Download battery charging guide

Survey
yes no Was this document useful for you?
   Thank you for your participation!

* Your assessment is very important for improving the workof artificial intelligence, which forms the content of this project

Document related concepts

Wind turbine wikipedia , lookup

Electrification wikipedia , lookup

Ground (electricity) wikipedia , lookup

Buck converter wikipedia , lookup

Stray voltage wikipedia , lookup

History of electric power transmission wikipedia , lookup

Switched-mode power supply wikipedia , lookup

Power engineering wikipedia , lookup

Voltage optimisation wikipedia , lookup

Electric battery wikipedia , lookup

Variable-frequency drive wikipedia , lookup

Single-wire earth return wikipedia , lookup

Wire wrap wikipedia , lookup

Vehicle-to-grid wikipedia , lookup

Mains electricity wikipedia , lookup

Power electronics wikipedia , lookup

Alternating current wikipedia , lookup

Three-phase electric power wikipedia , lookup

Power inverter wikipedia , lookup

Islanding wikipedia , lookup

Solar micro-inverter wikipedia , lookup

Transcript
BATTERY CHARGING GUIDE
For Grid-Connected and Off-Grid Systems
© 2012 Southwest Windpower, Inc.
All Rights Reserved
Building a Battery Charging/Battery
Backup System
Using the Skystream 3.7® wind generator, you can easily build a battery
charging system or connect to an existing renewable energy system. With
Skystream’s AC output power design, the Skystream will install in your
home’s circuit breaker just as any other large home appliance, supplying
your home’s electrical loads. In battery based systems your home host
inverter and battery will balance electrical demand. While there may be
many ways to configure a system, Southwest Windpower recommends the
following most common options.
more elements such as diversion loads, an auxiliary generator, photovoltaic
panels and charge regulators and may or may not be connected to the
electrical utility grid. Battery charging systems must also be safe and may
be subject to the same building code and zoning regulations as a typical
Skystream grid-connected installation. As such. battery charging systems
may be quite complex and must be carefully planned, taking into account
immediate needs, regulations and requirements as well as future needs.
A block diagram of battery charging system incorporating many typical elements is depicted in Figure 1.
Diversion Load
Scope
This manual provides the specialized information needed to incorporate
Skystream 3.7 in either grid-connected or “off-grid” battery charging systems.
Diversion Load
Control System
PV Array
Low Voltage
Load
Battery Bank
PV Charge Regulator
As battery charging systems are often much more complex than systems
using Skystream to supplement grid power, this manual does not attempt
to provide detailed instructions for every possible combination of battery
bank, solar panel array, diversion load, inverter, auxiliary generators, and
transformers.
Auxiliary Generator
Host Inverter
This manual does not contain detailed assembly and installation instructions for Skystream 3.7; refer to your Skystream Owners Manual for that
information.
Introduction
The most common application for Skystream 3.7 is as a supplement to
the AC power provided by the utility grid. However, Skystream may also
be successfully utilized in battery charging applications, including gridconnected systems with battery backup and completely off-grid battery
systems.
In addition to the basic system elements of the host inverter, Skystream
and battery bank, a battery charging system may also incorporate many
2 Skystream 3.7® Battery Charging Guide, Rev B
Skystream
