Download Session 6

Survey
yes no Was this document useful for you?
   Thank you for your participation!

* Your assessment is very important for improving the workof artificial intelligence, which forms the content of this project

Document related concepts

Earned value management wikipedia , lookup

PRINCE2 wikipedia , lookup

Cost estimate wikipedia , lookup

Construction management wikipedia , lookup

Transcript
Apply Time
Management Techniques
Week 6
Project Time Processes – Part 2
Certificate IV in Project Management 17871
Qualification Code BSB41507
Unit Code BSBPMG402A
BSBPMG402A Apply Time Management Techniques
1
Project Time Processes – Part 2
•
PMBOK Project Time Management Processes  6.1 Define Activities
 6.2 Sequence Activities
 6.3 Estimate Activity Resources
 6.4 Estimate Activity Duration
 6.5 Develop Schedule
 6.6 Control Schedule
•
Related processes from Project Integration
Management –
 4.1 Develop Project Charter
 4.2 Develop Project Management Plan
BSBPMG402A Apply Time Management Techniques
2
6.3 Estimate Activity Resources
• The process of estimating the type and quantities of
material, people, equipment or supplies required to
perform each activity
• Closely related to the Estimate Costs process (7.1) and
normally done simultaneously
• Sometimes the resources are captured in project
management software, most particularly human resources
• Supplementary registers are often maintained for non
human resources
Monitor
• Occurs during the Planning Phase
Initiation
Planning Execution
Close
Control
Adapted from PMBOK 4th Edition
BSBPMG402A Apply Time Management Techniques
3
6.3 Estimate Activity Resources
• Inputs to Estimate Activity Resources
 Activity list and attributes
 Resource Calendars
 Resource availability and skills
 Staffing policies and procedures
 Procurement policies and procedures
• Tools and techniques to Estimate Activity Resources
Alternatives
Analysis
Published
Estimating
Data
Bottom-Up
Estimating
Expert
Judgement
Project
Management
Software
Adapted from PMBOK 4th Edition
BSBPMG402A Apply Time Management Techniques
4
6.3 Estimate Activity Resources
• Published Estimating Data
 Many industries (eg Construction) have standard production
rates and unit costs for common activities
• Bottom-Up Estimating
 Decomposing activities into more detail to assist with
estimation
• Project Management Software
 Can assist with planning, organising and managing
resources
Monitor
 Different levels of sophistication
Initiation
Planning Execution
Close
Control
Adapted from PMBOK 4th Edition
BSBPMG402A Apply Time Management Techniques
5
6.3 Estimate Activity Resources
• Outputs of this process include –
 Activity Resource Requirements
– Captured in project management software or supplementary registers
 Resource Breakdown Structure
– Hierarchical chart of resources required
– Commonly depicted as the project organisation structure for human
resources
 Revised Activity List and Attributes
 Revised Resource Calendar
– Resources marked as unavailable
Monitor
Initiation
Planning Execution
Close
Control
Adapted from PMBOK 4th Edition
BSBPMG402A Apply Time Management Techniques
6
6.4 Estimate Activity Duration
• The process of approximating the number of work periods
needed to complete individual activities with the assigned
or estimated resources
• Previous experience in the type of project and activities
being estimated greatly helps with the accuracy of duration
estimates
• Duration is a function of work effort and resources
• Most project management software can perform this
function
Monitor
• Occurs during the Planning Phase
Initiation
Planning Execution
Close
Control
Adapted from PMBOK 4th Edition
BSBPMG402A Apply Time Management Techniques
7
6.4 Estimate Activity Duration
• Inputs to Estimate Activity Duration
 Activity list and attributes
 Activity Resource requirements and estimates
 Resource Calendars
 Project Scope Statement
 Productivity metrics and estimating data
• Tools and techniques to Estimate Activity Duration
Analogous
Estimating
Parametric
Estimating
Three-Point
Estimating
Expert
Judgement
Reserve
Analysis
Adapted from PMBOK 4th Edition
BSBPMG402A Apply Time Management Techniques
8
6.4 Estimate Activity Duration
• Analogous Estimating
 Develops duration estimates based on previous projects with
similar size, risk and complexity
 Relies heavily of expert judgement and previous experience
 Less costly and less time consuming than other methods
 Least accurate
 Most common form of duration estimating
• Parametric Estimating
 Duration is quantified by multiplying the quantity of work by
