Survey
* Your assessment is very important for improving the workof artificial intelligence, which forms the content of this project
* Your assessment is very important for improving the workof artificial intelligence, which forms the content of this project
IN THE HIGH COURT OF NEW ZEALAND WHANGAREI REGISTRY CIV-2014-488-0122 [2015] NZHC 884 BETWEEN DEREK PETER WHEELDON AND CAROL ANN WHEELDON, ANTHONY JOHN BUTCHER AND RUTH BARBARA ROGERS, LARRY LAWRENCE SMALL AND KM TRUSTEES SERVICES LTD, IVOR ANTHONY MILLINGTON AND NEVILLE EADE Plaintiffs AND BODY CORPORATE 342525 Defendant AND ROBYN KATHLEEN STENT Counterclaim Defendant Hearing: 2-6, and 10-11 March 2015 Counsel: B E Brill for the Plaintiffs and Counterclaim Defendant TJG Allan and TJP Gavigan for the Defendant Judgment: 30 April 2015 INTERIM JUDGMENT OF MUIR J This judgment was delivered by me on 30 April 2015 at 4.30 pm pursuant to Rule 11.5 of the High Court Rules. Registrar/Deputy Registrar Date:…………………………. Solicitors: B E Brill Ltd, Kerikeri Grove Darlow & Partners, Auckland WHEELDON v BODY CORPORATE 342525 [2015] NZHC 884 [30 April 2015] Introduction [1] Yet again the Courts are faced with a Body Corporate whose members have strongly divergent views as to how it should respond to alleged weathertightness issues. Together, they own the 22 apartments comprising the Bridgewater Bay Development adjacent to an estuary on the outskirts of Paihia. The development was constructed between 2003 and 2004. [2] In response to a detailed report by a specialist investigator 17 of the unit owners wish to proceed with a comprehensive repair which would, among other things, require regrading each of the apartment decks and remodelling (or replacing) existing joinery suites on the northern façade of the development. The cost is substantial. Although originally budgeted at approximately $1.7 million, recent escalation in building costs and the absence of a competitive local market has seen that budget increase to in excess of $3 million. During the course of the trial this option came to be identified by the defendant as the “holistic repair”. It would involve delivery of a development fully compliant with current Building Code requirements and, says the Body Corporate, would mitigate, as fully as possible, the current stigma attaching to the building. [3] The five plaintiffs, or at least those who owned apartments at the time, were initially supportive of (or passively accepted) the holistic repair option. However, with what they say is better information and in the face of escalating costs, they now submit that the Body Corporate’s proposed works are ultra vires and/or have not been properly authorised. They allege “capture” of the Body Corporate by the Auckland based “leaky building industry” and cupidity on the part of individual consultants. They contend for a limited or “targeted” repair, deny that there are any systemic problems with the development and say that all that is currently required is remedial work to the two timber-framed “penthouses” which sit on the fourth floor of the building. They say that such work should be paid for by the owners of those units and that although other elements of the building, and, in particular, deck membranes for the remaining 18 apartments, may be nearing the end of their service life, all that is, in due course, required is to lift and replace the membranes and tiles at a cost unlikely to exceed $6,000 per unit. [4] In addition to their attacks on the vires and procedural regularity of the Body Corporate’s repair plan, the plaintiffs also challenge various payments which the Body Corporate has made and levies which it has raised in the context of investigating defects and developing its plan. They say that the Body Corporate has unlawfully “raided” a long term maintenance fund and that other payments were similarly in breach of the Unit Titles Act 2010 (UTA 2010). [5] Each of the plaintiffs is, in turn, the subject of a counterclaim for outstanding levies which is met by a comprehensive challenge to the legality and procedural regularity of such levies. There are multiple individual components to that challenge. [6] The counterclaim defendant, Ms Stent, is a recent purchaser, having acquired her apartment in March 2014 (settled July 2014) with full knowledge of the alleged defects and at a price reflecting what was, at least at that stage, understood to be the likely costs of repair in accordance with the Body Corporate’s plans. She is the wife of counsel for the plaintiff. She is sued for outstanding levies on the same basis as are the plaintiffs on the defendant’s counterclaim. In its evidence the Body Corporate claims that all of the current dissention, the voluminous exchanges of correspondence which have occurred, the significant costs which have attended major High Court litigation, the resultant delays in undertaking the remedial work and the cost escalations which have followed can all be dated back to Ms Stent’s acquisition of her unit. It expresses a high degree of frustration with the current position. Background [7] Because specific design details relating to the development are more conveniently discussed in the section of the judgment relating to the requirement for repair or maintenance, I provide only a brief overview at this stage. Likewise, the history of the problems with the development and the Body Corporate’s response, culminating in its various actions and resolutions, are better addressed in the context of the plaintiffs’ specific challenges. [8] The Bridgewater development comprises four levels with the ground floor (identified as level one in the proceedings) providing car parking, storage and entry lobby. Each of levels two and three comprise 10 apartments, eight with two bedrooms and two of one bedroom. One bedroom apartments are centrally located, with the building “fanning” out either side in a gentle north facing arc. To either side of the one bedroom apartments are four two bedroom apartments. All apartments therefore enjoy views of the adjacent estuary and beyond from a deck on their northern side. Levels one, two and three are constructed of in situ concrete and plastered concrete block. Level four consists of two three bedroom apartments (referred to by the plaintiffs as “penthouses”). Their construction consists of monolithic cladding over timber framing. A number of issues emerge in relation to the adequacy of that construction. [9] The development follows a “wedding cake” design whereby each of the level three and four apartments are stepped back with their decks comprising the roofs or part roofs of the apartments below. The effect is to reduce the overall scale and bulk of the development and to maximise sun, privacy and fire separation. [10] Aesthetically, the central portion of the development is characterised by three “fins” which are clad in an aluminium composite known as ACP panels. The centre fin starts at level four and provides privacy between the two penthouse decks. In turn it runs through to the car parking level providing the same privacy to the one bedroom apartments on levels two and three. Additional “fins” pass through levels two and three marking the other “boundary” of the one bedroom apartments. Decks to the two bedroom apartments are in turn separated by plastered masonry walls. [11] The northern façade of the building (at apartment level) is substantially glazed but each of the two bedroomed apartments also includes timber framed “titan board” infill panels adjacent to the master bedroom. [12] Guttering both from the roof and decks is internal through the walls which separate each of the decks. Connection to the relevant downpipes from the level four decks is through drains in the relevant level three apartment ceilings. This internal reticulation system has given rise to significant problems with water penetration through level three ceilings and high moisture readings at the level one “rain heads” indicating that, somewhere in this encased system, leaking is occurring. [13] Problems with the development have been evident for some time. As early as 2006 the plaintiff Mr Millington, who purchased apartment 307 from the developer, was experiencing moisture problems in his ceiling which increased to the point that water began to start “seeping down [his] walls and into [his] carpet”. The likely source appeared to be the penthouse above whose owners he said had “long been complaining about the ponding of rain water on the decks”. [14] decks. As a result, certain remedial works were undertaken to the two penthouse However, problems continued and after a further lengthy period of complaints by Mr Millington he indicated an intention to bring a claim before the Weathertight Homes Resolution Service (WHRS). That was not pursued because of concerns about the development acquiring a leaky building stigma and eventually the immediate problem affecting Mr Millington appears to have been resolved. [15] Long term (albeit not continuous) committee member, Mr Andrews, deposes, however, that in the period prior to the January 2013 AGM he became aware, through discussions with other owners and as a result of his own observations, that there were a number of issues in respect of decks within the development, not limited to those at level four. These included water ponding, cracked tiles, some membrane failure and water cascading from the level three roof gutters onto the decks of level two during heavy rainfall events. [16] These concerns were ventilated at the 2013 AGM which resolved that the Committee be tasked to engage a consultant to investigate further. [17] AA Home Inspections (2000) Limited (AA) produced a report dated 22 April 2013. Its brief was limited to investigation of the level four decks and any other deck which the owners requested be inspected. In the event, six decks were examined by it. The inspection was visual only with no invasive testing. The report identified examples of water ponding and a requirement for remediation, including where applicable, establishment of positive falls to deck outlets. [18] Receipt of this report alerted Mr Andrews and others to what they considered may be more significant problems with the development. Those concerns were compounded by the re-emergence of moisture problems in the ceilings of three of the third floor apartments. AA was commissioned to provide a supplementary report following removal of sections of the apartment ceilings and reported evidence of current moisture ingress. [19] Mindful of impending limitation periods and on the advice of the Body Corporate Secretary, the Committee, which at that stage comprised Ms Gray and Ms Barr (supported by Mr Andrews and Mr Nimmo) then approached specialist leaky building solicitors Grimshaw & Co for advice. That firm recommended that a comprehensive review of the development be undertaken by Mr Andrew Gray of Origin Construction Consultants Limited (Origin) (now Veron Limited). Such investigation, which included invasive testing, took place on 10 and 11 October 2013 with an extensive report and recommendations provided on 18 October 2013 (the Origin Report). In summary, Mr Gray identified what he considered to be numerous original construction and design defects in the development. He proposed a comprehensive repair plan (the Origin Repair Plan) consistent with current Building Code requirements. The Origin Repair Plan represents the holistic repair advocated for by the Body Corporate. Substantive components of that repair plan involve work within the surveyed boundaries of individual units, that is, on private as opposed to common property. This includes establishing code compliant falls to the decks and all the associated works which regrettably derive from that. In that respect the Body Corporate invokes s 138(1)(d) of UTA 2010. Application of that section and, in particular, its interrelationship with s 80(1)(g) is a central issue in the case. [20] The Origin Report, together with the further documents described later in this judgment, was then provided to the owners. An urgent Extraordinary General Meeting (EGM) was convened on 9 November 2013 to discuss its implications. The matters decided at that meeting and the actions subsequently taken by the Committee and the Body Corporate are discussed in detail at [177] to [183] of this judgment. Suffice to say, that the battle lines are now drawn between the 17 owners who wish to proceed with the “holistic” repair option and the five owners who favour a targeted approach. Preliminary [21] In my Minute No 2, dated 2 March 2015, I recorded an oral application at the commencement of trial by counsel for the defendant to amend paragraph 14 of the defendant’s statement of defence which was formerly pleaded in terms of an admission with stated reliance on the full term of the minutes of the 9 November 2013 EGM. Mr Allan for the defendant indicated that this was a mistake and that the appropriate pleading was a denial coupled with reliance on the minutes. He said that the admission was inappropriate because paragraph 14 of the statement of claim alleged a delegation to investigate defects, but that word was not used in the relevant resolution and because the delegation was, in reality, an instruction. At the time I indicated that I was not persuaded that there would be any substantial difference in the evidence if the admission were withdrawn, but acceded to Mr Brill’s request that the matter be revisited in final submissions. At that point Mr Brill maintained his objection although he was unable to identify any specific prejudice. I allow the amendment. Interim decision [22] Following closing submissions on 10 and 11 March 2015 I received a memorandum from counsel for the defendant inviting the Court to issue, pursuant to r 11.2, an interim decision restricted to the plaintiff’s first cause of action (declarations and injunctive relief relating to the scope of intended remedial work) and leaving the second cause of action and counterclaims (propriety of and nonpayment of levies) for later determination if required. This invitation followed unsuccessful discussions between the parties about the basis on which these claims might be adjourned by consent. There has been no response to the defendant’s memorandum. [23] In my view the defendant’s proposal is sensible. The key issue facing the Body Corporate and its members is the vires of the Body Corporate’s intended remediation plans. Resolving that “bottleneck” is essential to finalising the plans, obtaining tenders and undertaking the work. That, in turn, allows the Body Corporate to quantify the claims which it and all 22 owners have progressed against parties whom they regard as responsible for the building’s defects. It places at a premium swift delivery of judgment and resolution of any appeals. An immediate focus on the key issues serves that purpose. [24] Moreover if (as I find) the Body Corporate’s intended plans are lawful and if such judgment is either accepted or ultimately upheld on appeal, I consider there to be a high probability that the many subsidiary issues relating to the propriety of individual payments and levies will be self-resolving. For example, if the development is indeed to be fully remediated to current code standards, arguments as to whether existing consultant payments were properly made from what the plaintiffs claim is a long term maintenance fund within the terms of UTA 2010 (but which the defendant denies was ever constituted as such) are likely to be academic. Likewise, if a comprehensive repair is to take place, there are likely to be higher priorities than whether the procedural requirements associated with an existing levy have been satisfied. [25] Specifically, the defendant’s memorandum suggests that, following determination of the first cause of action, the parties be given the opportunity to resolve the second cause of action and counterclaim and that, only in default of that occurring, would the Court be invited to give judgment on them. The defendant suggests the right to seek a determination “after 10 working days following the determination of the first cause of action”. This approach seems to me to be a practical one, although the 10 day suggested period should, in my view, be enlarged to 30 working days so that the issue can be considered in conjunction with appeal rights. Section 138(1)(d) UTA 2010. Interrelationship with s 80(1)(g) [26] Section 138(1)(d) of the UTA 2010 provides: 138 Body Corporate duties of repair and maintenance (1) The body corporate must repair and maintain – … (d) any building elements and infrastructure that relate to or serve more than 1 unit. [27] Section 80(1)(g) in turn provides: 80 Responsibilities of owners of principal units (1) An owner of a principal unit – … (g) [28] must repair and maintain the unit and keep it in good order to ensure that no damage or harm, whether physical, economic, or otherwise, is, or has the potential to be, caused to the common property, any building element, any infrastructure, or any other unit in the building: Central to the plaintiffs’ case is the proposition that, other than in what Mr Brill describes as a “Berachan type case”,1 the duties imposed on the Body Corporate under s 138(1)(d) are subordinated to the duties imposed on the unit owner under s 