Wind Turbine
High Voltage Load
Figure 1: Typical elements of a battery charging system
Utility Grid
Theory of Operation
The integration of Skystream into a battery charging system has requirements very similar to those of grid-connected systems without batteries. In
either case Skystream supplements high voltage (AC) power supplied by
another source. With grid-connected systems Skystream supplements the
utility grid while with a battery system Skystream may be supplementing
power supplied to an inverter from a battery bank, an array of photovoltaic
panels, an auxiliary generator or the utility grid.
As shown in Figure 1, in battery charging systems, Skystream is typically
connected in parallel with what are often called the “AC Out” terminals of
the host inverter along with the high voltage AC loads the inverter supports. Since the Skystream produces high voltage AC, it will directly provide
electricity (as long as the wind is blowing) for the high voltage loads and
thereby lessen demand from the host inverter. The inverter acts as a hub
for host energy throughputs, managing DC power, high voltage loads and
energy input such as from photovoltaic panels. In battery charging systems
the host inverter creates a “grid-like” environment to which Skystream can
synchronize and provide power.
Most inverters sold today have a form of H-bridge converter that allow
flow of DC current in two directions and AC coupling that can use excess
power on the AC bus for battery charging purposes. It is imperative that
the “host” inverter be of a sufficient capacity to safely manage the maximum output from Skystream in the event that there is no load operating
in parallel with the turbine. A regular 240 VAC split phase version of the
Skystream can produce 2.5 kW continuously with peak momentary outputs
over 3 kW; therefore, an inverter (or multiple inverters) with a rating over 3
kW is required. A single phase 120 VAC “battery charging” version of the
Skystream 3.7® is limited to 1500 watts continuous power but can produce peak outputs of 2 kW; therefore, an inverter with a rating of 2 kW is
sufficient for those applications.
Several inverter manufacturers have provided Southwest
Windpower with specific recommendations for which their inverters are appropriate for battery charging in connection with a
Skystream 3.7®. This is a partial list of compatible inverters as
there may be others that will work equally well that are not listed
here. Check with the manufacturer of your inverter to be certain it
can support this type of operation (See Table 1).
System Configurations
The following sections present four of the most common Skystream battery charging system configurations. The best configuration for your particular application depends on many factors including: availability of existing
equipment such as inverters, need for 240 volt power, wire run distance
and cost.
Schematics for a number of the battery charging system configurations are
presented at the end of this booklet. These schematics are provided as a
guide for typical installations – they are not intended to be comprehensive
installation drawings.
IMPORTANT: Note that the 120 volt, single phase model of Skystream
MUST NOT be connected to the utility grid as it is not UL approved for
this application.
Refer to Table 1 for specific inverter recommendations for each configuration.
Battery Charging Guide
3-CMLT-1385-01
Revision: B
Skystream 3.7® Battery Charging Guide, Rev B 3
Table 1: Configurations and suitable inverters
Option
A
A (Grid)
B
B (Grid)
C
C (Grid)
D
Skystream 3.7
Configuration
120/240
Split Phase
120/240
Split Phase
120/240
Split Phase
120/240
Split Phase
120/240
