* Your assessment is very important for improving the workof artificial intelligence, which forms the content of this project
Download Influence of increased wind energy infeed on the transmission network
Mains electricity wikipedia , lookup
Grid energy storage wikipedia , lookup
Electric power system wikipedia , lookup
Electrification wikipedia , lookup
Transmission line loudspeaker wikipedia , lookup
Telecommunications engineering wikipedia , lookup
Alternating current wikipedia , lookup
Electrical substation wikipedia , lookup
Electric power transmission wikipedia , lookup
Wind turbine wikipedia , lookup
Amtrak's 25 Hz traction power system wikipedia , lookup
Life-cycle greenhouse-gas emissions of energy sources wikipedia , lookup
Power engineering wikipedia , lookup
C6-107 21, rue d'Artois, F-75008 Paris http://www.cigre.org Session 2004 © CIGRÉ Influence of Increased Wind Energy Infeed on the Transmission Network Yvonne Sassnick, Matthias Luther, Ronald Voelzke* Vattenfall Europe Transmission GmbH, E.ON Netz GmbH, Siemens AG 1. Introduction Legislation passed in April 2000 and governing the infeed of regenerative energy compels network operators to link up to all the renewable generating sources and to purchase all the power generated for a specified infeed remuneration. Since this law came into force, in Germany there has been a notable increase in the proportion of power generated from renewable sources, particularly wind energy. Figures for late 2002 show a total installed wind power of about 12,000 MW, with a maximum load capacity in Germany of 80,000 MW. 50% of this installed wind power is placed in the Transmission System of E.ON Netz and 35% is placed in the Transmission System of Vattenfall Europe Transmission. Further expansion (especially in offshore regions) up to a figure of 25,000 MW by the year 2030 is planned. Nearly all these generating units provide their infeed in an unregulated manner, depending on available wind and regardless of network load. In Figure 1-1 to 1-3 the expected development of wind energy in Germany is drafted– On-Shore and Offshore- especially with the development in the E.ON Netz and the Vattenfall Europe Transmission system. Installierte Leistung / Installed Capacity, MW 50.000 45.000 40.000 Onshore and Offshore 35.000 30.000 25.000 20.000 Onshore 15.000 10.000 5.000 0 1990 1995 2000 2005 2010 2015 2020 2025 2030 Jahr / Year Figure 1-1: Development of wind energy in Germany *[email protected] 1 Figure 1-2: Planned development of offshore wind farms in the North Sea Figure 1-3: Planned development of offshore wind farms in the Baltic Sea By its very nature, wind energy infeed is stochastic and difficult to foretell. Wind predictions are based on weather forecasts and depend therefore on the accuracy of the latter. This means that load forecasts are subject to uncertainty spans of up to 15% on average. Additional reserve capacity must therefore be provided. As a result of unbundling (specified in the EU Directive of 1996, which was fully implemented in Germany), transmission network operators no longer possess their own generating plants and have therefore to purchase their power on the market. The absolute priority attached to renewable energies is detrimental to generation from conventional power stations. Particularly in periods of low demand, in conjunction with strong wind, there is a lack of controlling power in the network, owing to the low proportion of conventional generation. This calls for controllability of power generation. It is important to arrive at an optimal balance, in both economic and technological terms, between controlled wind energy infeed and the supply provided by conventional power plants. It is mainly northern Germany where wind energy is making progress. This region has hitherto accounted for relatively low electricity demand, with the result that the transmission network is not as substantial as elsewhere. The planned construction of more offshore wind farms in the North and Baltic Seas will lead to increasingly frequent bottlenecks in the transmission network in a north-south direction. Intensified use of wind energy will therefore necessitate improvements to the transmission network. Extension of wind energy requires a correponding extension of the grid. Network access regulations equivalent to those for conventional power stations have to be applied in future to wind farms with power infeed into the HV grid, too. This means for example that in the event of a short circuit near the point of common coupling a wind farm must, up to a fault duration of 150 ms, remain stable and connected to the network. Most of today’s wind generator types are not capable of this behaviour. Suitable models of wind generators must therefore be developed, allowing an examination of