80(1)(g) in the sense that, only in the event of default by the unit owner in his or her repair and maintenance obligations, does the Body Corporate have the duty (and associated power) to effect the repair. In the case of building elements requiring such repair, that would necessarily involve identification by the Body Corporate of the required scope of works, notice to unit holders to undertake the works, monitoring performance of that requirement, in default undertaking the work itself and, in that event, effecting a recovery from the individual unit owner under either s 138(4) or s 127. [29] Berachan concerned the replacement of the roof on a 12-storey property, where only 20 per cent of the roof was common property. The Court of Appeal held that the body corporate was entitled to assume responsibility in relation to the repair and maintenance of unit property provided that duty could be fairly seen as incidental to the duty to maintain and repair common property.2 [30] The Court observed at [4] that had the case arisen under s 138 of the 2010 Act, the Body Corporate would have the obligation to repair and replace the roof. Significantly, the Court of Appeal made that observation despite the fact that s 80(1)(g) of the UTA 2010 would have prima facie applied to the owner of the unit 1 2 Berachan Investments Ltd v Body Corporate 164205 [2012] NZCA 256, [2012] 3 NZLR 72. At [46]. who owned 80 per cent of the roof. Mr Brill’s exception is therefore inevitable in light of the Court of Appeal’s comments. [31] Mr Brill submits that the distinguishing characteristic of the Berachan case is that the building element concerned (the roof) was one which, in the words of the Court of Appeal, “looks and functions like a single entity”. Only by a line on a drawing could the separate components (those forming part of the unit and those comprising common property) be identified. Moreover, the roof was intersected by rain water collection gutters running its length through common and unit property. [32] Beyond this most obvious case, Mr Brill submits that the Body Corporate’s duties under s 138 arise only in the case of unit holder default and, even in that context, require what he terms a “particular and direct relationship” between the relevant building element or infrastructure which requires repair or maintenance and more than one unit in the development. The limits of such “particularity” and “directness” (beyond the Berachan type situation) are not defined. [33] In support of that proposition Mr Brill taps a deep philosophical vein. He invokes Lord Coke’s seventeenth century observation that “a man’s house is his castle … and is his safest refuge”.3 Mr Brill says that, consistent with that philosophy, the legislature must be taken as having preserved maximum sovereignty in the hands of individual unit holders and not to have “gratuitously” moved that sovereignty to the Body Corporate. He adopts a minimalist approach whereby only such sovereignty as he says is “required” to be transferred to the Body Corporate, passes to it. He says that concepts such as uniformity of appearance, consistency of outcome, etc are “commercial values” which must be subordinated to “personal values” such as uniqueness and refuge because “what we are dealing with here are people’s homes”. He invokes s 79(d) of the UTA 2010 in terms that the owner of a principal unit: 79 Rights of owners of principal units An owner of a principal unit — … 3 Semayne’s Case [1604] 5 Co Rep 91a, [1558-1774] All ER Rep 62. (d) [34] is entitled to quiet enjoyment of his or her unit without interruption by other unit owners or occupiers, or the Body Corporate or its agents, except as authorised by this Act or the Regulations. He says that where the Act recognises a joint responsibility on the part of a unit owner and the Body Corporate for repairs and maintenance, its scheme is served by “allowing the owners to be the players and the Body Corporate to be the monitor and referee”. In support of that proposition he submits that: (a) Because full liability for the repair costs will likely fall upon the owner he or she should have the opportunity to choose the contractor and to negotiate the contract details; (b) As the owner will have to live with the outcome on a day to day basis he or she ought to have the first opportunity to propose the nature, extent and sensory impact of a repair that is to be introduced into their own home; (c) The “right to repair” is a standard incident of property rights and would ordinarily accompany the unit owner’s indefeasible title and such a deeply ingrained right should be ousted only where the law and the circumstances cannot reasonably permit any other course; (d) The Body Corporate has less flexibility in relation to repair/maintenance in that it has no power to pursue a repair that involves betterment, or that extends to any in-unit items other than communal elements; and (e) Issues arise regarding the dispossession of owners for lengthy periods. While ss 138(3) and 80(1)(a)(ii) of the UTA 2010 grant the Body Corporate the right to obtain access at all reasonable hours and after giving reasonable notice to effect repairs and maintenance on private property, those powers fall well short of the lengthy periods of dispossession which a body corporate’s intended repair plan may involve. [35] I am unable to accept this primary submission which underpins much of the plaintiffs’ approach in this litigation. [36] The UTA 2010 was passed against a background of tension within the authorities about the powers of a body corporate to undertake work within unit boundaries. In Body Corporate 188529 v North Shore City Council (Sunset Terraces)4 Heath J identified a clear distinction between common and private property rights, holding that the Unit Titles Act 1972 contemplated corporate responsibility for the maintenance and repair of common property only. In that case the relevant plan had identified the boundary between private and common property as the “external face of exterior walls and glass adjoining common property in accessory units and to the centre line and walls between adjoining units”. So the outside face of each exterior wall was part of an individual unit. On that basis Heath J found that an amendment to r 2(b) of the default rules, whereby the Body Corporate assumed an obligation to keep in a good state of repair the exterior and roof of the building, was ultra vires the 1972 Act.5 [37] By contrast, Harrison J in Young & Ors v Body Corporate 1200666 adopted a more expansive role for the Body Corporate. In circumstances of disunity among the owners (which closely mirror those in the present case) and where a majority of owners contemplated a “complete and bespoke upgrade of the whole complex”,7 whereas the plaintiffs favoured “targeted repairs based on the individual needs of each unit”,8 his Honour held that the unusual configuration of the complex (a “wedding cake” structure again emulated in the present case) required the Body Corporate to repair parts of the exterior that were not common property. His Honour based that decision on the fact that leakage through a failure to keep the exterior in good condition placed at risk the development as a whole including the common property.9 4 5 6 7 8 9 Body Corporate 188529 v North Shore City Council [2008] 3 NZLR 479 (HC). At [106]-[110]. Young & Ors v Body Corporate 120066 (2007) 8 NZCPR 932 (HC). At [46]. At [10]. At [32]. [38] I accept Mr Allan’s submission that the purposes and effect of the 2010 Act was to enshrine the more flexible position contended for by Harrison J. To the extent necessary, there is ample support for that proposition in the legislative history of the Act. When introducing the then Unit Titles Bill to Parliament for its first reading, the Minister for Housing noted that the Bill proposed a “fundamental rewrite of the existing legislation” and that its “key changes include promoting sound property management practices”.10 He observed that “a body corporate needs to be able to act quickly and decisively on behalf of all unit owners and for the good of the development as a whole when repairs and maintenance need to be done”. 11 He then noted that the responsibilities of the Body Corporate for repair and maintenance “will be widened to include building elements and infrastructure that affects more than a single unit” and that “this will mean, for example, that if an apartment block has a leaky roof, it will be the Body Corporate’s responsibility to fix it rather than the responsibility of the owner of the top floor apartment”.12 [39] At the Committee stage of the Bill there was specific reference to the divergence in approach of the High Court authorities and to the fact that cl 122 (which became s 138 in the Act) followed the approach that the High Court took in the Young case. Reference was made to the clause being a “practical, fair and pragmatic contribution to solving the problem of leaky homes”13 and of it taking a “common-sense and pragmatic approach”.14 [40] However, in my view, recourse to this legislative history is unnecessary in that the purpose of the Act, as set out in s 3, strongly militates against the construction contended for by Mr Brill. That purpose is in terms: 3 Purpose The purpose of this Act is to provide a legal framework for the ownership and management of land and associated buildings and facilities on a socially and economically sustainable basis by communities of individuals and, in particular, - 10 11 12 13 14 (5 March 2009) 652 NZPD 1713. (5 March 2009) 652 NZPD 1713. (5 March 2009) 652 NZPD 1713. (25 March 2010) 661 NZPD 9859. (25 March 2010) 661 NZPD 9858. (a) To allow for the subdivision of land and buildings into unit title developments comprising units that are owned in a stratum estate in freehold or stratum estate in leasehold or licensed by unit owners, and common property that is owned by the Body Corporate on behalf of the unit owners; and (b) To create bodies corporate, which comprise all unit owners in a development, to operate in managing the title development; and (c) To establish a flexible and responsive regime for the governance of unit title developments; and (d) To protect the integrity of the development as a whole. (Emphasis added) [41] Recognition of flexibility and responsiveness, the requirement to manage buildings on an economically sustainable basis and the requirement to protect the integrity of the development as a whole all, in my view, point strongly to a more expansive interpretation of s 138 than the “default provision” for which the plaintiffs contend. Indeed, in my view, the plaintiffs’ proposition involves the antithesis of flexibility and responsiveness. In the event of identified repair, or maintenance of building elements, with Mr Brill’s necessary “particular and direct relationship”, the Body Corporate would be required to: (a) notify individual unit holders of the required works; (b) engage with each of them in terms of the work which the Body Corporate regarded as necessary, inevitably inviting argument from some owners (of which the five plaintiffs in this case are an example) who would assert on-going performance of the relevant building element and a requirement only to undertake the work at some future stage; (c) monitor the workmanship of what could be a disparate group of contractors so as to ensure a sufficiently adequate and uniform standard to protect the integrity of the development as a whole; (d) invoke its default power in respect of unit owners who failed to undertake the work required which (assuming others had undertaken it) would involve a contract with no continuity and at an inevitably higher price; (e) “referee” (Mr Brill’s word) the inevitable arguments between owners as to their respective responsibilities for elements of the structure which intersect their unit and other units and/or common property e.g. flashings at the junction of inter-tenancy walls and common property; (f) manage potentially difficult insurance issues which would invariably arise in respect of a part remediated building while those unresponsive to the Body Corporate’s requirements were either prompted into action or the work for which they are responsible was undertaken by the Body Corporate. The difficulties in this respect are highlighted by Harrison J in Young; 15 and (g) accommodate inevitable inconsistencies in timing and warranties (if indeed the latter were available on anything other than a “one contract” basis). [42] In many instances, while the Body Corporate would be brokering these complex relationships, the building would continue to deteriorate, costs would escalate and the health (and ultimately safety) of the occupants would be compromised. [43] In my view this is the very outcome which the new Act was intended to prevent. [44] In LV Trust Holdings Ltd & KP Trust Holdings Ltd v Body Corporate 114424,16 Asher J noted the provisions of s 3 and, in particular, the flexibility and responsiveness recognised in it.17 15 16 17 Young & Ors v Body Corporate 12006, above n 6, at [38]-[40]. LV Trust Holdings Ltd & KP Trust Holdings Ltd v Body Corporate 114424 [2012] NZHC 3578. At [57]. [45] Academic commentators likewise have emphasised the point. Mr Gibbons in his NZLS Unit Titles Intensive 2012 notes:18 s 138 further undermines [the “bright line” between unit property and common property] by giving the body corporate responsibilities over building elements and infrastructure, whether they are common property or unit property. This can be seen to have implications for the property rights of unit owners, as it allows a degree of intrusion by the Body Corporate into their property; this intrusion is amplified by combining the responsibility with the right of access. Fundamentally, a wall or balcony might be “private” property but it is still subject to the Body Corporate right of access, and limited sovereignty in respect of maintenance. However, while this affects individual property rights it ensures the buildings can be properly maintained for the benefit of all unit owners as a group. [46] Later, in his discussion of the decision in LV Trust Holdings Ltd v BC 114424, Mr Gibbons points out that, while the various comments made in that case related specifically to Schemes under the Act:19 … they illustrate that in relation to the division between common property and unit property a more flexible approach may increasingly find favour particularly given the scheme and purpose of the UTA 2010. The Court in LV Trust paid particular attention to the purpose of the UTA 2010 including the importance of a flexible and responsive “governance regime” and the importance of a “socially and economically sustainable basis” for the ownership and management of land and buildings: (At 56-57). In other words the purpose of the UTA 2010 allows for a more “global” approach to the integrity of an entire development, as opposed to the separation of unit property from common property. That was often an important theme in cases under the UTA 1972. … We must remember that this was a scheme case and schemes inherently allow a more flexible approach than is normally allowed for maintenance situations that do not allow schemes. However, the Court clearly pointed towards the purpose of the UTA 2010 and specific provisions such as 138, as allowing more attention to overall needs than to the niceties of lines on a plan. Reading LV Trust together with Berachan we can look forward to a more holistic approach to maintenance issues under the UTA 2010 than was often the case under the UTA 1972, with the realities of the building in a situation of primary importance in determining the outcome of future cases. [47] In a flow chart attached to that paper Mr Gibbons identifies the first question that requires determination where a building element or infrastructure may require repair as being whether the particular building element or infrastructure serves more 18 19 Thomas Gibbons Maintenance (New Zealand Law Society Unit Titles Intensive) 2012 at 66. At 72. than one unit. In the event that question is answered in the affirmative, Mr Gibbons identifies an obligation upon the Body Corporate to repair that building element or infrastructure. If in the negative, then the unit plan is to be checked to identify whether the building element or infrastructure is part of a unit or common property. If the former, then it is the unit owner’s responsibility to repair, and if the latter, the Body Corporate’s. [48] In my view this analysis best reconciles the provisions of ss 80(1)(g) and 138(1)(d) and is consistent with the Court of Appeal’s obiter observations in Berachan. It also best ensures attainment of the Act’s objective to protect the integrity of the development as a whole. “Integrity” in that sense is not simply structural but, by virtue of the expansive definition of “building elements”, aesthetic as well. Exterior components of the building, like decks and associated balustrading that relate in an aesthetic sense to other units (or indeed upon my analysis to common property) properly, in my view, fall within the provisions of s 138. That reinforces an active role (indeed duty) on the part of the Body Corporate to ensure works are carried out to a uniform standard and with uniform aesthetic outcomes. None