Split Phase
120/240
Split Phase
120
Single Phase
Grid
Not Connected
Grid-Connected
Grid-Connected
Not Connected
Not Connected
Grid-Connected
Not Connected
Transformer
Not Required
Not Required
Not Required
Not Required
120/240
Tranformer
120/240
Tranformer
Not Required
Inverter Type
120/240 VAC
Split Phase
120/240 VAC
Split Phase
(2) 120 VAC
Single Phase
(2) 120 VAC
Single Phase
120 VAC
Single Phase
120 VAC
Single Phase
120 VAC
Single Phase
Inverter Manufacturer
Model
Magnum Energy Inc.
MS2812
l
MS4024
l
MS4024AE
l
l
MS4448AE
l
l
l
l
l
l
l
Outback Power Products Inc.
FX2012T
l
FX2524T
l
FX3048T
l
VFX2812
l
VFX3524
l
l
l
VFX3648
l
l
l
l
l
l
l
l
VFX3024E
VFX3048E
VFX3024W
VFX3048W
GTFX3048
l
l
GVFX3524
l
l
GVFX3648
l
l
SMA, America Inc.
5048U
l
4248U
Xantrex
XW
l
4 Skystream 3.7® Battery Charging Guide, Rev B
l
l
l
l
l
Option A
120/240 volt (US residential voltage) Skystream with a SINGLE
120/240 VAC inverter
Option B
120/240 volt (US residential voltage) Skystream with two 120 VAC
inverters
Optional Utility
Grid Connection
Optional Utility
Grid Connection
Electric
Meter
240V
240V Inverter
120V Inverter
Electric
Meter
240V
120V Inverter
Breaker
Box
Battery
Breaker
Box
Battery
240V
240V
Figure 2: Simplified depiction of Option A
Figure 3: Simplified depiction of Option B
This configuration is a good choice for grid connected homes with a need
for battery backup and 240 volts. The single 120/240 VAC inverter provides for a compact and neat installation.
This configuration is a good choice for grid connected homes with a need
for battery backup and 240 volts. The system requires two 120 VAC
inverters wired in parallel. A detailed wiring schematics are contained in
Appendix A, Figure 1.
Skystream 3.7® Battery Charging Guide, Rev B 5
Option D
Option C
120/240 volt (US residential voltage) Skystream with 120 VAC
inverter and transformer
120 volt Skystream with a single 120 VAC inverter
Optional Utility
Grid Connection
120V
120V Inverter
Electric
Meter
Transformer
240V
120V
120V Inverter
Breaker
Box
Battery
Breaker
Box
Battery
240V
120V
Figure 4: Simplified depiction of Option C
Figure 5: Simplified deption of Option D
This configuration is a good choice for systems with an existing inverter.
It supports 240 volt loads and utilizes a transformer to adapt the voltage
between 240V and 120V. There is an inefficiency of approximately 20
watts associated with the transformer; however this inefficiency may be
acceptable in high wind areas and based on the cost of the transformer
compared to a second inverter. Detailed wiring schematics are contained in
Appendix A, Figure 2.
This option may be a good choice in applications that do not require 240
volt service. It is an economical system as only a single inverter is required.
However, because it is a 120 VAC system:
• The system may not be connected to the grid. 120 volt Skystream is not UL approved.
• The peak power available from the turbine is reduced which may make a 120/240
volt system a better choice in high wind areas.
• Wire is expensive if long wire runs are required – 120 volt systems require larger
wire compared to 120/240 volt systems.
• In these scenarios a 120 volt system may not be the best choice.
Detailed wiring schematics are contained in Appendix A, Figure 3.
6 Skystream 3.7® Battery Charging Guide, Rev B
Battery Voltage Regulation and Diversion
Loads
In the event that the batteries become fully charged, it will be necessary
to displace power that may otherwise overcharge and damage the batteries. In most cases a grid-connected system can utilize the grid itself as an
outlet for surplus energy (check with your local authorities for Net Metering
requirements in your area).
