* Your assessment is very important for improving the workof artificial intelligence, which forms the content of this project
Download Comparison of harmonic limit allocations in IEC TR 61000-3
Survey
Document related concepts
Power factor wikipedia , lookup
Buck converter wikipedia , lookup
Power inverter wikipedia , lookup
Variable-frequency drive wikipedia , lookup
Electrical substation wikipedia , lookup
Power over Ethernet wikipedia , lookup
Electric power system wikipedia , lookup
Electrification wikipedia , lookup
Three-phase electric power wikipedia , lookup
History of electric power transmission wikipedia , lookup
Audio power wikipedia , lookup
Power electronics wikipedia , lookup
Voltage optimisation wikipedia , lookup
Amtrak's 25 Hz traction power system wikipedia , lookup
Power engineering wikipedia , lookup
Switched-mode power supply wikipedia , lookup
Transcript
Comparison of harmonic limit allocations in IEC TR 61000-3-6 and ER G5/4-1 for MV Networks IEC TR 61000-3-6 Stage 1 section 8.1.1 provides limits based on ratio of agreed power, Si to short-circuit power, Ssc. Stage 1 section 8.1.2 provides limits based on ratio of sum of weighted distorting power, SDwi, to short-circuit power, Ssc. If the ratio Si/Ssc or SDwi/Ssc ≤0.2% then connection is permitted without detailed assessment. ER G5/4-1 The nearest comparable part of G5/4-1 is Stage 2 Table 10 which permits 130kVA 6-pulse convertor, 250kVA 12pulse convertor and 150kVA 6-pulse AC regulator to be connected without detailed assessment to 11kV; this assumes Ssc = 100MVA. This equates to SDwi/Ssc of 0.26%, 0.13% & 0.104% for the three types of 6-pulse convertor in the IEC, 0.125% for 12-pulse convertor & 0.105% for 6pulse AC regulator. Stage 2 section 8.2.1 gives a simplified stage 2 assessment. This gives limits on harmonic currents as a percentage of the current corresponding to the customer’s agreed power. Indicative limits are given in Table 5 applicable when agreed power, Si ≤1MVA, Si/Ssc <1%, background levels and not restrictive and there is no power factor correction. Stage 2 Table 12 gives current limits in Amperes. These are based on a single customer raising the harmonic voltage distortion levels by 25% of the planning levels. The Table only applies where background levels ≤75% of the planning level. This is a first come, first served approach and is not based on the agreed power. For comparison, at Si = 1MVA, G5/4-1 gives higher limits for h = 5, 7, 11 & 13 but not for some higher orders. Stage 2 section 8.2.2 gives a more complex assessment method: a) Establish the global harmonic voltage contribution, GhMV+LV, that can be allocated to the total of MV and LV installations supplied from the MV node. Note this requires knowledge of the transfer coefficient, T hUM, from the upstream system to the MV node by simulation. Example using existing The Table 12 limits have to be scaled according to shortcircuit power. The detailed Stage 2 section 7.3 assessment method involves prediction of voltage distortion taking account of background voltage distortion, assumed network impedance (based on 50Hz short-circuit power, harmonic order h and standard values of ‘k’ allowing for resonance) and customer requested emission currents up to the 50th harmonic. The predicted values are compared with the planning levels for 5th harmonic and THD. The assessment can done using a simple spreadsheet approach. It considers only the point of common coupling so like Stage 2 section 8.2.2 of the IEC is Comments The levels permitted are broadly of the same order but with IEC less conservative for all but one of the 6-pulse cases. The assumption of Ssc = 100MVA underlying Table 10 of G5/4-1 assumes a fairly robust network. It makes sense to scale the Table 10 limits according to short-circuit power but this is not mentioned in this part of G5/4-1. The IEC approach is more general, allowing for scaling for shortcircuit power. It also covers 33kV so would allow 1MVA sum of weighted distorting power for a typical 500MVA short-circuit power at 33kV. Both methods require knowledge of the background levels and both take account of short-circuit power but the IEC approach gives no guidance on what level of background distortion is acceptable for use of this method. The IEC approach is based on agreed power so applies the equal rights approach whereas G5/4-1 uses first come-first served. The G5/4-1 approach is not limited to Si ≤1MVA and so can be applied to a wider range of cases. With the IEC approach there are some concerns: a) How can it be applied retrospectively as existing customers may/will have taken part of the margin? b) It is unclear how the future load growth would be taken into account in deriving St. c) It would appear to treat those with small import capacity (e.g. generators) unfavourably if St relates to import capacity and not export capacity. d) Derivation of the transfer coefficient implies G5/4-1 planning levels: At 33kV fed from 132kV for h=5 with L5MV =2%, L5Us =2%, α=1.4 and T5UM = 1 then GhMV+LV = 0%! At 11kV fed from 33kV for h =5 with L5MV =3%, L5Us =2%, α=1.4 and T5UM = 1 then GhMV+LV = 1.65%. b) Establish the total available power, St, at the location under consideration. The analysis does not include neighbouring substations. c) Allocate a portion of the global emission limit based on the ratio of agreed power, Si, total available power, St, to a root α. limited to one node. No detailed modelling is required and consequently the approach can be applied without resorting to consultants. This Stage 2 approach is not applied to connection at 33kV and above. Many more connections are made at 11kV than 33kV and so this type of assessment represents a significant assessment activity. detailed modelling and so is more complex than the G5/4-1 equivalent. This has cost and resource implications. e) The allocation policy is not foolproof – background levels at LV could grow say due to increasing penetration of electronic loads. f) When LhMV = LhUS and ThUM = 1 then this gives GhMV+LV = 0% and it is not clear how to apply the technical report. g) 8.2.2.2 and 8.2.2.3 highlight limitations of the basic rules and offers alternatives adding to complexity e.g. “For distribution systems with long cables and overhead lines, where customer installations are distributed along the length of the feeders, the above approach may result in specifying too strict harmonic currents, thus penalising customers connected at some distance down the line…’ The report gives Annex B where it becomes clear that complexity is dramatically increased over G5/4-1 h) The allocation of part of the margin could increase cost for first ‘connectees’ and the margin reserved for others may be never be utilised. The move away from minimum cost may not be acceptable to OFGEM. Stage 3 section 8.3 involves conditional connection where higher levels than allowed under stage 2 may be conditionally allowed. The text does not appear to explicitly state that the effect on lower voltage networks must be considered. Conditional connection may be justified based on a number of reasons including the Stage 2 approach is, after consideration, judged to be too conservative. Stage 3 involves the determination of harmonic voltages at the PCC based on a harmonic impedance model of the network to take account of any resonance. For connections at 33kV and above the assessment takes account of the effect on lower voltage networks. Use of a computer analysis program is recommended. Increased levels of detail of assessment using computer analysis are implied. Stage 3 assessments are recognised as being onerous in time, skill level and resources.