Monitor
the labour hours required
 Relies on published estimating data
 Common in Construction
Initiation
Planning Execution
Close
Control
Adapted from PMBOK 4th Edition
BSBPMG402A Apply Time Management Techniques
9
6.4 Estimate Activity Duration
• Three-Point Estimates - PERT
 Calculates the Expected activity duration based on the
weighted average of the Most Likely, Optimistic and
Pessimistic estimates
 Often more accurate than other methods and quantified
range of uncertainty
• Reserve Analysis
 Inclusion of contingency
 Can be calculated for each activity
 Can be calculated for entire project
Monitor
Initiation
 Often a percentage based on risk or complexity
Planning Execution
Close
Control
Adapted from PMBOK 4th Edition
BSBPMG402A Apply Time Management Techniques
10
6.4 Estimate Activity Duration
• The major output of this process
 Activity Duration Estimates
 Draft or High Level Project Duration Estimate
• Often include some form of range of possible results
• Most common form of range is plus or minus - eg
 2 weeks +/- 2 days – the activity could take between 8 and
12 days
 3 weeks +/- 30% - the activity could take between 2 weeks
Monitor
and 4 weeks
Initiation
Planning Execution
Close
Control
Adapted from PMBOK 4th Edition
BSBPMG402A Apply Time Management Techniques
11
6.5 Develop Schedule
• The process of analysing activity sequences, durations,
resource requirements and schedule constraints to create
the project schedule
• All this data is entered into a project scheduling tool which
generates a schedule with planned dates for completing
project activities
• An iterative process with several cycles of refinement
• Baseline Schedule developed in Planning Phase
• Simultaneous with 6.1, 6.2, 6.3 & 6.4
Monitor
Initiation
Planning Execution
Close
Control
Adapted from PMBOK 4th Edition
BSBPMG402A Apply Time Management Techniques
12
6.5 Develop Schedule
• Inputs to Develop Schedule
 Activity list and attributes
 Project Schedule Network Diagrams – relationships and
dependencies
 Activity Resource Requirements
 Resource Calendars
 Activity Duration Estimates
 Project Scope Statement
 Project Scheduling Tool
 Scheduling Methodology and Standards
 Overall Project Calendar and Priorities
BSBPMG402A Apply Time Management Techniques
Monitor
Initiation
Planning Execution
Close
Control
Adapted from PMBOK 4th Edition
13
6.5 Develop Schedule
• Tools and techniques to Develop Schedule
Schedule
Network
Analysis
Critical Path
Method
Critical Chain
Method
Scheduling
Tool
Schedule
Compression
Resource
Levelling
What-if
Scenario
Analysis
Applying
Leads &
Lags
Monitor
Initiation
Planning Execution
Close
Control
Adapted from PMBOK 4th Edition
BSBPMG402A Apply Time Management Techniques
14
Critical Path & Critical Chain
• Critical Path Method
 Was developed in the 1950s by the Dupont Corporation
 The Critical Path Method, abbreviated CPM, or Critical Path
Analysis, is a mathematically based algorithm for scheduling
a set of project activities.
 It takes the activities in the Work Breakdown Structure, the
durations and the interdependencies, and calculates the
longest path through the project.
 It is the longest total duration of all the activities required to
complete a project
 Advanced techniques and calculations (such as early start
and early finish dates, and late start and late finish dates) are
now carried out using project scheduling tools
 Does a forward and backward pass through the schedule
with no regard for resource limitations
Adapted from PMBOK 4th Edition
BSBPMG402A Apply Time Management Techniques
15
Critical Path and Critical Chain
• Critical Chain Method
 Undertakes the same form of analysis and calculations, but
takes into consideration the resource availability and
constraints
 Takes the Critical Path and resource availability to produce a
resource constrained critical path OR Critical Chain
 It is the longest total duration of all the activities required to
complete a project, considering resource availability and
limitations
 Often done simultaneously with Critical Path
Critical Chain
=
Resource Constrained Critical Path
Adapted from PMBOK 4th Edition
BSBPMG402A Apply Time Management Techniques
16
Schedule Compression
Shortens the project schedule without changing project scope
1. Crashing
 Only works for activities where additional resources will
shorten duration
 Does not always produce a viable schedule
 Always results in increased cost
 Sometimes results in increase risk
increased Cost
Crashing
leads to
increased Risk
BSBPMG402A Apply Time Management Techniques
17