Regardless, all battery charging systems must provide protective measures
for circumstances of stand alone operation (whether it is a stand alone system or a grid connected system operating as a backup power supply).
In most cases the host inverter will serve to protect the batteries from
becoming overcharged if by no other means than that the host inverter will
suspend operation with a high DC voltage disconnect function. Unfortunately
that will also interrupt power to both the loads and the Skystream (which will
cause the Skystream to shut down). The SMA Sunny Island inverter is an
exception as is any inverter that has load shedding capability. If the batteries
reach full charge, the host inverter creates a phase shift which will cause the
Skystream to shut down but continue to support high voltage loads.
It is preferable, however, to avoid shutting down the Skystream. Not only
does it result in lower productivity, cyclical shut downs of the Skystream will
increase the wear and tear on the turbine itself.
A common form of regulation that has been used throughout the history
of small wind turbine battery charging systems is equally effective with the
Skystream. A secondary diversion load and diversion load control on the
DC bus can both allow the turbine to ride through the full charge condition,
regardless of duration, and maintain availability. It also provides an outlet for
useful energy that is otherwise lost if the turbine stops operating. The most
common form of diversion load is a simple resistive heater for either air or
water, and although a basic voltage-dependent switch can serve to “regulate”
the flow of electricity to the battery, a pulse width modulating (PWM) style
of switch is much more effective at maintaining battery state of charge and
diverting only an amount of energy that would cause the batteries to exceed
full charge voltage.
Special care should be given to the selection of diversion load and diversion load controller. The capacity of the load and controller must be
matched to the maximum continuous output of the turbine and the resistance of the load must be appropriate for the operating voltage of the batteries.
Southwest Windpower makes a suitably-sized load that is ordinarily used
in conjunction with the Whisper 500 battery charging turbine. That and a
high capacity diversion load controller such as a Morningstar TriStar60, a
Xantrex C40 or C60 can complete the diversion control system. Various
combinations of load and controllers can be combined in parallel depending on component capacity and operating voltage to achieve the net diversion capacity required, but for simplicity a single PWM controller and load
is desirable.
Wire Sizing
These wire sizing directions are for SINGLE Skysteam turbine installations
which are home-run to a main service panel. DO NOT attempt to use these
wire sizing instructions for a Skystream connected to a sub-panel or for
multiple Skystreams together.
Note that the largest wire size that may be connected to the Skystream
yaw terminals is #8 AWG (6 mm2). For installations requiring a larger wire
size (because of distance) Southwest Windpower recommends using a disconnect switch box installed between the tower and utility panel to transition to a larger wire size.
To determine the appropriate wire size, measure the total distance from the
turbine to the electrical utility panel including the tower height and refer to
the tables below.
Table 2 includes maximum wire length information for wire sizes #8 AWG
(10 mm2) and smaller without transitioning to a larger wire size. Select the
appropriate wire size based on the total wire length and Skystream voltage