of that can be achieved (or certainly it would be appreciably more difficult to achieve) under the model Mr Brill proposes. [49] In the present case there is unchallenged evidence from the defendant’s valuer Mr Taylor that in the absence of a “whole of building” repair effected under one contract by the Body Corporate, those units which are repaired in accordance with the Body Corporate’s intentions will, on account of the existence of unremediated units in the complex (or units subject to the “targeted” repairs eventually contemplated by the plaintiffs), have a value which is in the order of 10 per cent less than would otherwise be achievable. In Mr Taylor’s opinion, this follows from the fact that there would be a “real” perception of continued risk and uncertainty in relation to the 17 remediated units. Mr Taylor identified four individual components: (a) A perception of increased risk of buying a repaired unit within a multi-level, multi-unit development where five units remain unrepaired; (b) A perception of increased uncertainty regarding future events, namely whether purchasers of the repaired units would be liable to contribute to any future repair of the five remaining units; (c) A perception about the adequacy of the repairs done to the 17 units, given the possibility of unforeseen defects and damage emanating from the other units; and (d) A perception that the repairs to the 17 units might be compromised by unremediated parts of the building. [50] Mr Taylor’s overall position is summarised in his comment that: The concept of economic and aesthetic elements are interrelated in that the value of the units or their economic wellbeing is obviously tied to the market’s perception of the overall development’s structural, aesthetic and watertight integrity. [51] Mr Taylor was not cross-examined and the plaintiffs called no expert evidence to challenge his conclusions. In my view his opinions reinforce in a practical way why maintenance of the integrity of the development as a whole is an essential purpose of the Act. Only by doing so is it possible to manage the building on a socially and economically sustainable basis, as s 3 itself recognises. [52] I accept the defendant’s submission that the plaintiffs should not be heard to complain that it is unfair that they have to pay for the costs of repairs and maintenance to building elements and infrastructure (within the terms of s 138(1)(a)) by ownership interests in the first instance, with the Body Corporate later deciding what recovery steps it will take. I accept that was Parliament’s expressed intention and that people who want to be able to choose how and when they might repair building elements should carefully reflect on whether unit title ownership is appropriate for them. Albeit in a slightly different context, the words of Duffy J in St John’s College Trust Board v Body Corporate 197230 are apposite in terms:20 [52] Insofar as it may appear to be unfair that owners of units in one building must contribute to costs of common property located in another 20 St John’s College Trust Board v Body Corporate 197230 [2012] NZHC 827. building, the answer is that this is a fundamental element of this strata title development. The likelihood of this occurrence has been present from the outset. Anyone who did not want to subscribe to this type of liability need not have acquired a unit in this complex.21 [53] That applies irrespective of the fact that the s 80(1)(g) obligation is repeated in cl 14(b) of the Body Corporate’s residential operational rules. If the nature of the building element is such that the duty in s 138 is engaged, then the operational rules are necessarily “trumped” by the statutory obligations. [54] In summary therefore, I am satisfied that the Body Corporate was entitled to embark on a repair of the whole building without first giving individual unit owners the opportunity to effect their own repairs. Indeed, I see it as its obligation. In saying that, I assume for present purposes vires (the issue to which I now turn) and procedural regularity. Section 138(1)(d) of the UTA 2010 – when does it engage? [55] I set out at [26] above the relevant provision of s 138(1)(d). [56] Section 138(5)(c) in turn provides that: 138 Body Corporate duties of repair and maintenance … (5) [57] The duty to repair and maintain includes (without limitation) a duty to manage (for the purposes of repair and maintenance), to keep in a good state of repair, and to renew where necessary. A corresponding obligation arises on the part of each owner of a principal unit by virtue of s 80(1)(a)(ii) of the Act. This provides that such an owner: 80 Responsibilities of owners of principal units (1) An owner of a principal unit (a) 21 Must permit the Body Corporate (or its agents) to enter the unit at any time in an emergency and at all reasonable hours and Recognition that those who buy into body corporate developments agree to be bound by the democratic processes which underscore them is also a feature of the reasoning in World Vision of New Zealand Trust Board v Seal [2004] 1 NZLR 673 (HC). after giving reasonable notice, for any of the following purposes: [58] (i) … (ii) To maintain, repair, or renew any infrastructure for services and utilities that serve more than 1 unit and any building elements that affect more than 1 unit or the common property, or both. It will be noted immediately that there are some unfortunate conflicts in what were plainly intended to be complementary sections. These include: (a) The reference to maintenance, repair or renewal in s 80(1)(a)(ii) whereas the s 138 reference is to repair and maintain. That however is addressed by s 138(5)(c) which expands the duty to repair and maintain to include “renewal where necessary”. (b) Where s 80(1)(a)(ii) speaks to infrastructure “for services … that serve more than 1 unit” and building elements that affect more than one unit, the s 138(1)(d) reference is to building elements and infrastructure that relate to or serve more than one unit. So there is substitution of the word “relate” for “affect” and whereas, under s 80(1)(a)(ii), the word “serve” qualifies infrastructure and “affect” qualifies building elements, under s 138(1)(d) the words “relate to or serve” arguably qualify both building elements and infrastructure. (c) Significantly, whereas under s 80(1)(a)(ii) the owner of a principal unit must permit entry by the Body Corporate for maintenance, repair or renewal the building elements that “affect more than 1 unit or the common property, or both”, the duty under s 138(1)(d) on its face arises only in respect of building elements that relate to or serve “more than 1 unit”. [59] In relation to the issue identified in [58(c)] this is, in my view, one of those rare occasions where the Court should fill what I regard as an obvious omission from s 138(1)(d). It is true, as the authors of Statute Law in New Zealand state that “normally courts cannot write in what the legislature has not thought fit to include”.22 However, as Cooke P pointed out in Northland Milk Vendors Association Inc v Northern Milk Ltd, courts must try to make an Act work as Parliament intended and must give an interpretation that accords best with the “intention” or “spirit” of the Act. 23 Thus even where a purposive interpretation may not exactly be able to fill the gaps it may “bridge a hiatus”.24 This decision has been followed in others25 and as Messrs Burrows and Carter state, “has been used to produce a sensible solution when a drafting error has given rise to a situation that is untenable”.26 [60] In my view, insertion of the words “or the common property, or both” into s 138(1)(d) is justified for the following reasons: (a) Only by doing so are the two sections, which were clearly intended as complementary, properly harmonised; (b) The most uncontentious of all the Body Corporate’s duties has always been its obligation to maintain the common property. That obligation is recognised in s 138(1)(a) and was the basis for the Court upholding the vires of amended rule 2(d) in the Young decision. Relevantly Harrison J observed:27 A body corporate must have all powers reasonably necessary to protect the common property in a building including a power to repair and maintain parts of the external structure, the condition of which might expose the common property to consequential physical damage. Leakage through a failure to keep the exterior in good condition places at risk the development as a whole, incorporating of course the common property. (c) A duty to maintain and repair building elements within a unit which relate to or serve more than one unit but not building elements in the 22 23 24 25 26 27 JF Burrows and RI Carter Statute Law in New Zealand (4th ed, LexisNexis, Wellington, 2009) at 212. Northland Milk Vendors Assoc Inc v Northern Milk Ltd [1988] 1 NZLR 530 at 538 (CA). Burrows and Carter, above n 22, at 212. See Fleetwing Farms Ltd v Marlborough District Council [1997] 3 NZLR 257 (CA) at 267, Walker v Allan [2002] 1 NZLR 278 (HC) and BR v RL (2008) 28 FRNZ 46 (HC). Burrows and Carter, above n 22, at 213. Young & Ors v Body Corporate 120066, above n 6, at [32]. same location which relate to or serve common property makes little sense and leaves the common property exposed. Indeed, I go further. I accept Mr Allan’s submission that throughout the country there are likely to be hundreds of structures in which unit properties are constructed on top of common property and that for a body corporate to be under an obligation to repair both the common property and every unit in the development relating to another unit but not those units sitting on top of common property is “truly nonsensical”; (d) Any other approach is inconsistent with the stated purpose of the Act in s 3(d) “to protect the integrity of the development as a whole”. [61] However, if I am wrong in that approach, Mr Allan urges a purposive construction of the word “unit” in s 138(d) to include, in that context, the common property. [62] Unit is a defined term meaning:28 In relation to any land, means a part of the land consisting of a space of any shape situated below, on, or above the surface of the land or partly in one such situation and partly in another or others, all the dimensions of which are limited and that is designed for separate ownership. (Emphasis added) [63] In terms of s 54 UTA 2010: (a) The common property is owned by the Body Corporate. (b) The owners of all units are beneficially entitled to the common property as tenants in common in shares proportional to ownership interest (or proposed ownership interest) in respect of their respective units. [64] Mr Allan’s argument in this respect is that the “separate ownership” referenced in the definition of unit may include ownership as tenants in common in shares. Since that proposition is self-evidently correct in relation to any principal 28 Unit Titles Act 2010, s 5. unit of which there are multiple proprietors as tenants in common, it is difficult to resist his further proposition that a unit could include areas of the building in the separate albeit common ownership of the respective proprietors. [65] However, I prefer to deal with the matter in the manner indicated, namely by reading into s 138(1)(d) the same words “or the common property, or both” which appear at the conclusion of s 80(1)(a)(ii). [66] In the context of the Bridgewater development this conclusion means that in relation to the plaintiffs’ vires challenge I may look to the manner in which any level 2 building elements relate to or serve the common property. As I will expand on later in the judgment, that relationship is as obvious as the (conceded) relationship which the level 3 decks have to level 2 units. The Jurisdictional Facts [67] With that background there are accordingly three of what Mr Brill describes as “jurisdictional facts” which underpin the Body Corporate’s s 138(1)(d) duties, namely that: (a) repair, maintenance or renewal is necessary in respect of — (b) any building elements and infrastructure that — (c) relate to or serve more than one unit or the common property, or both.29 [68] In relation to each of these “jurisdictional facts” the plaintiffs assert a civil onus on the defendants to satisfy the Court that the relevant criteria are established. [69] For its part the defendant says that it has no such onus and further that, although it was obliged to act on expert advice and has done so, that is the limit of its obligations and that, so long as there was some material that could justify the 29 The statement of claim and Mr Brill’s submissions were premised on the proposition (rejected by me) that the body corporate has no duty in relation to building elements on private property that serve common property. decision made by it, even though contrary views were tenable, its decision to act under s 138(1)(d) cannot be challenged. [70] In support of that proposition the defendant relies on the decision of Jaine J in Re Bell30 as adopted by Heath J in World Vision of New Zealand Trust Board v Seal.31 [71] Re Bell involved an application for relief under s 42 of the former Act where, absent relief, a unanimous resolution would have been required. The relevant resolution related to sale of the caretaker’s flat and was supported by 96 of the 99 proprietors. Jaine J noted that s 42 gave no guidance to the Court of the principles upon which it was to act. He went on to say, however, that:32 The merits of the matter are best determined by those who are affected by it and have personal knowledge of it and after the matter has been considered by them with the opportunity for debate at a properly convened meeting of the Body Corporate. It should not be for the Court to substitute its view on the merits of the proposal and this Court is not persuaded that the reasons for opposing the motions must be examined with a view to considering whether the minority view on the merits of the proposal should be upheld with the result that the wishes of the majority could not be given effect to. This Court’s attention should be directed towards the procedures that led to the passing of the resolutions rather than the merits of them and a consideration of whether there was some material that could justify the decision, even though a contrary view was tenable. If there was an irregularity or impropriety in the procedures followed or it was apparent that there was no information upon which any reasonable person could reach the decision contained in the resolutions, then this Court may consider refusing an order sought under s 42 even though the required majority was obtained. [72] I reject both the plaintiffs’ and the defendant’s arguments on this issue. In my view, subject to the question of procedural regularity to which I will later return, once a decision has been taken by a body corporate to discharge its duties under s 138(1)(d) the onus is on any party (here the plaintiffs) to prove, on the balance of probabilities, that the jurisdictional requirements of the section are not satisfied. In so far as those jurisdictional requirements are concerned, however, I do not regard as a complete answer the fact that the Body Corporate has acted on expert advice with “some material” to justify its decision. I accept in that sense the plaintiffs’ reference 30 31 32 Re Bell HC Wellington M243/92, 22 October 1992. World Vision of New Zealand Trust Board v Seal, above n 21. Re Bell, above n 30, at 5-6. to “jurisdictional facts”. If the plaintiffs are able to demonstrate on the balance of probabilities that the various criteria of s 138(1)(d) are not engaged, then there can be no duty to undertake repairs within unit property and the proprietor’s entitlement to quiet enjoyment, under s 79(d), must prevail. [73] However, in my view, the observations of Jaine J are particularly apposite to the next stage in any body corporate’s assessment – namely, having determined that it must act, what the particular nature of its response should be. Such response will inevitably be conditioned on expert opinion. That much is recognised in Brooker v Body Corporate 154558,33 and in my opinion the merits of one repair plan over another are best determined by those who are affected by and have to fund it, have personal knowledge of it, have participated in any discussions relating to it at a properly convened meeting of the Body Corporate, and have decided accordingly. [74] I accept therefore the defendant’s submission that, provided the Body Corporate has acted on expert advice, that the expert engaged was suitably qualified, and that the advice was given in good faith, how the Body Corporate chooses to act, whether by way of the “holistic” solution proposed by the defendant or the targeted repairs for which the plaintiffs vigorously contend, is a matter for the Body Corporate and its decision should, ordinarily, be respected even if contrary views are tenable. However, that position assumes vires. [75] This accords with the approach of Asher J in LV Trust Holdings Ltd v Body Corporate 114424 where a distinction was drawn between the position of minorities in relation to economic issues affecting them alone and the position of such minorities with regard to decisions affecting the development as a whole. His Honour noted in respect of the competing schemes before him: [60] The fact that the applicants are in a minority of one and the majority of 14 are against their proposal is far from conclusive in the particular circumstances of this case. The assumption referred to in Tisch that the greater level of support from owners with the proposed scheme, the more likely it is to do justice, does not in all circumstances follow. As the Court of Appeal observed, the assumption does not invariably apply because a majority of owners may support a scheme that is unfair to the minority. 