameters (mean and variance) of this lognormal distribution can be calculated from Eqs (11) and (12), as long as ti is assumed to be deterministic. Also, the assumption is that all the random variables involved are independent. Construction Research Congress 2014 ©ASCE 2014 TOTAL PORTFOLIO COST Having calculated various using Eq. (13). 1749 , one can calculate total program cost, CYOE (13) will be very close to From Eq (13), one can conclude that the distribution of normal as long as the number of projects in the portfolio is sufficiently large and the correlation among various project costs can be neglected. It should be noted that the assumption of independence among project costs is not conservative. This assumption would be more accurate if the portfolio consists of projects that are in different geographical regions. It is evident that in the proposed framework, the randomness of costs and the escalation factor all play a role in the randomness of the total program cost, . NUMERICAL EXAMPLE In this hypothetical example, it is assumed that durations are fixed and costs and escalation factor are modeled as random variables. The portfolio consists of four projects as depicted in Figure 4. 1 2 3 4 5 6 7 Year 8 9 10 11 12 13 Cost / Budget Project 1 $100,000,000 Project 2 50,000,000 Project 3 $80,000,000 Project 4 $60,000,000 Figure 4. Portfolio barchart Project statistics are given in Table 2. Current portfolio total is $290M. The first project is scheduled to start one year from today and total duration for the four projects is 11 years. The escalated project cost is $351,632,000. Project costs follow a normal distribution with standard deviations equal to 20% of their means. These distributions are generally obtainable by conducting risk assessment on each project, identifying the risk factors, and summing up these risk factors to arrive at these distributions (Molenaar et al 2010). In the risk register, risks associated with labor and material cost variations are not included because those risks are captured through the distribution for escalation factor. The escalation factor follows a normal distribution with a mean of 3% per year and a standard deviation of 1.5%. The midpoint of construction approach has been used for calculation of CYOE. Values of Column (4) are calculated using Eq. (11) and values of Column (5) are calculated 14 15 Construction Research Congress 2014 ©ASCE 2014 1750 using Eq. (12). Total cost distribution is close to a normal distribution with the calculated mean and standard deviations. As a matter of validating the analysis, the process is simulated and simulation results are shown in Column (6). Table 2. Comparison of simulated vs calculated results Project Mean of Ci Std Dev of Ci Mean of CiYOE (1) (2) (3) (4) 1 $100,000,00 0 $20,000,00 0 2 $50,000,000 3 Calculate d Std Dev of CiYOE Simulated Std Dev of CiYOE (5) (6) $109,272,70 0 $22,034,602 $22,022,66 5 $10,000,00 0 $56,275,441 $11,378,575 $11,351,69 6 $80,000,000 $16,000,00 0 $101,341,60 7 $20,710,875 $20,774,98 5 4 $60,000,000 $12,000,00 0 $83,054,032 $17,107,682 $17,085,97 2 TOTA L $290,000,00 0 $351,632,00 0 $36,559,660 Figure 5. Results of simulation analysis for total portfolio costs Figure 5 shows the total cost distribution obtained through simulation. If the escalation factor had been modeled as a fixed value, then the total mean would have remained the same. The variance for the case of deterministic escalation factor would Construction Research Congress 2014 ©ASCE 2014 be smaller and could be calculated by summing project variances; total standard deviation for this case would have been $36,038,000. SUMMARY This paper provided an overview of modeling options for treating uncertainty in project portfolio cost, schedule, and escalation. It provided a practical solution to the case of probabilistic modeling of project cost and escalation factor. A numerical example was used to demonstrate the approach, and the accuracy of the analytical approach was verified by simulation. REFERENCES Ang, A. H-S., and W. H. Tang. (2007). Probability Concepts in Engineering. 2nd Ed., John Wiley and Sons, New York, NY. Bhurisith, I. (2000). "A cash flow model for construction project financing." MS thesis, Northeastern Univ., Boston. Drake B. E. (1978). "A mathematical model for expenditure forecasting post contract." Proc., CIB W-65 Symp. on Organization and Management of Construction, Haifa, Israel, 11-163-11-183. Miskawi, Z. (1989). "An S-curve equation for project control." Constr. Manage. Econom., 7, 115-124. Molenaar, K., S. Anderson, and C. Schexnayder. (2010). “Guidebook on risk analysis tools and management practices to control transportation project costs.” NCHRP Report 658, Transportation Research Board, Washington, D.C. Peer, S. ( 1982). "Application of cost-flow forecasting models." J. Constr. Div., ASCE, 108(2),226-232. Perry, W. W. (1970). "Automation in estimating contractor earnings." Mil. Eng., 410, 393-395. Touran, A. and R. Lopez. (2006). “Modeling Cost Escalation in Large Infrastructure Projects.” J. of Construction Engrg. & Manangement, ASCE, 132 (8), 853-860. Touran, A., M. Atgun, and I. Bhurisith.(2004). “Analysis of the U.S. Department of Transportation Prompt Pay Provisions.” J. of Construction Engrg. & Manangement, ASCE, 130 (5), 719-725. Zhang, Y.(2013). “A Portfolio Management Decision Support System for Transit Projects,” Dissertation submitted to the Dept. of Civil & Env. Engrg., Northeastern University in partial fulfillment for the requirements of the PhD, Boston, Massachusetts, August. 1751