configuration (240 VAC, split phase or 120 VAC, 1 phase).
Skystream 3.7® Battery Charging Guide, Rev B 7
Table 2
Wire Size
120/240 VAC, Split Phase
120 VAC, 1 Phase
4 AWG (25 mm )
See Table 2
See Table 3
6 AWG (16 mm2)
See Table 2
See Table 3
8 AWG (10 mm )
303 ft (92 m)
245 ft (75 m)
10 AWG (6 mm2)
190 ft (58 m)
155 ft (47 m)
12 AWG (4 mm2)
120 ft (37 m)
95 ft (29 m)
75 ft (23 m)
60 ft (18 m)
2
2
14 AWG (2.5 mm )
2
Note: If needed, the 75 ft (23 m) length of #8 AWG (10 mm2) wire may be
shortened and the larger gauge wire lengthened a corresponding amount.
However, DO NOT lengthen the #8 AWG (10 mm2) wire and lengthen the
larger gauge wire.
Use copper conductors only - Minimum wire temperature rating is 75° C (167° F).
Distance and wire size for 120/240 VAC, split phase systems based on
2400 watt power production and 2% (L-L) line loss. Distance and wire
size for 120 VAC systems based on 1500 watt power production and 4%
(L-L) line loss.
Table 3
System Voltage
Maximum Wire
Length
# 8 AWG
# 6 AWG
# 4 AWG
120/240 VAC,
Split Phase
650 ft (198 m)
75 ft (22.9 m)
--------------
575 ft (175 m)
120/240 VAC,
Split Phase
435 ft (13 m)
75 ft (22.9 m)
360 ft (110 m)
--------------
120 VAC, 1 Phase
600 ft (180 m)
75 ft (22.9 m)
--------------
525 ft (160 m)
120 VAC, 1 Phase
405 ft (123 m)
75 ft (22.9 m)
330 ft (100 m)
--------------
Warning: For your safety, make sure power is turned off
before working on any and all electrical connections.
If the required wire length is greater than can be accomplished with #8
AWG (10 mm2) wire, refer to Table 3. This table includes wire size information for installations requiring a transition to a wire size larger than #8 AWG.
Table 3 provides for a 75 ft (23 m) length of # 8 AWG (10 mm2) wire to be
run from the Skystream yaw to a disconnect switch box and a length of #4
or # 6 AWG (25 or 16 mm2) wire to be run from the disconnect switch box
8 Skystream 3.7® Battery Charging Guide, Rev B
to the utility panel. Select the appropriate wire size combination based on
the wire run length and Skystream voltage configuration.
1
2
3
4
7
6
5
8
SPAN BETW'N TOWER TOP TO
USABLE AWG FOR 4%
AC MAIN PANEL (FOR CU
LINE-NEUTRAL VOLTAGE
BATTERY CHARGING WITH A SINGLE PHASE
WIRE), ASSUMING 120VAC (LDROP BETW'N TURBINE
N) AT INVERTER TERMINALS,
AND SUB SERVICE PANEL
120 VAC SKYSTREAM AND A SINGLE 120 VAC
PEAK OUTPUT 1.5kW
INVERTER AND APPENDIX
NOT GRID CONNECTED
623 FT.
4 AWG
A: ELECTRICAL SCHEMATICS
A
"SKYSTREAM"
WIND TURBINE
391 FT.
6 AWG
245 FT.
8 AWG
155 FT.
10 AWG
95 FT.
12 AWG
NACELLE
10
B
NACELLE
CHASSIS
ELECTRICALLY
CONNECTED
TO YAW, WHICH
MUST BE
ELECTRICALLY
C CONNECTED TO
THE TOWER
WIRE SIZE
DEPENDENT ON
LENGTH BETWEEN
TURBINE AND
UTILITY (SERVICE
PANEL) CONNECTION
B
INVERTER
8
A
200 A
FUSE
+
AC HOT IN
AC NEUTRAL IN
CHASSIS GROUND
AC HOT OUT
-
C
AC NEUTRAL OUT
10
L1
N
G
D
L1 (black)
L1
L2
AC SERVICE
PANEL
N
N (white)
L2
MAIN
BREAKER
G
20 A
L1
BAT +
G (green)
GROUND
LEVEL
COMMON
-
D
GND
G
DEDICATED
WIND
POWER SYSTEM
KILOWATT-HOUR
METER
3
(OPTIONAL)
HOUSEHOLD
LOADS
N
G
6" MIN.
TOWER
GROUND
SYSTEM
LOAD +
20 A
12 INCH MAX.
10 INCH MIN.
E
DIVERSION LOAD CONTROLLER
DIVERSION LOAD
100 A
G N L1
9
5
SAFETY SWITCH
2-POLE, 30A, 240VAC,
SQUARE D #DU221RB
AT TOWER BASE
100 A
4
2
6
RUN FROM JNC. BOX AT
TOWER BASE TO HOME
24 INCH MIN.
*
7
+
-
BATTERY
BANK
E
NOTES:
1.
2.
F
EQUIPMENT SHALL BE INSTALLED IN ACCORDANCE WITH LOCAL RULES AND REQUIREMENTS.
PROVIDE WARNING SIGN READING "WARNING-ELECTRIC
SHOCK HAZARD-DO NOT TOUCH TERMINALS - TERMINALS ON BOTH THE LINE
AND LOAD MAY BE ENERGIZED IN THE OFF POSITION".
3.
LABEL "WIND POWER SYSTEM DEDICATED kW-HR METER".
4.
LABEL SWITCH AS "WIND GENERATOR SAFETY DISCONNECT SWITCH;