33 Brooker v Body Corporate 154558 (2005) 6 NZCPR 953 (HC) at [64]. [61] When the majority of owners will financially benefit and the minority will financially suffer, the majority support may do no more than reflect that unfairness. The position is different where the issue is one of method or scope, or aesthetics. If, for instance there is broad support for a particular colour scheme or design, that is likely to be highly persuasive. Not so when it is just a question of who out of the various owners should pay with division along payment lines. (Emphasis added) [76] In this case, although the detail will be more fully discussed in later sections of this judgment, the Body Corporate has acted on bona fide advice from an expert with substantial experience and who was identified and instructed by solicitors with specialist knowledge in the area. His advice to the Body Corporate was that the complex did not comply with the Building Code at the date of its construction and that remediation would involve reconstruction of the decks with adequate falls and certain consequential changes to the northern facade. The Body Corporate was, in my view, entitled to accept that advice and develop its scope of works accordingly. It was entitled to do so despite the existence of contrary views. It is not for the Court to substitute its own view on the merits of one repair plan over another or to examine, in the words of Jaine J, “whether the minority view on the merits of the proposal should be upheld with the result that the wishes of the majority could not be given effect to”.34 Are each of the level 4, 3 and 2 decks building elements? [77] This question can be simply answered. The definition of building elements in the Act is expansive and relevantly to this case specifically includes “decks” and “horizontal slab structures between adjoining units”, or “other features for the support of the building”.35 Are elements of infrastructure involved? [78] Again the answer is yes. Infrastructure is broadly defined to include:36 Infrastructure includes pipes, wires, ducts, conduits, gutters, watercourses, cables, channels, flues, conducting, or transmission equipment necessary for the provision of water, sewerage, drainage, stormwater removal, gas, 34 35 36 Re Bell, above n 30, at 5. Unit Titles Act 2010, s 5. Section 5. electricity, oil, shelter, protection from fire, security, rubbish collection, air, telephone connection, Internet access, radio reception, television reception, or any other services or utilities to or from a unit or to or from the common property. [79] I discuss in the next section how that definition is engaged and the nature of the “relationship or service” with other units/the common property. Do the relevant building elements and infrastructure relate to (or serve) more than one unit (or the common property, or both)? [80] I have already identified the inconsistencies between s 80(1)(a)(ii) and s 138(1)(d) in so far as issues of “service” and “relationship” are concerned. Because s 80(1)(a)(ii) associates the verb “serve” with infrastructure, Mr Brill urges that I should adopt a similar construction of s 138(1)(d) with the result that, in relation to building elements, the relevant inquiry should be whether they relate to more than one unit, and with regard to infrastructure, whether it serves more than one unit. He further suggests that because s 80(1)(a)(ii) uses the word “affect” rather than “relate” I should give a common meaning to both. [81] I do not consider that anything turns on these fine distinctions. [82] I adopt in respect of the expression “relate to” the meaning attributed by Harrison J in Young where he said:37 Something is incidental if it naturally attaches or is causally relevant to something else. The phrase “relates to” has a similar meaning of reference to or concern with. [83] Such definition is wide enough to capture the concept of “affect” in s 80(1)(a)(ii). [84] I accept that, typically, it may be more natural to talk of building elements within private property “relating to” other units or common property than of them “serving” such property and that the word “serve” typically is more naturally associated with infrastructure in the nature of pipes, wires, ducts etc. However, there may be building elements best described as serving more than one unit and 37 Young & Ors v Body Corporate 120066, above n 6, at [30]. infrastructure best described as relating to more than one unit and I would not preclude such a construction. [85] Having regard to the purposes in s 3, I accept Mr Allan’s submission that Harrison J’s approach means that s 138(1)(d) will be satisfied if the relevant building element or infrastructure: (a) naturally attaches to another unit (as in physically adjoining units); or (b) is causally relevant to another unit whether physically or economically (as in non-adjoining units) ; or (c) is referable to another unit whether physically or economically (as in both adjoining and non-adjoining units); or (d) [86] is concerned with another unit whether physically or economically. I would add to this that the inclusion of aesthetics in the definition of “building elements” and the emphasis on “integrity of the development” in s 3 means, in my view, that the economic relationship to which Mr Allan refers should include those factors, which inevitably reflect in value. [87] As indicated, the present case engages both issues of building elements and infrastructure. [88] As to infrastructure, it is not disputed that the deck outlets at all levels drain into an internal piping system which runs ultimately through the inter-tenancy walls at each of levels 3 and 2, thereafter entering the underground storm water reticulation system in the common property at ground level. [89] From the deck drains at level 4 there is a piping system within the ceiling cavity above level 3 involving two right-angle bends into the same system in the inter-tenancy walls. [90] In each of levels 3 and 2 there are outlets on either side of the decks connecting again into the same system. By virtue of this internal reticulation system the defendant’s expert Mr Gray describes there being “an inter-relationship vertically and horizontally for all of the units that have an inter-tenancy wall or slab forming any part of their physical boundary”. [91] The significance of this feature is, in the words of Mr Gray, “acute”, because he discovered at the base of every inter-tenancy wall what he described as “extremely high moisture readings”. Indeed, having drilled vertically from the base upwards into the boxed structure (in the nature of a rain head) within the common property at ground level he found that “many of them had simply turned to mush” indicating that the internal reticulation system is clearly leaking. [92] In respect of the decks, Mr Gray’s evidence was likewise that they related to or served more than one unit. His evidence was in terms that: As a physical element they [the decks] are required to shed water in such a way that water cannot: [93] stated: (a) Track through the deck membrane to the concrete structure below and/or through micro/hairline cracks in the concrete slab; (b) Track through penetrations in the concrete slabs such as pipes; (c) Track through gaps between deck elements such as slabs and walls or floors and walls to the units below or beside; (d) Track or enter through other components in contact with the deck such as cladding; (e) Cause or allow water ingress through insufficient clearances via momentum driven rain (rainwater bouncing vertically off the deck surface); (f) Tracking along the internal pipe work to units below and adjacent; (g) Tracking horizontally underneath inter-tenancy walls; or (h) Tracking through the porous slab into other parts of the property. Mr Gray referred to these cumulatively as the “ingress risk factors” and All of these potential ingress risk factors are present in Bridgewater as a result of the combination of its design features which, from a physical perspective involve the deck of one unit constituting the ceiling of another. [94] On that basis he rejected the plaintiff’s contention that the structure involved a series of self-contained “cells” in a “honeycomb” structure. That view was not in my assessment materially undermined in cross-examination and nor was there expert evidence against it. [95] Mr Gray’s evidence was in turn fully supported by the expert evidence of architectural designer David Bullen-Smith who the plaintiff did not cross examine. His principal conclusions were: (1) That the exterior or “envelope” of a building “dovetails” into economic value from two different architectural perspectives – a physical one and an aesthetic one. (2) Absent a properly constituted envelope water can migrate vertically and horizontally through a building structure, as concrete is porous. (3) There is no design detail in the consent documents reviewed by him which ensures that water cannot track horizontally from one deck to another through the intervening walls. (4) The storm water reticulation system was another example of interrelated structures in the development. (5) The decks were not compliant with Acceptable Solutions at the time the building was originally constructed. [96] I am therefore left in no doubt that all decks within the development constitute building elements relating to or serving more than one unit or the common property or both. That is the inevitable conclusion from the “wedding cake” design. Based on my construction of s 138(1)(d) (so as to include the additional words identified) the plaintiffs’ concession relating to the level 3 decks inevitably informs the level 2 position. And that conclusion is further fortified by the ability of water to track horizontally, as Mr Grey deposes, which means that the level 2 units relate inter se, satisfying the s 138(1)(d) criteria even without the additional words which I believe are appropriately imported. [97] I accept that it is more difficult to say that the small in-fill panels which the two bedroom apartments feature relate to or serve other units or the common property. They are discrete items within the boundary of each unit, effectively insulated from physical relationship with other units by glazing systems and/or the solid inter-tenancy walls. But they do relate aesthetically to the other units and, on the evidence of Mr Gray, are necessarily replaced as part of the exercise of establishing adequate falls on the decks. [98] Accordingly, the plaintiffs fail to discharge the onus in relation to this “jurisdictional fact” also. Requirement to repair and maintain (including renewal) [99] Mr Brill’s argument in relation to repair and maintenance has two facets. [100] Firstly, Mr Brill challenges, in a wholesale way, the adequacy of the expert opinion on which the defendant relies, namely that of Mr Gray. He submits that Mr Gray’s opinions are based on sufficiently ill-founded assumptions and inadequate facts, and that the problems with his evidence are sufficiently pervasive that it should be rejected in total as unlikely to offer “substantial help within the terms of s 26 of the Evidence Act 2006.” He suggests that this submission is supported by, what he calls, Mr Gray’s “wary, evasive and defensive” demeanour under cross-examination. [101] Secondly, he submits that the repair plan proposed, involving as it does adherence to the current Building Code and Acceptable Solutions, goes beyond repair and maintenance (including renewal) and involves betterment to the development which is beyond the Body Corporate’s powers and duties. Mr Gray’s evidence [102] Mr Gray’s substantive evidence was contained in a 193 paragraph affidavit dated 2 February 2015. In addition, he provided a supplementary affidavit exhibiting the full Origin Report, including photographs, which he prepared for the Body Corporate in October 2013. He was cross-examined at length by Mr Brill on both that affidavit and report and re-examined by Mr Allan. [103] I address first the issue of demeanour and Mr Brill’s submission under s 26 of the Evidence Act. I reject that submission, although there were occasions when Mr Gray’s position did appear pedantic. An example was his response to attributed comments at the EGM on 9 November 2013. However, in response to a question from the Bench he candidly admitted that the minutes expressed the general tenor of his comments, while not obviously being his precise words. Overall I found his demeanour appropriate and that he endeavoured at all times to maintain objectivity and independence which are pre-requisites for the receipt of his evidence. I address separately criticisms of the content of the evidence. Do the decks require repair and maintenance? [104] At one level the answer to this question is obvious and not materially disputed by the plaintiffs. That is because, demonstrably, at least some of the decks are in need of immediate attention, as are all the drainage systems. I set out below the problems which are currently occurring: (a) In respect of apartments 401 and 402 (the penthouses) there has been a significant history of problems with the decks, which in part comprise the living room ceilings of the units below. Mr Gray deposes that this history has its origins in three principal faults with the decks. Firstly, he says they have inadequate falls (he identified a 0.6 per cent fall on the deck of unit 401 and a 0.1 per cent fall on the deck of 402). Secondly, he says there is an inappropriate drainage detail whereby the flange of the deck drain sits proud of the underlying membrane with the result that water penetrating through the porous joints in the tiles cannot be expelled. Thirdly, and significantly, he identifies non-performance of the membrane which he says has “allowed it to soak up water like a sponge and allow the moisture to pass through it to the surface below.” Indeed, he says that if the membrane was “intended to have been a “waterproof membrane” then self-evidently it has failed dismally”. (b) There is a history of water ponding on at least some of the decks. In his evidence on behalf of the Body Corporate, long-term committee member Mr Andrews says that ponding of water has been identified as a problem for in excess of two years and rejects the suggestion of the plaintiffs’ witness Mr Millington that historical discussion of water ponding at general meetings was isolated to the level four decks. He refers to a report commissioned on 22 April 2013 from AA which viewed the decks of units 401 and 402, 304, 309, 201 and 209. The report refers to evidence of “surface water ponding on the deck of apartment 304” and, in its summary, to the fact that “water was ponding in a couple of areas on the decks viewed”. In his evidence Mr Gray says that he observed the physical evidence of water pooling on the decks of apartments 201, 303, 309, 401 and observed residue from the pooling of water on the decks of apartments 302, 401 and 402. In combination with the minimal falls which he measured on five of the decks (402 – 0.1°, 401 – 0.6°, 301 –0.3°, 302 – 0.1° and 304 – 0.6°) he concluded that this pooling demonstrated noncompliance with cl E2 of the Building Code, and in particular cl E2.3.1, which states the requirement to “shed precipitated moisture”. (c) There is a similar history of cracked and loose tiles which Mr Andrews again deposes pre-dates the January 2013 AGM. That problem was plain to see in the course of the site inspection. On one deck (303) the tiles had become completely detached from the substrate and were able to be removed and replaced. In other areas movement in the tiles could be detected when weight was applied to them. I also observed evidence of cracked tiles. (d) Throughout the development there are problems with the membrane under the tiles. In relation to apartment 401 where remedial work was undertaken approximately four years after the tiles were originally laid, there is an apparent waterproof membrane under the tiles. However, Mr Gray deposes that on testing there were blisters and fine pin prick holes through the surface, such that when pressure was applied to the membrane, water seeped through the holes indicating a breach of the surface layer. In relation to the level 2 and level 3 apartments it appears the problem is even more significant. Where the tiles had lifted in apartment 303 the matting beneath them can be readily identified. There is as Mr Gray states, no evidence of any waterproof membrane over the cork acoustic mat. As a result, the mat has absorbed moisture which in evidence Mr Gray said will, over time, rot the cork, affect its acoustic properties and lead to the underlying screed becoming saturated with moisture. Mr Gray further deposes that given all decks were