the dynamics of such units, and with the aid of which the requirements imposed on the network (especially the power electronics) can be derived. Linking up large offshore wind farms to public networks over long distances is a complex technological challenge. This paper presents suitable basic concepts in the form of AC or DC solutions; the technological and economic contextual conditions are discussed. The political activities concerning the promotion of wind energy must not overlook the fundamental technical problems; these can only be solved by the joint efforts of all concerned (e.g. wind generator manufacturers, wind farm operators, network operators and their associations). A number of studies are under way. The intention is to derive basic technological recommendations, thereby arriving at a consensus among all parties. 2 2. Effects of increased wind power generation on system planning and grid operation Power infeed by wind power producers (WPP) is fundamentally subject to different patterns than are the cases with conventional power sources such as thermal, gas turbine or hydroelectric generating plants. Assuming a general availability of the conventional plants themselves, the power to be generated can be planned exactly and can be fed in at the required time. The situation with wind power stations is different. In most cases the wind velocities in northern Germany, but also over the Baltic or North Sea, are mostly within the range of 3 to 12 m/sec. Within this range, the power produced by a wind generator depends very considerably on the wind velocity (Figure 2-1). Thus, planning the operation of a transmission network depends substantially on the precision of the weather forecasts, quite particularly if the share of the wind power generation accounts for a significant portion of the network load. One further major factor is that German legislation on renewable energy does not impose any obligations on wind farm operators to feed in a certain amount of power. They basically feed in the maximum possible power obtainable from the wind and they receive a maximum payment. It is the transmission network operator’s responsibility to gauge the coming infeed on the basis of the weather forecast. Vattenfall Europe Transmission’s grid covers an area of about 100,000km2, with a maximum load of around 10,000 MW. By the end of 2002, the wind power output installed amounted to 4,200 MW. A further 5,000 MW of onshore wind power and 1,500 MW of offshore wind power are to be added by the year 2010. Figure2-1: Average power output Figure2-2: Forecast, correction and actual output At present, the wind power to be fed in is planned on the basis of a preview compiled on the previous day in the period up to 9:00 a.m. On the actual day, a correction is then incorporated by 4:00 a.m. on the basis of the updated weather forecasts. Unfortunately, in many cases the actual profile of the power output figures for all wind generators feeding into the grid deviates considerably. Figure 2-2 shows this with reference to the example of January 30, 2003. As a result the transmission system network operators are obliged by law to take receipt of and pay for all the renewable energy (mainly wind energy) generated in the accounting grid. By contrast, transmission network operators can sell parts of the renewable energy vertically to their subordinate networks (as a monthly band) or horizontally to neighbouring transmission networks as a daily band in accordance with the forecast. These sales can be referred to as refined energy because they are no longer subject to stochastic fluctuations. Forecast generation is balanced out over delivery bands by means of electricity trading. As the actual generation of wind energy never tallies with the forecast, further deviations must be balanced out by the transmission network operator. As the wind power infeed increases, the transmission capacity of the network is a further problem. Most WPPs are connected in relatively low loaded regions. The transmission networks in these regions have been expanded to only a limited extend. Appropriate transmission capacities must be created in order for the power to reach the load centres. 3 Moreover, existing conventional power stations will be offering their generating capacity on the free market, selling it throughout Germany or Europe. Consequently, free energy trading is suffering increasing constriction owing to a lack of transmission capacity. This is why transmission capacities must be expanded. According to calculations orderd by VE Transmission, additional 400 kV overhead lines over a distance of about 500 km are needed for this purpose in the network area of VE Transmission till 2011. Considering the usual length of time required for approval processes, it is to be feared that network capacity will not keep up with wind power expansion, which has been assigned priority. Besides network expansion expenditure, there are additional costs due to dramatic rise in compensating power caused by inexact forecasts; there costs greatly those of network expansion – Figure 2-3. Figure2-3: Expected extra costs for grid extension Studies for E.ON Netz have shown that grid and operation due to implementation of extensions up to 1000 km transmission lines wind power (voltage level 110 kV – 400 kV) are required till year 2016. 