REMOVING AC POWER TO TURBINE ACTIVATES ITS SAFETY BRAKE".
5.
LABEL "REMOVING AC POWER TO TURBINE ACTIVATES ITS SAFETY BRAKE".
6.
ONLY COPPER WIRES MUST BE USED AT TURBINE TERMINALS.
7.
USE APPROPRIATE AWG WIRE FOR BATTERY CONNECTIONS
8.
INVERTER CONNECTIONS ARE FOR ILLUSTRATION PURPOSES ONLY. REFER TO INVERTER OWNER'S
MANUAL FOR SPECIFIC CONNECTION INSTRUCTIONS
9.
LIGHTENING SURGE SUPPRESION SHOULD BE INSTALLED ACCORDING TO RECOEMNDATIONS IN THE
SKYSTREAM OWNER'S MANUAL
10.
THE MAXIMUM WIRE SIZE THAT CAN BE ACCOMODATED AT THE TURBINE CONNECTION IS #8 AWG.
TRANSITION TO LARGER WIRE CAN BE AT THE TURBINE OR AT THE TOWER BASE TO MINIMISE VOLTAGE
DROP.
TOWER
FOUNDATION TOP
SURFACE TO BE
MIN. 6" ABOVE
GROUND LVL.
REFER TO SWWP
FOUNDATION DWG.
1" DIA. SCHED. 40
RIGID PVC CONDUIT;
SUNLIGHT RESISTANT;
UL LISTED
1
2
F
Southwest Windpower
Flagstaff, Arizona U.S.A.
Battery charging with a single
phase inverter
doc. n° 3-CMLT-1088
3
4
5
6
7
© 2012 Southwest Windpower, Inc.
All Rights Reserved
scale 1 : 1 rev. C
size A sheet 5 of 5
Figure 1: Option B - 120/240 volt (US residential voltage) skystream with two 120 VAC inverters
BATTERY CHARGING USING A 240 VAC
SKYSTREAM AND TWO 120 VAC INVERTERS
IN PARALLEL AND GRID CONNECTED
GROUND ROD
DIVERSION LOAD CONTROLLER
AND DIVERSION LOAD
BAT +
WIRE SIZE DEPENDENT ON
LENGTH BETWEEN TURBINE
AND UTILITY (SERVICE
PANEL) CONNECTION. SEE
TABLE ABOVE.
100A
FUSE
DIVERSION
LOAD
9
10
SAFETY SWITCH
2-POLE, 30A, 240VAC,
SQUARE D #DU221RB
AT TOWER BASE
4
6
TOWER
G N L2 L1
5
7
D
L1
L2
12 INCH MAX.
10 INCH MIN.
GROUND
LEVEL
3/24/09
C
Generalize and revise wire size table
22 Oct 9
SPAN BETW'N TOWER TOP TO AC
MAIN PANEL (FOR CU WIRE),
ASSUMING 240VAC (L-L) AT AC
MAIN PANEL, TURBINE OUTPUT
2.4kW
USABLE AWG FOR 2%
LINE-LINE VOLTAGE
RISE BETW'N TURBINE
AND AC SUB SERVICE
PANEL
763
480
303
190
119
4 AWG
6 AWG
8 AWG
10 AWG
12 AWG
FT.
FT.
FT.
FT.
FT.
NEU IN 1
AC OUT
AC GND
INVERTER #2
MAIN
BREAKER
AC TERMINAL
BLOCK
BAT +
BAT -
NEU OUT
L2 (red)
L2
AC GND
G (green)
GND
N L1
20 A
AC OUT
L1
L2
MAIN
BREAKER
AC SERVICE
SUB PANEL
120/240V
L2
20 A
AC IN 1
NEU IN 1
L1
DEDICATED
3
WIND
POWER SYSTEM
KILOWATT-HOUR
METER
(OPTIONAL)
C
AC MAIN SERVICE
PANEL 120/240V
STACKING
UTILITY
METER
N
D
G
G
20 A
20 A
E
HOUSEHOLD
LOADS
TOWER
GROUND
SYSTEM
RUN FROM JNC. BOX AT
TOWER BASE TO HOME
24 INCH MIN.
N
240VAC
TO SERVICE
TRANSFORMER,
UTILITY GRID
GROUND
SYSTEM
G
TOWER
FOUNDATION TOP
SURFACE TO BE
MIN. 6" ABOVE
GROUND LVL.
REFER TO SWWP
FOUNDATION DWG.
*
NOTES:
EQUIPMENT SHALL BE INSTALLED IN ACCORDANCE WITH NEC ARTICLE 705.
PROVIDE WARNING SIGN PER NEC 690-17 READING "WARNING-ELECTRIC
SHOCK HAZARD-DO NOT TOUCH TERMINALS - TERMINALS ON BOTH THE LINE
AND LOAD MAY BE ENERGIZED IN THE OFF POSITION".
3.
LABEL "WIND POWER SYSTEM DEDICATED kW-HR METER".
4.
LABEL SWITCH AS "WIND GENERATOR SAFETY DISCONNECT SWITCH;
REMOVING AC POWER TO TURBINE ACTIVATES ITS SAFETY BRAKE".
5.
LABEL "REMOVING AC POWER TO TURBINE ACTIVATES ITS SAFETY BRAKE".
6.
ONLY COPPER WIRES MUST BE USED AT TURBINE TERMINALS.
7.
USE APPROPRIATE AWG WIRE FOR BATTERY CONNECTIONS.
8.
iNVERTER CONNECTIONS ARE FOR ILLUSTRATION PURPOSES ONLY. REFER TO INVERTER OWNER'S
MANUAL FOR SPECIFIC CONNECTION INSTRUCTIONS
9.
LIGHTENING SURGE SUPPRESION SHOULD BE INSTALLED ACCORDING TO RECOMENDATIONS IN
SKYSTREAM 3.7 OWNER'S MANUAL
10.
THE MAXIMUM WIRE SIZE THAT CAN BE ACCOMODATED AT THE TURBINE CONNECTION IS #8 AWG.
TRANSITION TO A LARGER WIRE CAN BE AT THE TURBINE OR TOWER BASE TO MINIMIZE VOLTAGE
DROP.
1.
2.
1" DIA. SCHED. 40
RIGID PVC CONDUIT;
SUNLIGHT RESISTANT;
UL LISTED
1
A
B
6" MIN.
E
F
APPROVED
10
L1 (black)
G
Add Charge controller, ECO xxxx
NEU OUT
DC
GND
N
N (white)
N