built at the same time (March 2002 to December 2003) and that he has seen no evidence in the property file to suggest there were multiple contractors involved with construction of the same deck elements, he regarded it as a reasonable assumption that the decks were constructed using the same methodology and are therefore likely to have the same common problems. (e) There are obvious problems with the internal drainage system, as previously discussed in this judgment, with the result that the rain heads have, in Mr Gray’s words, “simply turned to mush”. Testing at that location indicated a 100 per cent moisture content. (f) In addition Mr Gray identified less significant problems involving deck tile grouting in contact with the bottom edge of the cladding and an insufficient cladding to deck clearance. [105] Mr Gray summarised these problems in his affidavit in terms: If, as I have observed, and as appears from the plaintiffs’ evidence … there are cracked tiles, loose tiles, membrane separating from the slab, waterlogged membranes beneath the tiles, porous screed and grout then the individual constituent elements are not performing either individually or collectively to shed precipitated moisture. [106] In addition to problems with the decks Mr Gray also identified as problems with the building: (a) what he described as consistently high readings in a high percentage of the timber frames associated with the infill panels adjacent to the glazing systems on the northern face of the building; (b) an absence of waterproofing membrane to the top of the plaster overwood framed parapet wall between units 401 and 402 resulting in elevated moisture levels. Photographs 51 and 52 annexed to the Origin Report show recordings of 36.8 per cent and 31.8 per cent respectively at that location. (c) numerous instances of cracking to the fibre cement sheet cladding at the penthouse level; (d) problems with cladding being hard down on joinery head flashings; (e) absence of sealing in respect of metal cladding panels; (f) unsealed junctions between the express joint cladding; and (g) unsealed joinery jamb junctions and vertical cladding/wall junctions. [107] However it is clear that Mr Gray’s approach to remediation is based not only on currently observed defects and danger of water ingress, but on the wisdom of preventative action which is a concept the Supreme Court recognised as appropriate in Body Corporate 207624 v North Shore City Council.38 38 Body Corporate 207624 v North Shore City Council [2012] NZSC 83, [2013] 2 NZLR 297. [108] Viewed in their totality, Mr Gray concludes that the multiple demonstrated problems with the decks establish that they are, and were at the time of their construction, non-compliant with cl E2.3.1 of the Building Code in that they do not and did not “shed precipitated moisture”. He describes this as “original design or construction defect” and says that although, with the exception of the apartment 401 and 402 decks, there may not currently be any visible sign of leaking, he does not regard this as a determinant of repair or maintenance. He says he cannot preclude the fact that there may already be leaking and concludes: Regardless of whether or not leaking is occurring now across all units’ decks in Bridgewater, the fact is that these decks – which form the roof of the property below – are defective and did not meet the Code at the time of construction and will not do so until repaired properly. [109] And further that: In my opinion, not only did the decks not comply with the Code at the time of construction, in any event the decks either have failed or will likely do so long before the end of the building’s life. [110] The plaintiffs attack this evidence on a number of fronts. [111] Firstly, they say that Mr Gray bases his entire findings of Code breach on an incorrect understanding of the meaning of “must shed precipitated moisture” in cl E2.3.1 of the Building Code. Mr Brill submits that Mr Gray’s construction is idiosyncratic and effectively identifies non-performance as occurring even in the context of the “minutest of puddles”. He submits that the word “shed” means no more than “to get rid of” with no implications regarding the speed with which this must occur. [112] I do not accept this submission. I agree with the interpretation underpinning Mr Gray’s evidence that the process of shedding should commence immediately after a rainfall event and should cease once, as Mr Gray puts it, “the principles involved with gravity after the rain or water on the surface has (sic) ceased to act”. Mr Gray went on to say that if, after a rainfall event, you were to look at the rest of the surface of the roof and there were other areas where there was no water then at that point you could reasonably assume that the shedding was done and that any balance water on the surface had not been “shed” but rather was retained water which would disperse only by evaporation. I accept that analysis. Evaporation does not, in my view, equate to “shedding”. On that basis the evidence of “pooling” previously referred to establishes that the decks concerned are not, in my view, Code compliant. [113] Secondly, the plaintiffs submit that Mr Gray adopts a “guilty until proven innocent” approach with regard to the level 2 and 3 decks premised on the fact that there was clear evidence of level 4 failure and with an assumption that level 2 and 3 decks will at some future point fail if they have not already. Mr Brill suggests that Mr Gray’s interpretation of cl E2.2 of the Building Code’s requirement that buildings must be constructed to provide adequate resistance to penetration by “moisture” involves an affirmative proof of prevention. He suggests that Mr Gray has indulged in “fact free speculation” rather than attempting to establish the facts or to apply generally recognised standards. He identifies a number of inspections which he says could have taken place to determine the exact level of performance of the level 2 and 3 decks. [114] I accept that Mr Gray’s presentation at a committee meeting on Wednesday 7 May 2014 included (as recorded by the Secretary) the stated observations: (a) There is clear evidence that the decks on level 4 have failed; (b) That a visual inspection suggests the decks on all levels are constructed the same; (c) It is a reasonable assumption that the decks on levels 2 and 3 will fail at some point if they have not already failed; and (d) That evidence of failure had not yet been fully confirmed and would occur in the remediation programme. [115] There is, however, in my view, danger in taking that evidence out of context. The minutes record the previous advice by Mr Gray was that although all of the level 2 and 3 decks had not yet been investigated, there was evidence that the walls around the decks had been compromised as the result of moisture. He subsequently expressed confidence that a “complete solution” was the only sensible solution for the complex’s design failings. [116] Nor did Mr Gray’s evidence in this proceeding proceed on the basis of a simple extrapolation from the level 4 failings. There was direct evidence, for example, of tile failure in level 3 apartments, including the evidence I was able to observe myself during the course of the site inspection (I refer in that respect to lifted and cracked tiles and to the fact that in places where adhesion had been lost with the substrate there was evidence of retained moisture under the tiles which was expressed through the grout when weight was applied to them). Moreover, the submission overlooks the absence of waterproof membrane in apartment 303 which, if anything, makes its position worse than that of either of the level 4 apartments. Finally, there are all the other acknowledged defects at levels 2 and 3 including the fact that the deck tile grouting was in contact with the bottom edge of the cladding, the insufficient cladding-to-deck clearance and the inadequate falls which manifest themselves in the instances of pooling which were identified. [117] The third area of attack is related to the second and focuses on the drainage detail to the deck of penthouse apartment 402 which is known to have leaked. As previously indicated, that detail provides for the collar of the drainage outlet to stand proud of what appears to be a waterproofing membrane (albeit not an adequately functioning one) at that level. In turn, water is “encapsulated” (Mr Gray’s word) under the tiles and cannot escape. [118] On the basis that all of the decks were constructed by the same contractor, Mr Gray extrapolates that detail to each of the level 3 and 2 decks. The plaintiffs are critical of that extrapolation because of remedial work undertaken in 2007 on the level 4 decks. They suggest that the drainage detail complained of is unique to level 4 and a result of that remedial work. [119] That proposition was, however, rejected by Mr Gray. [120] The following exchange summarises his position: Q: The point is there was extensive work including membrane work done on that deck four years after the membranes were laid on the apartment decks and yet you assume that what you see on 402, it is a reasonable assumption to assume that all the apartment decks will be just the same? A: When I looked at 402 the first time I was conscious that there had been repairs and I was very careful, I believe to look for original construction. You can tell what is new sealant, what is original sealant. You can – we are familiar with looking at these junctions, we are familiar with looking at series works and you get good at identifying – [121] The position is confused by the fact that further temporary repairs were made in the vicinity of the apartment 402 “back” drain in 2013 and it was put to Mr Gray that: Q: What you might have detected as being the difference between the new and the old was in fact the difference between the 2013 work versus the 2003 or 2007 work? [122] Mr Gray responded to that by saying that it was “altogether possible” but that he was, he believed, “quite thorough and careful”. His earlier evidence had been that you could see evidence of two membranes – an original one which disappeared without touching the edge of the tiles and a subsequent liquid applied membrane painted up to the edge of the tiles as opposed to going under them. Mr Gray expressed confidence that the original work he was looking at was that completed in 2003. [123] Ultimately this issue falls to be determined on burden of proof principles. Mr Gray was confident that he could identify original construction by reference to the membrane which passed under tiles and the plaintiffs adduced no evidence that the remedial work undertaken in 2007 involved construction of a unique drainage detail in relation to apartment 401. [124] However, even if there was such a unique detail and assuming it to be the principal cause of the problems which occurred on level 4, there remain a number of identified problems on the level 2 and 3 decks as previously discussed. [125] Next the plaintiffs are critical of Mr Gray’s proposition that deck membranes are building elements with a required 50 year life span in terms of sub-cl B2.3.1 (Durability) of the Building Code. His evidence in that respect was based on the proposition that membranes were an element “difficult to access or replace” within the terms of sub-cl B2.3.1(a)(ii). On this point the plaintiffs are, in my view, on firmer ground. The decks constituted part of the “building envelope”. Such was accepted by Mr Gray. The building envelope includes the exterior cladding and the proposition that a deck membrane should have a greater durability requirement than, for example, a wall cladding, seems to me a dubious one. [126] In this respect the plaintiffs called evidence from a Mr Reed - a semi-retired self-employed building contractor who stated that he was “surprised” by Mr Gray’s view that the durability provisions of the Code required deck membranes to have a service life of 50 years. He stated that Territorial Authorities almost always require membrane suppliers to provide “producer statements” under the Building Act and that he was unaware of any manufacturer which claimed its product will last 50 years without maintenance or renewal. [127] Insofar as Mr Gray’s opinion was based on the “difficulty” identified in subclause B2.3.1(a)(ii) there is nothing, in my view, to say that such replacement was not simply “moderately difficult” within the terms of subclause B2.3.1(b)(i). If that is the case then a 15 year durability requirement would apply. [128] However, while accepting that the plaintiffs demonstrate an incorrect approach in this regard, it does not, in my view, get them to the point they require. For a start, there is compelling evidence from apartment 303 that there is in fact no waterproof membrane (or no waterproof membrane in the location it should be) under the deck tiles. Even if there was such a membrane it would, on the plaintiffs’ approach to the durability requirements, be nearing the end of its service life. Moreover, such membranes as have been able to be identified are not performing. I am not persuaded that when one looks at the combination of cracked tiles, loose tiles, membrane separating from slab, waterlogged membranes and water-logged acoustic matting, it is realistic to suggest that the decks are not currently in need of repair or maintenance, taking into account that they were all constructed at the same approximate time and by the same contractor. [129] Finally, the plaintiffs are critical of Mr Gray’s evidence in relation to moisture readings. In his written submission Mr Brill introduced this aspect of his argument in terms: Mr Gray’s recommendation for replacement of the whole northern elevation of the building is based on moisture readings which he insisted in crossexamination are not merely indicative of potential problems but “absolute”. [130] I do not regard that as a fair representation of why Mr Gray’s remediation plans extend to (effective) replacement of the northern façade. Although he identified elevated moisture levels in the wooden framing associated with the façade “in fill” panels (which I discuss in greater detail below) what the plaintiffs refer to as “replacement of the whole northern elevation of the building” does not, it seems to me, to have been significantly driven by that fact. Rather, such replacement follows from Mr Gray’s assessment that remediation works to the decks need to be compliant with the current Code, that this necessitates establishment of adequate falls which, in combination with the required step down from the living room areas in turn requires construction of a bulk head and either refurbished or replacement glazing systems. It is not the moisture readings themselves which drive that replacement. [131] Nevertheless, the moisture readings formed a significant part of Mr Gray’s evidence of non-performance with sub-cl E2.3.2 (prevention of penetration of water that could cause undue dampness) and his assessment that the B2 durability requirements were not being met. [132] That evidence was developed at length in his principal affidavit and is supplemented by the moisture maps appended to his original report. [133] At levels 3 and 4 those moisture maps were focused on the in-fill panels adjacent to the northern elevation glazing systems. [134] Some 28 readings of moisture levels were taken in and around that location with the results ranging from between 15.5 per cent and 89.4 per cent. The 89.4 per cent figure was an outlier and my calculations show that the average reading was 21.9 per cent at that location. As Mr Gray explains in his evidence, all recorded percentages must, in turn, be adjusted upwards by two per cent to reflect the assumed use of radiata pine in the relevant framing. [135] In his evidence Mr Gray said that, for a building of this age and assuming that there was a weathertight envelope, he would expect the framing in wall cavities to have a moisture level of 8-14 per cent (which he described as the equilibrium moisture content (EMC). Measured against EMC, he concluded that there were “consistently high readings in a high percentage of the testing [he] conducted”. He stated that “these readings were sufficiently high in my professional opinion to establish a recommendation to repair”. [136] That evidence is to be considered against the Department of Building and Housing’s Guide to the Diagnosis of Leaking Buildings,39 which sets out a three level analysis in the following terms: 39 Moisture content readings in this range fall within the maximum allowable range for untreated radiate pine as per NZS 3602:1995 for members protected from weather and dry conditions While moisture content of this level could indicate possible problems, it is generally considered that this level will not support timber decay Moisture content readings in this range indicate problems exist and excess moisture should be immediately corrected Such levels must be considered a warning that remedial action is required to prevent future damage Mould growth may be common in wall cavities Once decay is established, there is a significant probability that ongoing decay can and will occur at and close to 18% moisture content. Moisture content of 24-35% will allow decay to Up to 18% 18-24% Department of Building and Housing Guide to the Diagnosis of Leaky Buildings (May 2011). initiate depending upon the treatment of the timber, however, once decay is established there is a significant probability that ongoing decay will occur at and close to 18% MC. 24% and above. [137] Under cross-examination Mr Gray further stated that whether the framing timber in the Bridgewater Apartments was treated or not (he assumed not, given the timing of the development’s construction) moisture at the levels he recorded would mean that the framing elements would not meet the B2 durability requirements and that, even if the timber was treated, toxigenic moulds would almost certainly grow on the surface, even if no actual decay occurred. [138] Mr Gray expressed the firm view that the durability requirement for the timber framing was 50 years pursuant to sub-cl B2.3.1 on the basis that such framing constituted a building element that was difficult to access or replace, and that what was involved was in the nature of walls providing structural stability to the building. The structural significance of the infill panels and associated framing is strongly supported in the evidence of Mr Bullen-Smith. [139] I agree that the juxtaposition of building elements such as floors, walls and fixings in sub-cl B2.3.1(a) (requiring a 50 year lifespan) and elements comprising the “building envelope” referred to in sub-cl B2.3.1(b)(i) supports the proposition that structural framing behind a cladding system (the envelope) has a durability requirement of a minimum 50 years. Moreover, failure of such elements could, in my opinion, go undetected during both normal use and maintenance of the building within the terms of sub-cl B2.3.1.