Download Chamonix IEFC session: Cooling and Ventilation

Survey
yes no Was this document useful for you?
   Thank you for your participation!

* Your assessment is very important for improving the work of artificial intelligence, which forms the content of this project

Document related concepts
no text concepts found
Transcript
CV activities for CPS during
YETS
PS & PSB YETS meeting 8-10-2015
Highlights
• The manpower is common for all the
machines of the PS Complex and for half of
the LHC.
• Time constraints must be sent to the
contractor → please send your specific
request for water.
• Preliminary plan as been established.
Highlights
Activities for the YETS
• Normal yearly maintenance
• Example for the cooling circuits:
• Emptying the primary circuits and cleaning
of the cooling towers
• Repairs
• Necessary maintenance (filters, belt,
greasing, …)
• Instrumentation check / calibrating
• Bugs fixing
• Corrective maintenance
Activities for the YETS
• Leir, Linac 2 and 3:
• Mechanical overhaul of one secondary pump
• Linac 3:
• Replacement of the power and control cables connections
of the ventilation
• Booster:
• Cleaning the heat exchanger of the cooling plant
• Mechanical overhaul of one primary pump
• Modification of the beam dump ventilation (sensor +
control) → Test with the CCC
• Installation of a flowmeter on the extraction air duct for
HSE
• Create new connections on cooling circuit for power
converter in room BRF2
• Take samples and inspection to prepare LS2 works
• Request of the Survey (see hereafter)
Activities for the YETS
• PS:
• POPS cooling: create new connections for the future cooling of the
dummy loads.
• Creation of new connections for the 10 MHz cavity
• Chilled water pumps mechanical overhaul
• Take samples and inspection to prepare LS2 works
• ISOLDE
• Target cooling: modification of the control system for the leak
detection
• Main cooling plant: new version of the program and functional tests
• Modification of the stack (roof bldg.170)
• Medicis: functional test of the ventilation and commissioning of the
hot cell ventilation
• East Area
• Main cooling plant: new version of the program and functional test
• AD
• Modification of the main cooling pipework to install flowmeter
• Sump in TT6: correctives interventions
MEYRIN, CPS (1/2)
Linac + Leir
Booster
PS
Circuits
Stop
Restart
LEIR – LINAC 2 and
3 (Demi water)
15/12/2015
25/01/2016
LINAC 2 (Raw water)
Running
LINAC 3 (Raw water)
15/12/2015
25/01/2016
Booster / TT2
16/12/2015
01/02/2016
Booster – chilled
water (affecting PS
359 RF room)
16/12/2015
01/02/2016
PS – Central building
Anneau
16/12/2015
26/01/2016
PS – Main magnet
16/12/2015
01/02/2016
POPS
16/12/2015
26/01/2016
PS – Chilled water
16/12/2015
26/01/2016
MEYRIN, CPS (2/2)
Machine
Circuits
Stop
Restart
Isolde
7/12/2015
29/02/2016
East area
18/11/2015
21/03/2016
AD
TBD
AD Target
16/11/2015
TBC
CTF3
CTF3
TBD
nTOF
nTOF
Running
Isolde
East area
AD
29/03/2016
Survey request
Survey request
Survey request