Schedule Compression
Shortens the project schedule without changing project scope
2. Fast Tracking
 Phases or activities normally performed sequentially are
performed in parallel
 Only works if activities can be overlapped to shorten duration
 May result in rework and increased risk
 Can result in decreased cost
decreased Cost
Fast Tracking leads to
BSBPMG402A Apply Time Management Techniques
increased
Rework
increased
Risk
18
6.5 Develop Schedule
• The major outputs of this process
 Project Schedule
– Milestone charts
– Bar chart – GANTT charts
– Project Schedule Network Diagrams – PERT Charts
 Schedule Baseline
 Revised Activity Resource Requirements
 Revised Activity Attributes
 Project Calendar
 Revised Risk register
Monitor
Initiation
Planning Execution
Close
Control
Adapted from PMBOK 4th Edition
BSBPMG402A Apply Time Management Techniques
19
What is a GANTT chart?
• Gantt charts are named after their creator, an American
engineer Henry Laurence Gantt, who created the first
bar charts in the early 1910’s.
• It converts the Work Breakdown Structure into a
graphical display of a project schedule
• It displays the durations of all scheduled activities
including the interdependencies
• Often also includes information on project milestones
and resource allocation to activities
• It has become one of the most widespread project
management tools due to the prevalence of MS project
BSBPMG402A Apply Time Management Techniques
20
Sample GANTT Charts
BSBPMG402A Apply Time Management Techniques
21
What is a PERT chart?
• PERT stands for Programme Evaluation and Review
Technique
• It was created by a Naval scientist, Frederick Taylor, in
the 1950’s
• It is a project management technique for determining
how much time a project needs before it can be
completed.
• Each activity is assigned a best, worst and most
probably completion time estimate.
• These estimates are then used to determine the average
completion time and are represented graphically in a
network diagram
BSBPMG402A Apply Time Management Techniques
22
Sample PERT Charts
BSBPMG402A Apply Time Management Techniques
23
6.6 Control Schedule
• The process of monitoring the status of the project in order
to update progress and manage any changes to the
baseline project schedule
• Includes –
 Determining the current status of the project schedule
 Influencing the factors that create the schedule changes
 Determining that the project schedule has changed
 Managing changes as they occur
• Occurs during Monitoring & Controlling
• Is part of Perform Integrated Change
Control (4.5)
BSBPMG402A Apply Time Management Techniques
Monitor
Initiation
Planning Execution
Close
Control
Adapted from PMBOK 4th Edition
24
6.6 Control Schedule
• Inputs to Control Schedule
 Project Management Plan
 Project Schedule
 Performance data
 Project Reporting standards
• Tools and techniques to Control Schedule
Performance
Reviews
Project
Management
Software
Status
Reports
Resource
Levelling
Variance
Analysis
BSBPMG402A Apply Time Management Techniques
Applying
Leads &
Lags
Scheduling
Tool
Schedule
Compression
What-if
Scenario
Analysis
Adapted from PMBOK 4th Edition
25
6.6 Control Schedule
• The major outputs of this process
 Work Performance measurement
 Costs and impacts of variance and corrective actions
 Lesson learned
 Change Requests
 Project Management Plan updates
– Schedule baseline
– Schedule management plan
– Cost baseline
 Project Schedule updates
 Status Reports
Monitor
Initiation
Planning Execution
Close
Control
Adapted from PMBOK 4th Edition
BSBPMG402A Apply Time Management Techniques
26
Team Assignment Criteria
Team Assignment
Components
Marks
Basic Competency
Higher Competency
Work Breakdown Structure
including deliverable/activity
duration (start and end dates)
and interdependencies
5
Basic WBS presented in Excel
or a table
High level deliverables and
activities included
Some interdependencies are
indicated
Detailed WBS in MS Project
Phases broken down into
detailed deliverables and
activities with appropriate
indentation
Interdependencies on all
activities
Baselined Gantt chart indicating
the critical path
5
Basic Gantt chart
Report showing critical path
Detailed Gantt chart
Report showing critical path
and the duration
Explanation of the tools and
techniques used to estimate the
activity durations and timelines
10
Basic understanding of tools and
techniques
At least two estimating methods
used
Advanced understanding of
tools and techniques
More than two methods used
and experts consulted
20
13 to 16
Total
BSBPMG402A Apply Time Management Techniques
17 to 20
27