(a)(iii). There is also the obvious difficulty of replacing the framing systems which provide in-situ support for the deck glazing systems and to which interior wall boards are attached. [140] Mr Gray also relied for his opinions on an article published by Beagle Consultancy Ltd whose principal, Dr Robin Wakeling, he described as the leading authority in relation to the effect of moisture ingress on timber. In his article Dr Wakeling suggests, as a rule of thumb: Once decay is established there is a significant probability that on-going decay will occur at and close to 18% MC but for uninfected wood the MC conditions required for decay are closer to the fibre saturation point, probably 24-30%. [141] Later in his report he identifies that fungal growth often occurs in the range of 16-30 per cent. [142] The plaintiffs in turn quote Dr Wakeling as saying that “when investigating an unknown situation it is important not to rely on MC readings in isolation” and that: an important qualification is that all moisture content readings and cardinal values used or referred to during investigation and remediation are indicative, not absolute (including 18%). [143] I accept that isolated readings in excess of the identified thresholds do not of themselves indicate systemic problems. However, that is not the case here. Rather, there is extensive evidence of readings which are sufficiently high to indicate, in the words of the Department of Building and Housing’s Guide that “remedial action is required to prevent future damage”. Indeed, the average readings are at the upper limit of what the Department effectively identifies as the “danger zone” (allowing for the two per cent adjustment previously referred to). [144] In my view, Mr Gray was on solid ground in identifying excess moisture problems in the north wall framing arising out of an original design or construction defect. As I have already indicated,40 I do not regard the framing as relating physically to other units by virtue of the solid inter-tenancy walls, but it supports an aesthetic component (the cladding system) which does so relate and is indicative of the fact that in their current construction the decks are not preventing the “penetration of water that could cause undue dampness” within the terms of sub-cl E2.3.2. Clearly the moisture is migrating from somewhere and the logical culprit is, as Mr Gray suggests, a design construction defect with the decks. [145] Similar problems with wooden framing arise in relation to the ACP clad “fins” because the construction detail allows water which penetrates the tiles (whether the result of cracks or simply the porosity of the grout) to travel under the 40 At [97] above. ACP panels where they abut the deck surface. Mr Gray’s evidence is that behind those panels is a timber frame which is significantly exposed to water ingress and condensation. Summary – repair and maintenance [146] The plaintiffs, in my view, fall a long way short of discharging the onus of establishing that repair and maintenance of the decks is not required. Having reached that point and having regard to the principles previously discussed,41 the decision of the Body Corporate as to how (in terms of method or scope) it addresses these problems is, in the words of Asher J in LV Trust Holdings Ltd v Body Corporate 114424, “highly persuasive”. Only in the event that the Body Corporate’s remediation plan went beyond repair and maintenance (including renewal) to a point where betterment was contemplated, would I regard it as appropriate for the Court to intervene. It is to that issue that I now turn. Betterment [147] The plaintiffs argue that the Origin Repair Plan, insofar as it contemplates bringing the development to a standard of current Code compliance, constitutes betterment which is beyond the repair and maintenance mandate of s 138 and is thus ultra vires. [148] The defendant acknowledges that works properly described as betterment within unit boundaries cannot be undertaken by it (absent consent). To that extent it recognises that proposals (for example, to install double glazing as part of the remediation works) cannot be imposed on individual propositions unless mandated by the relevant territorial authority as part of a building consent process. But it says the essential works contemplated by it, albeit that they are designed to satisfy the requirements of the current Code and to facilitate the issue of a new Code Compliance Certificate, are not in the nature of betterment. Rather, they simply reflect the reality of what is inevitably required to now lawfully remediate the original design and construction defects in the building. So, unfortunate though it is, 41 See [73]-[76] above. Mr Gray deposes that remediation cannot be effected by, for example, simply lifting the current deck tiles, relaying a new membrane and retiling. [149] The key consideration is the absence of proper falls to the decks as constructed. That issue is developed at length in Mr Bullen-Smith’s unchallenged evidence. He says that under current Code requirements all decks require a minimum of 1.5° fall, although some Councils (Auckland City being an example) require that any deck functioning as a roof have a 2° fall, the rationale being that construction to a minimum 1.5° requires a degree of accuracy which is not readily available. [150] In order to attain that fall the decks have to rescreeded. In turn, a problem is created at the junction between the interior and exterior of the apartments. Currently the ‘step down’ between the interior and the decks is between 60 and 70mm. Although Mr Gray does not identify this as a specific building defect he does say that it was non-compliant with the BRANZ “Good Membrane Practice Guide” current at the time of the building’s construction, which specified for a minimum 100mm threshold. In any event, creation of adequate falls now would all but eliminate the existing step down and to comply with Code requirements a “bulkhead” will need to be constructed with a 150mm threshold. As previously indicated, that in turn flows through to a requirement to “cut-down” or replace the existing joinery and replace the existing infill panels. It is for these reasons that the costs of a fully Code compliant remediation so substantially exceed the costs (less than $10,000 per level 2 and 3 unit) which the plaintiffs believe should be spent. [151] To an extent the competing positions tended to focus on whether a building consent was required for deck remediation works and the implications of s 112(1) of the Building Act 2004 in so far as it allows alteration of existing buildings. [152] In his evidence on behalf of the defendants, Mr Gray stated that in his assessment the deck remediation required application for and grant of a building permit. Such application has in fact already been made. He based that assessment on his analysis of cl 1 of Sch 1 of the Building Act which exempts from building consent requirements the “repair and maintenance of any component or assembly incorporated in or associated with a building provided that comparable materials are used”. However cl (1)(3) in turn provides: 1 General Repair, Maintenance and Replacement … (3) However, subclauses (1) and (2) do not include the following building work: (a) complete or substantial replacement of a specified system; or (b) complete or substantial replacement of any component or assembly contributing to the building's structural behaviour or fire-safety properties; or (c) repair or replacement (other than maintenance) of any component or assembly that has failed to satisfy the provisions of the building code for durability, for example, through a failure to comply with the external moisture requirements of the building code; or (d) sanitary plumbing or drainlaying under the Plumbers, Gasfitters, and Drainlayers Act 2006. [153] Mr Gray’s position was that replacement of the deck tiles and membranes required a building consent by virtue of sub-cls (a) and (c). [154] In respect of sub-cl 3(a) Mr Gray’s reliance is misplaced. Specified systems are defined in the Act to include identification as such by Order in Council. There is no relevant Order in Council relating to any composite membrane/tile deck cladding system. [155] Mr Gray is, in my view, on surer ground in relation to sub-cl 3(c). The durability requirements of the Code (cl B2 durability) have as their objective that a building will, throughout its life, satisfy the other objectives of the Code. Those objectives include the performance objectives of sub-cls E.2.3.1 and E.2.3.2. That is in turn reinforced by the wording of cl (1)(3)(c) of Sch 1 of the Building Act. [156] Whether a building consent is required is ultimately an issue of statutory construction (informed in this case by expert opinion as to the existing building’s satisfaction of performance criteria). In my view, having regard to the conclusions I have previously reached on the evidence, Mr Gray is correct in his assessment that a building consent is required to remediate the decks. The absence of adequate falls across the development, the evidence of ponding on many of the decks, and the absence or non-performance of deck membranes are sufficient to preclude compliance with the Code’s durability (and associated performance) requirements. [157] From this premise Mr Gray says the die is cast because it is “highly unlikely” that any territorial authority will issue a building consent to remediate the decks to the Code requirements applicable at the time the building was originally constructed.42 Rather, in order to obtain such consent and the Code Compliance Certificate which the defendant anxiously anticipates to restore value to the development, compliance with current Code requirements will be necessary. That in turn is the genesis of significant costs the Body Corporate now faces. [158] Mr Gray’s evidence in this respect was supported by Mr Bullen-Smith and was not, in my view, materially undermined on cross-examination. No contrary evidence was called by the plaintiffs.43 [159] Mr Brill’s response to this evidence was to say that the matter fell to be decided not on the basis of Mr Gray’s evidence but on the proper construction of s 112 of the Building Act which he said authorised remediation of the decks to 2003 standards. [160] I regard that submission as misconceived. Section 112 does not detract from the s 17 Building Act requirement that all building work must comply with the Building Code (or the ss 67-70 provisions relating to waivers or modifications which are not, on the evidence, engaged in this case). Building Law in New Zealand summarises the position as follows:44 42 43 44 Mr Gray’s recorded advice to the 2015 AGM was in terms “The Council would not allow the complex to be rebuilt to the 2004 Code but required it to be remediated to the 2014 code” (Minutes of AGM held 31 January 2015 at page 10). Significantly, the expert evidence called by the plaintiffs from Prendos Director Mr Maiden and which I ruled inadmissible following argument on the first day of trial, did not contradict Mr Gray’s approach in this respect. Building Law in New Zealand (online looseleaf ed, Thomson Reuters) at [BL112.02]. In other words: Any new work must comply completely with the Building Code subject to any waiver or modification granted by the territorial authority (for example, if a shower compartment made of ordinary glass is being replaced, then the replacement must be made of safety glass as required to comply with the Building Code); and After the alteration, the whole building must comply with the Building Code to the extent specified by s 112. [161] The “extent specified” is that the building will “continue to comply at least to the same extent as it did then comply”45 but that is a reference to the building as a whole. It is not a mandate for a repair or replacement of the particular element which has failed in accordance with some historical and now superseded Code requirement. [162] Department of Building and Housing’s: Determination 2011/09346 is on point and discussed in Building Law in New Zealand.47 The determination related to a relocated house and associated alterations. It confirmed that s 112 applied to the compliance of the building as a whole (after alteration) and not to the building work itself. Therefore new stairs replacing rotten stairs in a relocated house had to comply fully with the Building Code. They were not an existing building element simply because they were located in the same place and built to the same dimensions and configurations as the original stairs. [163] In my view this conclusion follows logically from s 17 of the Building Act, which provides: 17 All building work must comply with Building Code All building work must comply with the Building Code to the extent required by this Act, whether or not a building consent is required in respect of that building work. 45 46 47 Building Act 2004, s 112(1)(b)(ii). Departmet of Building and Housing Determination 2011/092 (21 October 2011). Building Law in New Zealand, above n 45, at [BL112.02]. [164] Significantly, the section consigns to the point of irrelevance much of the argument in the case about whether a building consent is necessary for the membrane work to the decks. Exactly the same principles apply whether or not a building consent is required. [165] For these reasons I accept the defendants’ position that the scope of works set out in the Origin Report does not constitute betterment and is thus authorised in terms of s 138. I exclude some of the improvements (such as double glazing, addition of ranch sliders to bedroom suites etc) which have been mooted in some of the defendant’s discussions. They should be presented to owners as effectively “optional extras” at individual proprietor’s cost. [166] I caveat the judgment also with the observation that, were there to be a lawful basis on which the relevant territorial authority issued a building consent for a reduced scope of works than that contemplated in the Origin Report, then the Body Corporate would necessarily need to consider its position further. As desirable as the objective of ensuring the building meets 2015 standards may seem to the defendant and the majority of its members, this judgment is premised on that being a necessary incident of required repair and maintenance and not a lawful objective in itself. Alleged procedural irregularity [167] The plaintiffs claim that, even if the Body Corporate has the power to undertake the ‘holistic’ repair contemplated in the Origin Report, it has never adequately authorised it. They do not question the Body Corporate’s commitment to that plan as a matter of fact. Indeed, their own statement of claim pleads: Despite the plaintiffs’ objections the Body Corporate intends to proceed with the Origin Repair Plan, subject to minor adjustments. It proposes to fund this work by levies, past and future, on all unit owners in proportion to their ownerships interest under the Unit Titles Plan. However, they say that there has never been a formal adoption of the Origin Repair Plan or resolution to undertake remediation in its terms, as they say is required. [168] That the Body Corporate by an overwhelming majority of votes wishes to proceed with a comprehensive and co-ordinated repair under the supervision of a single consultant and with the intention that the process deliver a building compliant with the current code within as tight a timeframe as possible cannot be seriously disputed. If any confirmation of that is required it is provided for by the 2015 