G
BAT -
100A
FUSE
BATTERY
BANK
DATE
4/27/07
5/24/07
ECO 1188
ECO 1212
B
AC TERMINAL
BLOCK
AC IN 1
DC
GND
+
2
NC
A
STACKING
COMMON NEGATIVES
LOAD+
DESCRIPTION
100 A
BATTERY
POSITIVE
B
8
INVERTER #1
G
NACELLE
CHASSIS
ELECTRICALLY
CONNECTED
TO YAW, WHICH
MUST BE
ELECTRICALLY
C CONNECTED TO
THE TOWER
8
REVISIONS
REV.
"SKYSTREAM"
WIND TURBINE
NACELLE
7
6
5
HOUSEHOLD LOADS
A
4
100 A
3
60 A
2
60 A
1
Proprietary rights are included in the information disclosed herein. This information is
submitted in confidence and neither the document nor the information disclosed herein shall be reproduced or transferred to other documents for manufacturing or for any
other purpose except as specifically authorized in writing by Southwest Windpower.
2
3
4
5
Unless otherwise specified CAD-generated drawing
dimensions are in mm. do not manually update
tolerances are :
distances
angles
APPROVALS
DATE
X. ± .5
± 30 '
DRAWN J.M. Yeager 22 Oct 9
.X ± .2
CHECKED
.XX ± .1
Skystream MATERIAL
-NEXT ASSY USED ON FINISH
APPLICATION DO NOT SCALE DRAWING
1 Skystream 3.7® Battery Charging Guide, Rev B - APPENDIX A: ELECTRICAL SCHEMATICS
RESP ENG
MFG ENG
QUAL ENG
Southwest Windpower
Flagstaff, Arizona U.S.A.
Battery charging in a 240V
Grid Tied system
with two 120V inverters
CAD file :
doc. n° 3-CMLT-1088
scale none rev. C size A3 sheet 1 of 5
Figure 2: Option C - 120/240 volt (US residential voltage) Skystream with 120 VAC inverter and transformer
2
3
4
REV.
C
BATTERY CHARGING USING A 240 VAC
SKYSTREAM A SINGLE 120 VAC INVERTER
A TRANSFORMER AND GRID CONNECTED
A
NACELLE
"SKYSTREAM"
WIND TURBINE
AC SERVICE
SUB PANEL
120/240V
WIRE SIZE DEPENDANT ON
LENGTH BETWEEN TURBINE AND
UTILITY (SERVICE SUB PANEL)
CONNECTION. SEE TABLE ABOVE.
9
L1
L2
8 AWG
190 FT.
10 AWG
119 FT.
12 AWG
AC HOT OUT
AC NEUTRAL OUT
CHASSIS GROUND
AC NEUTRAL IN
AC HOT IN
N
7
L2 (red)
L2
G (green)
GND
DEDICATED
WIND
POWER SYSTEM
KILOWATT-HOUR
METER
GROUND
LEVEL
L2
TOWER
GROUND
SYSTEM
RUN FROM JNC. BOX AT
TOWER BASE TO HOME
C
G
Bat +
Load +
Common
-
G
N
AC MAIN SERVICE
PANEL 120/240V
D
MAIN
BREAKER
L2
20 A
GROUND
SYSTEM
3
6" MIN.
E
-
DIVERSION LOAD CONTROLLER
DIVERSION LOAD
-
BATTERY
BANK
120V
L1
G
200A
FUSE
+
G
L1 (black)
12 INCH MAX.
10 INCH MIN.
A
B
10
INVERTER
8
+
N
N (white)
N
G
D
6 AWG
303 FT.
20 A
10
SAFETY SWITCH
2-POLE, 30A, 240VAC,
SQUARE D #DU221RB
AT TOWER BASE
4 AWG
480 FT.
100 A
6
G N L2 L1
5
763 FT.
120:240 3KVA 1V MAX.
RISE AUTOTRANSFORMER
20 A
HOUSEHOLD LOADS
4
2
APPROVED
23 Oct 9
USABLE AWG FOR 2%
LINE-LINE VOLTAGE
DROP BETW'N TURBINE
AND AC SUB SERVICE
PANEL)
40 A
40 A
NACELLE
CHASSIS
ELECTRICALLY
CONNECTED
TO YAW, WHICH
MUST BE
ELECTRICALLY
C CONNECTED TO
THE TOWER
DATE
SPAN BETW'N TOWER TOP TO
AC SERVICE PANEL (FOR CU
WIRE), ASSUMING 240VAC (LL) AT AC PANEL, TURBINE
OUTPUT 2.4kW
L1
MAIN
BREAKER
8
REVISIONS
GENERALIZATION AND WIRE SIZE TABE REVISION
L1
N
20 A
HOUSEHOLD LOADS
B
7
6
5
100 A
1
UTILITY
METER
E
N
24 INCH MIN.
G
G
F
*
TOWER
FOUNDATION TOP
SURFACE TO BE
MIN. 6" ABOVE
GROUND LVL.
REFER TO SWWP
FOUNDATION DWG.
EQUIPMENT SHALL BE INSTALLED IN ACCORDANCE WITH NEC ARTICLE 705.
PROVIDE WARNING SIGN PER NEC 690-17 READING "WARNING-ELECTRIC
SHOCK HAZARD-DO NOT TOUCH TERMINALS - TERMINALS ON BOTH THE LINE
AND LOAD MAY BE ENERGIZED IN THE OFF POSITION".
3.
LABEL "WIND POWER SYSTEM DEDICATED kW-HR METER".
4.
LABEL SWITCH AS "WIND GENERATOR SAFETY DISCONNECT SWITCH;
REMOVING AC POWER TO TURBINE ACTIVATES ITS SAFETY BRAKE".
5.
LABEL "REMOVING AC POWER TO TURBINE ACTIVATES ITS SAFETY BRAKE".
6.
ONLY COPPER WIRES MUST BE USED AT TURBINE TERMINALS.
7.
USE APPROPRIATE AWG WIRE FOR BATTERY CONNECTIONS.
8.
iNVERTER CONNECTIONS ARE FOR ILLUSTRATION PURPOSES ONLY. REFER TO INVERTER OWNER'S
