Download AC Single Rail Track Circuits Set

Survey
yes no Was this document useful for you?
   Thank you for your participation!

* Your assessment is very important for improving the workof artificial intelligence, which forms the content of this project

Document related concepts

Flexible electronics wikipedia , lookup

Immunity-aware programming wikipedia , lookup

Resistive opto-isolator wikipedia , lookup

Multimeter wikipedia , lookup

Rectiverter wikipedia , lookup

Surge protector wikipedia , lookup

Transcript
Engineering Procedure
Signalling
CRN SI 004
AC SINGLE RAIL TRACK
CIRCUITS – SET-UP, TEST &
CERTIFICATION
Version 1.1
Issued December 2015
Owner: Principal Signal Engineer
Approved by: Stewart Rendell
Authorised by: James Zeaiter
Disclaimer. This document was prepared for use on the CRN Network only. John Holland Rail Pty Ltd
makes no warranties, express or implied, that compliance with the contents of this document shall be
sufficient to ensure safe systems or work or operation. It is the document user’s sole responsibility to
ensure that the copy of the document it is viewing is the current version of the document as in use by
JHR. JHR accepts no liability whatsoever in relation to the use of this document by any party, and JHR
excludes any liability which arises in any manner by the use of this document.
Copyright. The information in this document is protected by Copyright and no part of this document may
be reproduced, altered, stored or transmitted by any person without the prior consent of JHR.
UNCONTROLLED WHEN PRINTED
Page 1 of 10
CRN Engineering Procedure - Signalling
AC Single Rail Track Circuits – Set-Up, Test & Certification
CRN SI 004
Document control
Revision
Date of Approval
Summary of change
1.0
May 1997
RIC Standard SC 07 43 01 00 WI Version 1.0 May 1997.
1.0
May 2011
Conversion to CRN Signalling Standard CRN SI 004.
1.1
December 2015
Review and Update
Summary of changes from previous version
Section
Summary of change
2.2
Move track connection note text from Appendix 1 into this section
2.10
Update to include an indicator diagram
3.2 (new)
Move Phasing note text from Appendix 1 to create a new section
Appendix 1
Removed
Appendix 2
Renamed Appendix
© JHR
Issued December 2015
UNCONTROLLED WHEN PRINTED
Page 2 of 10
Version 1.1
CRN Engineering Procedure - Signalling
AC Single Rail Track Circuits – Set-Up, Test & Certification
CRN SI 004
Contents
1
2
General ......................................................................................................................................... 4
Initial Set-Up ................................................................................................................................ 4
2.1
Clear Old Track Connections ........................................................................................... 4
2.2
Bonding and New Connections........................................................................................ 4
2.3
Check Bonding and Connections..................................................................................... 5
2.4
Check Auxiliary Track Equipment .................................................................................... 5
2.5
Equipment Check ............................................................................................................. 5
2.6
Check Auxiliary Track Equipment .................................................................................... 5
2.7
Equipment Check ............................................................................................................. 5
2.8
Power-Up - Feed End ...................................................................................................... 5
2.9
Power-Up - Relay End ..................................................................................................... 6
2.10
Shunt and Correspondence Check .................................................................................. 6
3
Final Adjustment and Measurement ......................................................................................... 6
3.1
Initial Adjustment .............................................................................................................. 6
3.2
Track Circuit Polarity (Phasing) Check ............................................................................ 6
3.3
Drop-Shunt Check and Final Adjustment ........................................................................ 7
4
Certification ................................................................................................................................. 7
4.1
Zero-Feed Relay Voltage ................................................................................................. 7
4.2
Test Shunt ........................................................................................................................ 7
4.3
History Cards ................................................................................................................... 7
Appendix - Track Circuit History Card ................................................................................................ 8
© JHR
Issued December 2015
UNCONTROLLED WHEN PRINTED
Page 3 of 10
Version 1.1
CRN Engineering Procedure - Signalling