3. Effects of increased wind power generation on spinning reserve power requirements All previously described questions are referred to steady state system conditions. It makes a big difference whether only a few wind mills are operated in a grid or a significant portion of generation is wind power based. It’s a fact that the under voltage protection of existing wind power plants is set to 80% Un. Below this value the wind generators will deactivate particularly to protect itself from destruction. This can result in severe under frequency conditions within the UCTE grid. Figure 3-1 shows the voltage funnel in case of a 3 phase short circuit in the VE Transmission grid near the city of Magdeburg. The coloured areas show grid areas with residual voltages below 15% to 80%. Obviously all wind generators installed in these areas will trip if their under voltage protection is set to 80% Un. In total about 3,700 MW wind power generation will be tripped. Figure3-1: Voltage funnel in case of three phase fault near Magdeburg 4 Other calculations in the grid of E.ON Netz have shown that these values can even be exceeded in the near future. It was assumed that the short circuit current contribution of the wind generators varies between In and 5xIn. Installed wind generation onshore and offshore (MW) 2001 3,500 2006 6,400 2011 12,800 Maximum outage of wind power generation in MW I”scWPP=5In 1,700 – 1,800 2,200 – 3,400 2,000 – 3,500 I”scWPP=In 2,400 – 3,000 4,300 – 4,800 3,800 – 5,700 Table 3-1: Wind power generation losses due to system faults /1/ 2016 15,700 2,500 – 3,900 4,400 – 6,600 In the entire UCTE grid at present a max. outage of 3,000 MW can be covered by the available spinning reserve power. Larger generation outages will result in severe frequency drops. One method imaginable to avoid these conditions could be an increase of the available spinning reserve power within the UCTE grid. Taking into account the current price level of fast spinning reserve power and the fact that this suggestion can scarcely be translated into practice among all UCTE members its necessary to find other options. Why not reduce the setting of the under voltage protection of the wind generators. This could be an effective alternative; at least during the first system protection time step of 150 msec. Detailed calculations have shown that settings of 0.4 Un to 0.5 Un would change the situation to uncritical system conditions. 4. System integration of offshore wind farms 4.1 Three phase AC transmission concept For energy transmission with AC-submarine cables over large distances should be chosen a transmission voltage as high as possible and three-conductor three phase cables. Contrary to single conductor cables, the three conductor cable is an essential prerequisite for compact routing and thus for ultimate approval of the outgoing power cables. Three conductor cables with XLPE insulation and maximum operating voltages up to 170 kV can be assumed to reflect the state of the art; cables for operating voltages up to 245 kV will be available in the near future. Figure 4-1 shows the essential components of such a transmission system from the offshore central station to the grid connection node /2/. The maximum transmission power is limited to about 230 MW per system for 170 kV cables and to about 340 MW for 245 kV cables (see Figure 4-2). Due to the alternating current three-phase cables are able to give off capacitive charging power. The charging current puts a burden on the effective cable cross-section in addition to the active power transmitted and must be taken into consideration. Depending on the reactive power conditions of the wind farm central station and at the grid connecting node, it is advisable to plan corresponding power factor correction (PFC) systems in parallel with the cable. Figure 4-1: Components of an AC offshore – onshore transmission 5 400 350 300 250 200 P in MW I in A 1000 900 800 700 600 500 400 300 200 100 0 I-170 kV I-245 kV P-170 kV P-245 kV 150 0 200 400 600 800 1000 1200 1400 cable size in m m 2 Figure 4-2: Transmission capability of AC XLPE-cables 4.2 Three phase DC transmission concept The high voltage DC transmission system (HVDC) with cables is capable of effective and stable transmission over