AGM which took place five weeks prior to the hearing of this claim. At that meeting a motion, promoted by plaintiff Mr Small, was put in terms: ORDINARY RESOLUTION: a) “That the Committee’s advisers negotiate with tenderers for a staged repair plan as follows: i) Stage 1 of the works to be limited to the repair plan for the two penthouse decks (including any interior damage to Units 3.5 and 3.6), the staircase and the control room, with a target completion date of 1 May 2015; destructive testing should be undertaken on all floors. ii) Stage 2 of the proposed works, being all the remainder of the repair plan not included in Stage 1, be separately costed and be the subject of further consideration at an EGM to be held after the High Court decision in the injunction proceedings is available.” Moved: V Bath (substituted J Nimmo) Seconded: K Jury DEFEATED UNANIMOUSLY [169] That motion received no support from the meeting.48 Even allowing for the fact that the plaintiffs were precluded from voting as a result of non-payment of levies related to the remediation programme (and the legality of which they challenge in claims which are not addressed in this interim decision), the motion would have been heavily defeated. The reality is that within a body corporate of 22 owners there are five only who wish to proceed other than on the ‘holistic’ basis predicated in the Origin Report. [170] In approaching this aspect of the plaintiffs’ claim I am mindful therefore of the demonstrated wishes of the clear majority of owners. They should be respected if at all possible. In my view it is not the role of the Court to submit the Body Corporate’s resolutions to a pedantic or overly critical analysis. Albeit that often, as in this case, body corporates will engage the services of a professional secretary, 48 It was moved by Mr J Nimmo (despite the fact he did not support it) in order to facilitate discussion. Mr Small was precluded from voting because of unpaid levies. allowance should, in my assessment, be made for the fact that they are often comprised of non-professional people, and committees of volunteers. To expect the same precision of language as one might, for example, in a commercial contract is in my view unrealistic. In my assessment, the test should be whether, having regard to the full context in which resolutions occur, it can be safely concluded that the Body Corporate has indeed committed itself to the Origin Repair Plan. [171] For the defendant Mr Allan submits that the UTA 2010 does not even specify that a resolution is a prerequisite for a body corporate fulfilling its functions. He says that it is not unlawful for a body corporate to do its duty under the Act without a resolution and that such a resolution is “merely a record for future reference”. [172] In my view that submission is difficult to align with the provisions of s 101 of the Act. Subsection (1) provides that: 101 How matters at general meeting of body corporate decided (1) Any matters at a general meeting of a body corporate relating to an exercise of a duty or power that may not be delegated … must be decided by special resolution. [173] In so doing the UTA 2010 recognises that even where a body corporate is under a statutory duty (as for example that imposed by s 138), exercise of that duty occurs via resolution, either “special” in terms of s 101(1) or “ordinary” in terms of s 101(2). [174] However, I agree that the fact that the Body Corporate is under a duty to repair and maintain the common property, assets and building elements identified in s 138(1) is an additional reason why a relatively benign approach should be adopted to the meaning and effect of its resolutions in that respect. [175] I make one further preliminary observation. If contrary to the conclusion I have arrived at I had held that there was some inadequacy in the Body Corporate’s adoption of the Origin Repair Plan and its commitment to undertake the works in the manner Origin described, then I would have considered the appropriate course to have been for any consequential orders in the plaintiffs’ favour to have lain in Court for a period of two months in order to allow adequate opportunity for such procedural/technical issues to be re-addressed. Again I would consider it the Court’s function to facilitate and not obstruct the wishes of the majority of owners. [176] I turn then to the relevant factual background and resolutions. [177] The critical meeting is the EGM of the Body Corporate held on 9 November 2010. In its statement of defence the defendant pleads that at this meeting the Body Corporate unanimously resolved to: … effect a repair of the OCDD [original construction and design defects] by a single contractor under the supervision of a single consultant for the whole of the structure so as to render the defendants and owners structure code compliant and thereby obviate the stigma attaching to the building and units. [178] In considering the specific resolutions passed at that meeting the defendant submits that context is everything. Specifically it refers to the following: (a) Against a history of ponding on some of the decks and water ingress into level 3 apartments from the penthouse decks in August 2013, reports were commissioned from first AA and subsequently Origin into the weathertightness and performance of the building. The brief to Origin occurred in the context of a looming limitation date in respect of proceedings and sought advice as to whether Bridgewater’s structure met the requirements of the Building Code at the time it was constructed. Mr Andrews describes the purpose of the report as being “to identify original construction and/or design defects in Bridgewater for the Council proceeding”. (b) The Origin Report was published on 18 October 2013. It addressed in detail identified original construction and design defects and set out “remediation description”, the purpose of which was to summarise the required works needed to repair the building and ensure that it will continue to meet the future requirements of the NZBC. It is common ground that the plan which Mr Gray describes is the “holistic” option which the Body Corporate wishes to pursue. In particular, it provides for removal and disposal of all existing infill panels, deck tiles and membranes, removal of all exterior joinery units to the north elevation, rescreeding decks to ensure adequate falls, provision of adequate upstands, and installation of new deck membranes with tiles on supporting deck jacks. (c) The Origin Report was distributed to all owners within four days of receipt together with an agenda for the EGM to be held on 9 November 2013 and the necessary proxy postal voting forms. (d) On the same day all owners were provided with a copy of the statement of claim dated 4 October 2013 which the Body Corporate had lodged with the High Court in Whangarei in order to protect relevant time limits. That statement of claim pleaded, inter alia, that: 19 As a result of the Defects and Damage the plaintiffs will be required to carry out extensive repairs to the Bridgewater Bay apartments to rectify the Defects and the Damage. Claimed losses included loss of rental income, costs of alternative accommodation and moving and storage costs, all consistent with a substantial repair and an inability to occupy the apartments while that was taking place. (e) The agenda for the EGM consisted of a detailed introduction and then a series of proposed resolutions, some with their own specific introductory paragraphs. (f) The general introduction recorded the history of leaks from the fourth floor penthouses and that the Committee had requested solicitors Grimshaw and Co investigate the ability to recover associated remedial costs from relevant parties. Grimshaw’s recommendation to the Committee was to engage an expert to undertake a review of the balance of the complex in case the problems were systemic. The introduction noted the urgency with which this needed to be done in view of relevant limitation periods. Reference was then made to the attached report from Origin. (g) The following is then recorded in the minutes: Unfortunately the report suggests that a complete recladding of the northern face of the building is necessary along with re-working of all the deck areas to create proper falls in a weathertight solution. The ends of the buildings will also need attention as will Harditex cladding on the two penthouses… The Committee believes it is important that an extraordinary general meeting be held to discuss the report and to enable owners to address any questions they may have to Mr Gray or Grimshaws. The meeting has been scheduled for Saturday 9 November 2013 at 10.30 am…. The Committee are very conscious that this communication will come as a disappointment to all. However, now that the situation has been largely assessed it is important that the Body Corporate agree how to address them. (h) Under the “agenda” section the following appears: 3) Receipt of Origin Building Consultants Limited October 2013 Report It is anticipated that there will be a brief presentation by Mr Gray followed by a full and frank discussion on the report and its implications. Options available to owners if you are not satisfied with the report include seeking verification of Origin’s findings and recommendations by either: i) Having the report peer reviewed, or ii) Obtaining an independent report from the government subsidised Weathertight Homes Resolutions Service. It is the Secretary’s recommendation to the Committee that if verification is to occur by way of a review then the WHRS is a useful vehicle for this. Motion “That the Body Corporate look to lodge a multi-unit claim with the WHRS to obtain an independent report on the buildings’ condition.” (This requires 80% of owners to sign a consent form with the WHRS) 4) Repair Management It will be necessary for the Body Corporate to engage an appropriate lead consultant to manage the repair process. This will either be an architect or consultant familiar with remedial works arising from design and construction failings. The role of the architect will be to design a remediation solution, prepare plans and specifications sufficient for tendering and building consent, manage the tendering of the works and oversee the remediation. Motion “The Committee be delegated authority to investigate and appoint a lead consultant to manage the building remediation process.” 5) Defect Litigation Mr Paul Grimshaw of Grimshaw & Co will be available to address the meeting. Grimshaw’s are NZ’s pre-eminent legal firm in the area of representing plaintiffs in construction defect claims. Based on the information to hand Grimshaw’s believe a sound case exists against a number of parties including most importantly the Far North District Council. The importance of Far North District Council as a defendant is that unlike other defendants it cannot go broke and it has statutory duties in terms of the building works which appear to have clearly been breached. Motion “The Committee’s appointment of Grimshaw’s to instigate defect litigation is ratified and Grimshaw’s be engaged to represent the interest of the Body Corporate and owners in the proceedings.” (i) In addition the Committee had, prior to the EGM, received an estimate of the cost of remedial works from quantity surveyors Kwanto Limited showing the cost of a “complete recladding of the northern face of the building” as being $1.7 million. One of the plaintiffs, Mr Butcher, deposes to having received a copy of this estimate on or about 5 November 2013, albeit he was not at that stage a committee member. Plaintiff Mr Small said in evidence that although he did not receive the report he was aware from the discussion which occurred at the EGM of Kwanto’s estimate. [179] Set out below are the relevant passages from the minutes relating to receipt of the Origin Report and consequent resolutions: 4.0 BUILDING ISSUES The Secretary introduced Mr Gray to the meeting. commented: 1. Andrew There are two types of building reports that are generally produced. The first deals with damage and the second with liability. The report that has been presented to date deals with damage. It responds to: i. ii. iii. iv. Is there damage? Does it need to be repaired? What is needed to remediate? What is the likely cost? The second report about liability is about who is responsible and why. Clearly if a decision is made to proceed down the litigation route then this report will need to be prepared as well. If a decision is made to repair prior to litigation then during the repair process the necessary evidence will become available. Andrew noted that the survey was not a complete survey as access to some parts of the building was simply not available. Practical access to the top areas was not available. As a result the report contained some assumptions however the underlying scope of remedial repairs is in his view sound. This includes: a. b. c. d. The decks. The walls inside the decks. Inter-tenancy walls between decks. The ends of the building (not the concrete elements) and hoppers at ground level. Andrew confirmed that the exercise carried out provides for a “likefor-like” replacement. This is to reflect the legal claim that would be possible in terms of the complex. This is not to say that the remedial work would need to be an exact like-for-like and it is likely it would be sensible for the Body Corporate to consider changing cladding options to improve design elements and to remove stigma. Andrew noted that the next decision for owners is how to move forward. This included a decision as to whether to pursue the claim first or to repair first. He noted most people would repair first gathering their evidence for trial during the remediation process. The evidence needs to identify: a. b. c. d. Why and how the buildings leaked. How the construction compared to the consent drawings. How the construction compares with technical details. The quality of documentation and construction. Mr Gray confirmed in response to questions: Only the areas where damage has been identified will be repaired. Targeted repairs are generally not permitted under the current Building Act. Attempting to repair just around the windows where water ingress was evident is not permitted. To be compliant with the Building Code the building needs to meet performance standards (E2 and B2). This essentially says that the building should not suffer from external water sources and the structural elements should have a 50 year life. The joinery when removed needs to be refurbished. An alternative is to replace with new joinery depending upon cost. To achieve appropriate minimum falls the decks will need to be taken up and re-screeded. Nibs will need to be created on which the cut down joinery will be reinstalled. A discussion took place in relation to the possibility of seeking to register with the Weathertight Homes Resolution Service. This will enable the Body Corporate to obtain a further report effectively duplicating Andrew’s report at a cost of fifteen hundred dollars. There would be a time delay of 3 – 6 months in accepting the report even if the 80% owner approval threshold which is required for registration was achieved. In carrying out the report destructive testing would take place which would mean holes and patches cut out of the cladding to assess the extent of damage behind. After discussion it was resolved. Mr Gray noted notwithstanding the fact that water ingress may not be evident from the inside of the units the design and construction of the complex was such that there was a strong probability of ingress. The readings taken in terms of moisture ingress were consistently high across the range of readings. The number and extent of high readings are sufficient to make an assessment of general failure. Often it is not until the claddings comes off the extent of water ingress and decay is evident. Due to the timing of construction it is probable that the timber is not treated. Even if treated, the level of treatment will leach out over time and in likelihood would breach the 50 year durability provision. RESOLVED “That the Body Corporate not lodge a claim with the WHRS.” Moved: J Nimmo Seconded: W Ludwig CARRIED 4.0 (sic) COMMITTEE The next agenda item contemplated the Committee being delegated authority to appoint a lead consultant. The need for the Committee to be empowered reflected a timeline which would see building works complete by December 2014. For this to be achievable it would be necessary for the consultant to be appointed prior to Christmas and the preliminary work undertaken for presentation to the Body Corporate AGM in late January. Additional nominations for the Committee were received from Tony Butcher, Neville Eade, Phil Andrews, John Nimmo and Terry Gray. Concern was expressed about the possibility of one unit being represented by two Committee members and the optimum size for the Committee together with the benefit of onsite owners. After discussion it was: RESOLVED: “That the Committee be enlarged by three members being Phillip Andrews, John Nimmo and Tony butcher to join Viv Bath and Margaret Gray”. Moved: W Ludwig Seconded: V Bath CARRIED RESOLVED “That the quorum for the Committee shall be fixed at three.” Moved: K Townsend Seconded: W Ludwig The meeting then went back to Motion 4 and it was: RESOLVED: “That the Committee be delegated authority to investigate and appoint a lead consultant to manage the building remediation process”. Moved: K Townsend Seconded: L Small CARRIED The Secretary indicated that he had taken the liberty of contacting four reputable consultants and requested that they put forward proposals for the lead consultancy role by the previous Friday. These had been received, collated and a scheduled distributed together with copies of the proposal to the Committee. The larger Committee would now be copied in. The Secretary noted that four of the proposals were similar in cost and in line with or under the Kuanto (QS) forecast. One was significantly above. Three of the four consultants estimated a timeline of 48-52 weeks from start to finish. Mr Gray noted that this was consistent with his recommendation. Two, Context Architecture and Resolution Architecture suggested that in addition to their architectural services they would look to utilise the services of a Building Surveyor/Clerk of Works for onsite management and oversight. It was suggested to the Committee that consideration be given to appointing either of Context or Resolution. The Committee would meet in person or by email/teleconference to resolve this as soon as possible. At this point the meeting thanked Mr Gray for his attendance and he left the meeting. [180] In relation to the key resolution “that the Committee be delegated authority to investigate and appoint a lead consultant to manage the building remediation process”, the plaintiffs say that this does not address any of the who, what, why, when, where and how questions relating to the process and that it is an inadequate foundation for the pleading in the statement of defence previously referred to. [181] In response the defendant says that, having regard to the context in which the resolution was passed, the resolution is adequate authority for what is proposed. In particular it says: 1. The agenda specifically identified a full reclad as necessary. 