AC Single Rail Track Circuits – Set-Up, Test & Certification
1
CRN SI 004
General
This instruction describes procedures for the putting into operation, testing and certification
of an AC single rail track circuit equipped with a double-element vane relay, in a typical
CRN installation.
Commissioning a new track circuit consists of removing any old equipment, connecting the
new equipment and any new bonding, powering-up the new equipment, then carrying out
the final adjustments and certification checks.
All care must be taken, that none of the necessary checks and tests specified in this
document are omitted.
This procedure applies to all forms of Single-Rail AC track circuit listed in Table 1, below.
Track Cct
Type
Track Feed
Set
Feed Res
Value
Feed Trans
Volts(type)
Relay
Protection
Min Drop
Shunt
Test Shunt
Sig Bch
(standard)
St 47
1.0
6
Shielding
Impedance
0.25
0.25
Sig Bch
(high
voltage)
St 51
6
30
25 ohm
0.25
0.25
WB&S
WB&S
16.5
20
‘501’
Rectifier
0.5
0.5
Table 1 - Single-Rail AC Track Circuit Arrangements
2
Initial Set-Up
Initial set-up details the activities generally carried out by the set-to-work team. It covers
removal of any old track circuit equipment and the connection and powering-up of the new
equipment.
2.1
Clear Old Track Connections
Where an existing signalling system is being renewed, the first step is the removal of all
old, redundant track circuit connections. This includes old feed and relay connections,
impedance bonds, and spark-gap connections.
2.2
Bonding and New Connections
Bond out all redundant insulated joints. Remove any temporary bonds around new
insulated joints. Connect any new parallel and series bonds. Check that all mechanical
joints are bonded out.
Make all new rail connections, and close up all terminal links.
Check that impedance bond sideleads are all of equal length and securely terminated to
bond and rails, that neutral connection is secure, and track feed and relay cables are
correctly terminated.
It is critical that the rail terminations of track connection cables are as low-resistance as
possible, in view of the high DC and AC currents flowing through them, and especially in
view of the need to keep traction return currents balanced. As a guide, the voltages to be
expected on good new connections should be less than 2mV.
© JHR
Issued December 2015
UNCONTROLLED WHEN PRINTED
Page 4 of 10
Version 1.1
CRN Engineering Procedure - Signalling
AC Single Rail Track Circuits – Set-Up, Test & Certification
CRN SI 004
Measure the AC voltage drop at each connection between the connecting cable
conductors and the head of the rail near the termination. If the cable cores are not
accessible, measure from a point on the connection lug, as close as possible to the
insulation.
Note that, where duplicated sideleads are fitted, a low millivolt reading will be measured
on both, so long as at least one is making good contact.
Any reading over 5mV should be taken to indicate a suspect connection. Check the
tightness of the securing nuts and, if this does not work, dismantle the connection, clean
all mating surfaces with abrasive or solvent as required, reassemble and tighten carefully.
2.3
Check Bonding and Connections
Walk length of track circuit, checking track against the new track insulation plans.
2.4
Check Auxiliary Track Equipment
Check that any auxiliary track circuit equipment, such as traction tie-in bonds and
electrolysis bonds have been reconnected.
Check that any traction tie-in cables are terminated.
2.5
Equipment Check
Check that track transformer and feed resistance are correctly installed, with feed
resistance unit of correct value.
Check that surge protection is installed, correct arrestors fitted, and earthing is installed
and correctly terminated.
2.6
Check Auxiliary Track Equipment
Check that any auxiliary track circuit equipment, such as traction tie-in bonds and
electrolysis bonds have been reconnected.
Check that any traction tie-in cables are terminated.
2.7
Equipment Check
Check that track transformer and feed resistance are correctly installed, with feed
resistance unit of correct value.
Check that surge protection is installed, correct arrestors fitted, and earthing is installed
and correctly terminated.
2.8
Power-Up - Feed End
Connect track feed 120 volt supply and close outgoing cable links.
Adjust feed resistance to about 1.0 ohms.
Set feed transformer connection to correct output tap.
Measure feed end rail volts.
Check that track polarity is reverse to that of the previous AC track. (See Appendix 1). If
not, then reverse the connections between feed set and feed end impedance bond.
© JHR
Issued December 2015
UNCONTROLLED WHEN PRINTED
Page 5 of 10
Version 1.1
CRN Engineering Procedure - Signalling
AC Single Rail Track Circuits – Set-Up, Test & Certification
2.9
CRN SI 004
Power-Up - Relay End
Check that surge protection is installed, correct arrestors fitted, and earthing is installed
and correctly terminated.
Close incoming relay fuse and link, and relay local coil Bx120 fuse and link.
Observe that the relay energises. The relay should pick up strongly, but not violently.
If the relay drives down, reverse the connections between relay and relay-end impedance
bond.
Impedance Bond Resonation:
If the track circuit uses 2000 amp/rail resonated impedance bonds, these should now be
adjusted.
If the relay does not pick up, or picks up only weakly, it may be necessary to increase the
feed transformer secondary volts.
If the relay picks up too strongly, it may be necessary to decrease the feed voltage, by
increasing the feed resistance (to a maximum around 0.75 ohms) or decreasing the
transformer secondary volts.
2.10
Shunt and Correspondence Check
Using a fixed shunt (in accordance with the Table 1), applied at the relay end of the track,
shunt the track and observe that the relay de-energises.
Where the track circuit is indicated on an indicator diagram, check the correspondence of
the track circuit to the diagram indication as part of this shunt check.
3
Final Adjustment and Measurement
Final adjustment details the adjustment of the track feed set to achieve the specified relay
operating values.
3.1
Initial Adjustment
Measure that the relay control voltage is between 120% and 200% of the compression
voltage recorded on the relay test label. If it is outside this range, adjust the track feed
voltage correspondingly.
Feed voltage adjustments should, as far as possible, be made by adjusting the feed
transformer tapings; this will ensure that the feed resistance value is maintained suitably
high to provide a good operating phase angle.
3.2
Track Circuit Polarity (Phasing) Check
With AC track circuits, it is critical that at any interface between a pair of tracks, the phasing
of one track is opposite to the phasing of the other. This requirement exists to ensure that
if the blockjoints at the interface fail, the relay of one track cannot be held falsely energised
by the feed of the other. This requirement can be relaxed, at an interface where two feed
ends abut.
To check track phasing between two single-rail track circuits, measure the voltages on the
signalling rail, from either side of the blockjoint to the common traction rail, and the voltage
directly across the blockjoint on the same rail. If the tracks are correctly phased, the sum
of two track circuit voltages will equal the voltage across the joint; if the sum of the voltages
© JHR
Issued December 2015
UNCONTROLLED WHEN PRINTED
Page 6 of 10
Version 1.1
CRN Engineering Procedure - Signalling
AC Single Rail Track Circuits – Set-Up, Test & Certification
CRN SI 004
is significantly different from the measured value, then the tracks are not correctly phased
and corrective action needs to be taken.
At the interface between single and double-rail track circuits, the ‘half-bond’ voltage on the
double rail track takes the place of one ‘rail to common’ voltage.
3.3
Drop-Shunt Check and Final Adjustment
Measure the relay control coil volts (without the shunt applied); this should be about 1 volt,
or 50% above the compression voltage recorded on the relay test label, whichever is
greater.
Check the drop-shunt of the track, using a variable shunt unit at the relay end of the track,
connected two metres outside the sidelead connections.
The drop-shunt measured should be greater than the minimum specified in Table 1. A final
drop shunt value between 150% and 200% of the minimum is acceptable. If the initial value
is outside this range, an attempt should be made to adjust the track feed for a better drop
shunt.
Note: While the final setting may involve some compromise, it should be possible to
achieve a suitable control voltage while retaining a drop shunt value below the 200% value
and certainly above the minimum.
The relay is de-energised when all front contacts can be seen open.
4
Certification
Certification covers the proving of correct operation of the track circuit, and the completion
of all documentation activities.
4.1
Zero-Feed Relay Voltage
With all adjacent tracks operating, disconnect the feed from the track under test, and record
the AC voltage on the relay control coil.
If the remaining voltage exceeds 30% of the relay release value, this must be reported as
a track circuit fault, and the cause of the excessive voltage located and rectified.
4.2
Test Shunt
Test shunt the track, using a fixed shunt of the value stated in Table 1. Sets of three shunts
should be made at the following points:
- 2m from the feed end rail connections
- Mid-track
- At both ends of any parallel-bonded section of track (where points are involved)
- 2m from the Relay end rail connections
4.3
History Cards
When all track work is complete, fill in individual history cards for all tracks tested by the
team. The cards should be signed by the responsible member of the team.
End of Procedure.
© JHR
Issued December 2015
UNCONTROLLED WHEN PRINTED
Page 7 of 10
Version 1.1
CRN Engineering Procedure - Signalling
AC Single Rail Track Circuits – Set-Up, Test & Certification
CRN SI 004
Appendix - Track Circuit History Card
© JHR
Issued December 2015
UNCONTROLLED WHEN PRINTED
Page 8 of 10
Version 1.1
CRN Engineering Procedure - Signalling
AC Single Rail Track Circuits – Set-Up, Test & Certification
© JHR
Issued December 2015
CRN SI 004
UNCONTROLLED WHEN PRINTED
Page 9 of 10
Version 1.1
CRN Engineering Procedure - Signalling
AC Single Rail Track Circuits – Set-Up, Test & Certification
© JHR
Issued December 2015
CRN SI 004
UNCONTROLLED WHEN PRINTED
Page 10 of 10
Version 1.1