several hundreds of kilometers. One crucial factor is that no capacitive charging current at all put a stress on DC cables. Furthermore a DC connection does not transmit any short circuit currents from the shore to the medium-voltage distribution level in the wind farm, thus making grid connection of the WPPs more cost effective at the medium-voltage level. Furthermore onshore voltage sags due to internal faults will not be transmitted to the wind generators. The voltage DC link converter with IGBT power semiconductors is recommended as the ideal solution. Its spatial compactness and its suitability for use on the “dead” isolated network outperform the concept of the phase-commutated thyristor converter. Four quadrant operation of the converter makes it possible to control the active and reactive power balances at the wind farm end independently or one another, and can therefore be additionally applied for power optimization in order to cut the costs of the wind turbines. The converter system can be produced as a bipolar system with 150 kV in a twelve-pulse circuit. Between the onshore and offshore stations power is exchanged with the aid of two single-conductor cables. The DC cables of the forward and return conductors are laid jointly. Losses of the cables, heat development and the anticipated magnetic fields are clearly less than in the case of three-phase cables. The dimensions and weight of the DC cables are also clearly less than in the case of three-phase cables, and so laying is clearly easier and more cost effective. Contrary to the AC transmission concept power losses occur not mainly in the cable but in the converter systems. Figure 4-2 shows the essential components of a DC offshore – onshore transmission /2/. Figure 4-3: Components of a DC offshore – onshore transmission The transmission capacity of available HVDC links varies between 250 to 300 MW per system. 6 Number of parallel systems 4.3 Comparison of AC and DC transmission concepts For the reason of limited transmission capability of both AC and DC systems it is strictly recommended to consider these ranges of transmission capability. The decision about number and size of individual windmills in a wind farm is not only determined by the available area but also by the capability of economical and effective power transmission to shore, see Figure 4-4. 7 6 5 4 3 2 1 0 0 250 500 750 1000 1250 Wind farm pow er [MW] HVDC plus AC 150 kV Figure 4-4: Transmission capacity of parallel AC and DC systems /3/ If only investment costs and power losses of AC and DC transmission systems are compared, AC solutions are of higher economic viability than DC systems up to 100 km to 120 km transmission distance. Also the total power losses of AC solutions are less or equal to those of DC solutions. Other investigations have figured out that DC solutions can be more reliable for a stable system operation in the case of system faults with corresponding voltage sags. For the design of large scale offshore wind power generation both AC and DC solutions should be considered taking into account investment costs, losses and system stability. 5. Conclusion This paper considers technical aspects of the present situation of wind power generation in Germany and the consequences of an ongoing wind power extension, particularly of offshore wind power for planning and operation of the German grid. There is no doubt that a further wind power extension requires high investments in new HV transmission lines and enhancements of transmission capabilities. Studies have shown that: • Extension of wind energy requires corresponding network extensions • The technical characteristics of wind generation units must correspond to the requirements of a safe and reliable grid operation, this is of particular importance during and after system faults • Extended wind power generation requires more balancing reserve power with corresponding higher costs • Solutions of large scale offshore wind farm connections are in the development stage. Further detailed basic design studies of AC and DC solutions are necessary as well as investigations regarding system transients / stability of large scale offshore wind farms. 6. References /1/ Gundolf Dany, Hans-Jürgen Haubrich, Matthias Luther, Frank Berger, Klaus von Sengbusch, “Auswirkungen der zunehmenden Windenergieeinspeisung auf die Übertragungsnetzbetreiber“, Energiewirtschaftliche Tagesfragen, 53.Jg. (2003), Heft 9 7 /2/ Ronald Voelzke, Yvonne Sassnick, Norbert Christl, “Integration of large scale wind farms into grids, technical aspects of transmission system design and grid control”, 2003 EWEC conference, Madrid June 16.-19. /3/ Ronald Voelzke, “Planung und Auslegung von Netzen für große offshore Windparks und deren Einbindung in Übertragungsnetze“, Husum Wind 2003 8