2. The agenda identified as options either acceptance of the Origin Report or obtaining an independent peer report or a report from the Weathertight Homes Resolution Service. 3. The Body Corporate’s resolution in terms that it “not lodge a claim with the WHRS” can be construed as an affirmative resolution adopting the Origin Report, particularly given the reference in the agenda to the circumstances (non-satisfaction with the Origin Report) in which WHRS involvement might be sought. 4. The statement of claim left nobody under any illusion that a substantial repair was required. 5. The discussion in the minutes under the heading “Committee” indicated a desire on the part of the Body Corporate to move forward speedily with the repair process and that it anticipated a December 2014 completion date. 6. The resolution takes its flavour from the agenda and in particular the explanatory material under the heading “Repair Management”. The defendant says that, assumed within the appointment of the lead consultant, is that such a consultant would design a remediation solution, prepare plans and oversee the works, all as generally contemplated in the Origin Report. Essentially the Body Corporate invites a construction of the resolution in terms “We have decided to do the job generally in accordance with the Origin Repair Plan. You, the Committee, are now instructed to get on with the job, first by investigating options for the appointment of a consultant and then appointing such consultant to manage the process”. [182] I have come to the conclusion this is the correct construction of the resolution while acknowledging that it could, of course, have been more fulsomely expressed. I do so for the following reasons: (a) The only repair plan before the owners at the EGM was that developed by Origin. (b) The plan set out in comprehensive detail what the problems were with the building and what was required to remediate them. (c) Mr Gray spoke to the report at length and the minutes record that he was clearly interrogated in some detail about it by those present. (d) The meeting decided against options promoted in the event that it was “not satisfied with the report”. I accept therefore the defendant’s submission that it could be taken as having adopted the report – as much so as if a specific resolution to that effect had been passed. (e) The key resolution refers to the appointment of a lead consultant “to manage the building remediation process”. That can only refer to the “process” already extensively discussed at the meeting and identified in the Origin Report. As such the resolution implicitly accepts the Origin Repair Plan. The only significant decision yet to be taken was identification of the relevant consultant. That is confirmed by the ensuing discussion which focuses on four options and concludes with the statement that “the Committee would meet in person or by email/teleconference to resolve this as soon as possible”. [183] I also accept Mr Allan’s submission that the resolution was in fact in the nature of an instruction rather than a delegation. Certainly the requirements of reg 22 of the Unit Titles Regulations 2011 sit uncomfortably with the content of the resolution. [184] I consider myself supported in this construction of the resolution by the subsequent conduct of the parties. Although I do not regard the present case as governed by the rules of contractual interpretation, I am guided by what the cases in that context say about subsequent conduct as a guide to interpretation, namely that the focus should be on actions which shed light on the shared intention of the parties rather than the meaning intended or understood by one party only.49 [185] In my view the subsequent conduct best illustrative of what was actually approved is that of the Body Corporate’s Committee. Among its members was Mr Butcher, who is one of the plaintiffs in this proceeding. Having appointed Resolution Architecture as the consultant to manage the remediation process the Committee went on, in the period January to May 2014, to: 1. Approve Resolution Archiecture’s detailed design for the purposes of preparing a building consent application; 2. Approve a structural design quote from Cook Costello Engineers; 3. Approve WSP Fire Consultancy to provide fire engineering consultant services; 49 See for example Wholesale Distributors Ltd v Gibbons Holdings Ltd [2007] NZSC 37, [2008] 1 NZLR 277. 4. Confirm ongoing consultancy arrangements with Veron Limited (formerly Origin). [186] In relation to the design approval document for building consent purposes the following extract from the cross-examination of Mr Butcher is instructive: Q He asked you and your co-Committee members to sign the design approval document, didn’t he? A. Well I’m not sure whether I signed it, to be quite honest. Q Just answer my question. He asked you to sign it didn’t he? A Yes, yes he did. Q And what did you do having received his email, asking you to sign the design approval authority? A I’m not sure what I did to be quite honest. Q Well you certainly did not object to your other co-Committee members signing it, did you? A That’s right. Q You were comfortable with them – A Yes. Q – signing the design approval authority? A Yes. Q And did you realise when this email came through, that this was the remedial solution that the Body Corporate had instructed you to proceed to put into effect? A Yes. Q And in putting it into effect, you were also aware the Body Corporate had on the 25th of January 2014, given some instructions to the architect to make some changes to the design, is that correct? A Yes that’s right. Q And you approved those design changes as well did you? A Again, I’m not sure whether I did or not. Q You certainly didn’t object to those design changes did you? A No I did not object to it. [187] Also instructive is the plaintiff Mr Small’s correspondence to the Body Corporate in September 2014 at which point he had decided no longer to support the Origin Repair Plan. In that correspondence he refers to discussions with other owners “who asked why I changed my view after originally voting in favour of the complex rebuild”. Mr Small was an attendee at the November EGM and although in his affidavits and under cross-examination he stated that all the EGM did was give the committee authority to advance “to the next step of a full investigation towards the repair of our building”. I consider his September 2014 statement as to what he was voting for more compelling. [188] In addition, and by way of backstop to the November 2013 EGM resolution Mr Allan relied in closing on several subsequent resolutions of the Body Corporate. In response Mr Brill took a pleading point saying that the statement of defence had relied exclusively on the decisions taken at the meeting on 9 November 2013. Mr Brill is correct in terms of how the matter is pleaded. Because of the conclusions I reach in terms of proper construction of the November resolutions it is not ultimately necessary for me to rely on Mr Allan’s identified “backstops”. However, had it been necessary I would have been reluctant to see them determined on a pleading point and would have granted an amendment to the statement of defence to accommodate them, if formally sought. [189] The matters to which Mr Allan refers are threefold: (a) (i) At the AGM on 25 January 2014 an extensive presentation was made by Messrs McLeay and Miram of Resolution Architecture about the scope of the intended remedial works under headings “Roof”, “Exterior Cladding”, “Decks”, “Lift and Plant Room”, “Fire Protection” and “Other Issues”. (ii) The minutes record a general discussion about the wish of members to progress the remedial work as expeditiously as possible and their desire that consultants not be delayed in progressing the remedial designs. To that end a resolution was unanimously passed in terms that “The meeting approve a design utilising the following key components: a) New wall aluminium weatherboarding; b) Decks to be retiled with tiles on jacks; c) Double glazing to be installed in new window joinery…” (iii) This resolution was not identified in the agenda and in terms of s 101(3) of the Act therefore could not have been lawfully able to be voted on. (iv) Mr Allan submits, however, that the adoption of the minutes of that meeting at the next EGM of the Body Corporate, held on 20 May 2014, constitutes a ratification of the resolution. He relies in that respect on the decision in BC172018 v Gundry.50 Although the invalidity of the January resolution relates not to the content of the resolution but the process adopted, I doubt whether it is possible to ratify a resolution which the statute says was incapable of being voted on in the first place, and no authority was cited in support of that proposition. That issue aside, I do not accept that the latter confirmation of minutes at which an unauthorised vote took place can of itself be considered an adequate act of ratification. The decision in Body Corporate 172018 v Gundry does not assist. In that case an express resolution ratifying earlier committee resolutions was passed. (b) (i) Next Mr Allan relies on the decision of the Committee previously referred to approving Resolution’s design for the purposes of a building consent application. In that context Mr Allan refers to the unanimous resolution of the Body Corporate carried at its AGM on 25 January 2014 delegating to the Committee “the full powers and authorities of the Body Corporate, subject to any prior direction given at any general meeting of the Body Corporate or prohibition as contained in s 108(2) of the Act. He also refers to the (uncontested) 50 Body Corporate 172018 v Gundry [2014] NZHC 954. notice of that delegation given pursuant to the Unit Titles Regulations 2011. (ii) For the plaintiffs Mr Brill challenges that delegation on the basis that the relevant resolution is not identified as “a special resolution” in the agenda and minutes. However, it was so identified in the postal voting or directed proxy form sent with the agenda and, having received the requisite majority required for a special resolution I consider it valid as such. (iii) I regard the Committee’s approval of the design as significant. From that point on there cannot, in my opinion, be any realistic argument that the Body Corporate had not, in a procedurally acceptable way, committed to the “holistic” solution. (c) (i) Thirdly, Mr Allan relies on the failed resolution promoted by Mr Small at the 2015 AGM (refer [164] above). (ii) That resolution having been defeated, Mr Allan submits that the corollary of the defeated propositions can be taken as accepted, namely that the repair proceed on a comprehensive rather than “staged” basis and that stage 2 (everything other than repair to the penthouse decks, staircase and control room) not be deferred. (iii) I have already indicated my view that defeat of this resolution indicates the consistency of the Body Corporate’s position throughout. [190] As indicated I do not consider it is necessary to rely on these backstops. [191] I make one final observation in respect of the minutes of the 9 November 2013 EGM. [192] At page 5 there is a section which appears under the heading “Costs”. It commences with the following: In response to a query as to what levies would be necessary the Secretary confirmed: 1. Costs through to the annual general meeting scheduled for Saturday 25 January 2014 can be met from Body Corporate reserves. 2. There is likely to be a need for a special levy at the AGM (of between $50,000 and $100,000) to take the Body Corporate through to the point where tenders had been obtained and a decision to proceed with remedial work occurred. This will necessitate a major levy. [193] Initially I questioned whether these recorded observations contemplated a later revisiting of the issue and a decision at that point only to adopt the Origin Report. Ultimately, however, I was persuaded by Mr Allan’s arguments in terms: 1. This item in the minutes records a matter of general discussion and not an agenda item. 2. It is not a discussion about whether it is intended to repair in accordance with the Origin Report but rather how much money would be necessary to get the Body Corporate through to the point when tenders were called. 3. The reference to “proceeding with the remedial work”, in context, refers to acceptance of any specific tender or, in other words, a decision to contract with someone for which there would need to be a levy. [194] I do not therefore regard this aspect of the Minutes as detracting from my previous analysis. Declarations and injunction [195] The above findings are sufficient to dispose of the application for declaration and injunction in paragraphs [A] to [D] of the plaintiff’s prayer for relief (first cause of action). [196] Prayer F relating to legal costs incurred in the context of the Body Corporate’s claim against Far North District Council and others was abandoned in opening. [197] That leaves prayer E which seeks: A declaration that the Body Corporate must recover the cost of repairs or maintenance undertaken within any Unit from the owner of that Unit (except where damage is caused by water leaked from another Unit). [198] This declaration was addressed by Mr Brill in opening but not further elaborated on in closing. [199] The position is that the Body Corporate has not yet made any decision pursuant to s 138(4) of the UTA 2010 relating to the recoverability of costs incurred for “repairs or maintenance to building elements or infrastructure contained within any principal unit”. Indeed, apart from consultant’s reports no such costs have yet been “incurred” within the terms of the section because of the challenge made in the present proceedings. In my view the Body Corporate should be entitled to consider this issue as and when it arises without the prior dictate of the Court. The approach it may choose to adopt in relation to a holistic repair may well be different to that which may, for example have applied if the plaintiff’s have succeeded on their primary claims and the only significant repairs contemplated were those at penthouse level. Even if there was jurisdiction to make a declaration at this stage, which I doubt given the prospective nature of the expenses, I would decline to exercise the relevant discretion. The matter can be addressed at the relevant time. Result [200] I dismiss the claims for declarations and injunctions sought in paragraphs AE of the plaintiffs’ prayer for relief (first cause of action). [201] I adjourn the plaintiffs’ second cause of action and the defendants’ counterclaims to be determined on application of any party no earlier than 30 working days following delivery of this interim judgment. Costs [202] I reserve costs to be addressed in the Court’s final judgment. In the event the Court is not called upon to dispose of the plaintiffs’ second cause of action or the counterclaims, and costs are unable to be resolved by the parties, I invite memoranda (maximum five pages) which should proceed on the basis of a 2B award in the defendant’s favour. In that event I invite the parties to exchange memoranda in draft so as to limit areas of disagreement. __________________________ Muir J