MANUAL FOR SPECIFIC CONNECTIONS
9.
LIGHTENING SURGE SUPPRESSION SHOULD BE INSTALLED ACCORDING TO RECOMENDATIONS IN
SKYSTREAM OWNER'S MANUAL
10.
THE MAXIMUM WIRE SIZE THAT CAN BE ACCOMODATED AT THE TURBINE CONNECTION IS #8AWG.
TRANSITION TO LARGER WIRE CAN BE AT THE TURBINE OR TOWER BASE TO MINIMIZE VOLTAGE DROP.
1" DIA. SCHED. 40
RIGID PVC CONDUIT;
SUNLIGHT RESISTANT;
UL LISTED
1
240VAC
TO SERVICE
TRANSFORMER,
UTILITY GRID
NOTES:
1.
2.
2
3
4
5
6
GROUND
SYSTEM
E
F
Southwest Windpower
Flagstaff, Arizona U.S.A.
Battery charging with a 120VAC
inverter, 120/240V Autotransformer
with 240VAC Grid Tie
doc. n° 3-CMLT-1088
7
scale 1 : 1 rev. C
size A sheet 3 of 5
Skystream 3.7® Battery Charging Guide, Rev B - APPENDIX A: ELECTRICAL SCHEMATICS 2
Figure 3: Option D - 120 volt Skystream with single 120 VAC inverter
1
2
3
4
7
6
5
SPAN BETW'N TOWER TOP TO
AC MAIN PANEL (FOR CU
WIRE), ASSUMING 120VAC (LN) AT INVERTER TERMINALS,
PEAK OUTPUT 1.5kW
USABLE AWG FOR 4%
LINE-NEUTRAL VOLTAGE
DROP BETW'N TURBINE
AND SUB SERVICE PANEL
623 FT.
4 AWG
391 FT.
6 AWG
245 FT.
8 AWG
155 FT.
10 AWG
95 FT.
12 AWG
BATTERY CHARGING WITH A SINGLE PHASE
120 VAC SKYSTREAM AND A SINGLE 120 VAC
INVERTER AND NOT GRID CONNECTED
A
"SKYSTREAM"
WIND TURBINE
8
NACELLE
10
B
NACELLE
CHASSIS
ELECTRICALLY
CONNECTED
TO YAW, WHICH
MUST BE
ELECTRICALLY
C CONNECTED TO
THE TOWER
WIRE SIZE
DEPENDENT ON
LENGTH BETWEEN
TURBINE AND
UTILITY (SERVICE
PANEL) CONNECTION
B
INVERTER
8
A
200 A
FUSE
+
AC HOT IN
AC NEUTRAL IN
CHASSIS GROUND
AC HOT OUT
-
C
AC NEUTRAL OUT
10
L1
N
G
D
L1 (black)
L1
L2
AC SERVICE
PANEL
N
N (white)
L2
MAIN
BREAKER
G
20 A
L1
DIVERSION LOAD CONTROLLER
DIVERSION LOAD
100 A
G N L1
9
5
SAFETY SWITCH
2-POLE, 30A, 240VAC,
SQUARE D #DU221RB
AT TOWER BASE
100 A
4
2
6
BAT +
G (green)
12 INCH MAX.
10 INCH MIN.
GROUND
LEVEL
G
DEDICATED
WIND
POWER SYSTEM
KILOWATT-HOUR
METER
3
(OPTIONAL)
-
D
HOUSEHOLD
LOADS
N
G
TOWER
GROUND
SYSTEM
COMMON
GND
6" MIN.
E
LOAD +
20 A
RUN FROM JNC. BOX AT
TOWER BASE TO HOME
24 INCH MIN.
*
7
+
-
BATTERY
BANK
E
NOTES:
1.
2.
F
EQUIPMENT SHALL BE INSTALLED IN ACCORDANCE WITH LOCAL RULES AND REQUIREMENTS.
PROVIDE WARNING SIGN READING "WARNING-ELECTRIC
SHOCK HAZARD-DO NOT TOUCH TERMINALS - TERMINALS ON BOTH THE LINE
AND LOAD MAY BE ENERGIZED IN THE OFF POSITION".
3.
LABEL "WIND POWER SYSTEM DEDICATED kW-HR METER".
4.
LABEL SWITCH AS "WIND GENERATOR SAFETY DISCONNECT SWITCH;
REMOVING AC POWER TO TURBINE ACTIVATES ITS SAFETY BRAKE".
5.
LABEL "REMOVING AC POWER TO TURBINE ACTIVATES ITS SAFETY BRAKE".
6.
ONLY COPPER WIRES MUST BE USED AT TURBINE TERMINALS.
7.
USE APPROPRIATE AWG WIRE FOR BATTERY CONNECTIONS
8.
INVERTER CONNECTIONS ARE FOR ILLUSTRATION PURPOSES ONLY. REFER TO INVERTER OWNER'S
MANUAL FOR SPECIFIC CONNECTION INSTRUCTIONS
9.
LIGHTENING SURGE SUPPRESION SHOULD BE INSTALLED ACCORDING TO RECOEMNDATIONS IN THE
SKYSTREAM OWNER'S MANUAL
10.
THE MAXIMUM WIRE SIZE THAT CAN BE ACCOMODATED AT THE TURBINE CONNECTION IS #8 AWG.
TRANSITION TO LARGER WIRE CAN BE AT THE TURBINE OR AT THE TOWER BASE TO MINIMISE VOLTAGE
DROP.
TOWER
FOUNDATION TOP
SURFACE TO BE
MIN. 6" ABOVE
GROUND LVL.
REFER TO SWWP
FOUNDATION DWG.
1" DIA. SCHED. 40
RIGID PVC CONDUIT;
SUNLIGHT RESISTANT;
UL LISTED
1
2
F
Southwest Windpower
Flagstaff, Arizona U.S.A.
Battery charging with a single
phase inverter
doc. n° 3-CMLT-1088
3
4
5
6
3 Skystream 3.7® Battery Charging Guide, Rev B - APPENDIX A: ELECTRICAL SCHEMATICS
7
scale 1 : 1 rev. C
size A sheet 5 of 5
Southwest Windpower Inc.
1801 West Route 66
Flagstaff, Arizona 86001 USA
t: +1 928.779.9463
f: +1 928.779.1485
www.windenergy.com
Southwest Windpower GmbH
Mannesmannstr. 6
50996 Cologne Germany
t: +49 (0) 221 16 53 94 50