Download April 30, 2008

Survey
yes no Was this document useful for you?
   Thank you for your participation!

* Your assessment is very important for improving the workof artificial intelligence, which forms the content of this project

Document related concepts

Ohm's law wikipedia , lookup

Power engineering wikipedia , lookup

Three-phase electric power wikipedia , lookup

Current source wikipedia , lookup

Rectifier wikipedia , lookup

History of electric power transmission wikipedia , lookup

Power electronics wikipedia , lookup

Schmitt trigger wikipedia , lookup

Electrical substation wikipedia , lookup

Voltage regulator wikipedia , lookup

Surge protector wikipedia , lookup

Buck converter wikipedia , lookup

Switched-mode power supply wikipedia , lookup

Voltage optimisation wikipedia , lookup

Stray voltage wikipedia , lookup

Alternating current wikipedia , lookup

Opto-isolator wikipedia , lookup

Mains electricity wikipedia , lookup

Transcript
April 30, 2008
Re:
•
•
Voltage Profile Improvement in Loss Factor Base Cases.
Some stakeholders are requesting the ISO to improve the bus voltage accuracy
used in the loss factor base cases. The AESO attempts to maintain the maximum
possible accuracy with the given loss factor resources and time constraints.
Generally, the ISO has ensured all bus voltages (69 kV or higher) in the base
cases are within 5% of historical levels.
Voltages do not affect loss factors as much as accurate power flows do.
Based on the stakeholders request the AESO recommends the following actions and
asks for stakeholder input (highlighted and underscored segment below) along with
explanation and rationale to finalize the process –
•
•
•
Voltages at buses 240 kV and higher with more than 500 MW of net injection
(load or generation) will be evaluated to _____% of the historical voltage.
All other buses 69 kV or higher will be evaluated to _____% of the historical
voltage.
Historical voltages will be determined from the PI database following the current
process.
The AESO would like to point to make stakeholders aware of the following items related
to voltage profiles in the base cases –
•
•
•
The current process allows the AESO to check and adjust about 600 buses (69
kV and higher) per case (12 cases in total). It takes about two to three weeks to
check and adjust (an iterative process) all 12 cases.
It takes about 1 week to fix the bus voltages to within 2.5 kV for one operational
case for about 100 buses. If the same care was applied to the loss factor cases,
the ISO would have to adjust about 600-700 buses for each of the 12 cases and
we estimate an effort of about 4 months.
The timeframe doing the loss factor base cases is extremely compact (roughly 6
weeks to finalize the 12 cases) to meet the November deadline for final loss
factors.
2500, 330 - 5th Ave SW Calgary, Alberta T2P 0L4
t (403) 539-2450 | f (403) 539-2949 | www.aeso.ca
-2Stakeholders are requested to provide input on the issue by May 14, 2008. The input
should reflect some level of engineering analysis. The ISO will quantify the responses
and provide a recommended course of action by May 23, 2008. Please note the AESO
holds the right of determining a course of action regarding this issue.
As always, please contact me if you have any questions.
Yours truly,
Originally Signed by:
Robert Baker, P.Eng.
AESO, Operations Forecasting
Related documents