Download electrical design brief - Turkish Technology Group

Survey
yes no Was this document useful for you?
   Thank you for your participation!

* Your assessment is very important for improving the workof artificial intelligence, which forms the content of this project

Document related concepts

Electrician wikipedia , lookup

Mains electricity wikipedia , lookup

Ground (electricity) wikipedia , lookup

National Electrical Code wikipedia , lookup

Telecommunications engineering wikipedia , lookup

Electrical wiring in the United Kingdom wikipedia , lookup

Electrical wiring wikipedia , lookup

Home wiring wikipedia , lookup

Transcript
ERKEM
İnşaat Sanayi ve Ticaret A.Ş
PROJECT BRIEF
CONSTRUCTIONAL AND ARCHITECTURAL DESIGN BRIEF:
This project shall completely construction of Expo Center of Al Najaf Al Ashraf using with
materials developing today’s technology and scope of the works is explained with the items
mentioned below;
1. Constructional Works :
1.1. 1 storage building will be constructed with steel, according to the structural and
architectural design of the buildings.
1.2. Internal walls of all buildings will be bond according to the design.
1.3. The plastering of the internal walls will be completed after the installation of
electrical and mechanical materials.
2. Heat and Water Insulation :
2.1. Water at the roofs will be collected with the drains and PVC pipes then
transferred to the main drainage line.
3. Architectural Works :
3.1. Windows :
Windows will be manufactured by using aluminium profiles and one glazing glass and
installed according to the drawings.
3.2. Wooden Doors :
Internal doors will be wooden material and these are manufactured and installed according
to the Turkish Standart Norms. We reserve the right to select the manufacturer and/or
supplier of each item depending on the technical, commercial and especially delivery
conditions during the material order stage based on availability and production schedule of
the manufacturing plants.
3.3. Aluminium Doors :
Main entrance doors and fire escape doors of the buildings will be aluminium doors. these
are manufactured and installed according to the Turkish Standart Norms. We reserve the
right to select the manufacturer and/or supplier of each item depending on the technical,
commercial and especially delivery conditions during the material order stage based on
availability and production schedule of the manufacturing plants.
3.4. Ceramic Floor and Wall Coverings :
All WC of all buildings floors and walls will be covered by the ceramic tiles.
1/9
Tunus Cad. No. 76/5 Kavaklıdere 06680 Ankara / Turkiye Tel: +90 312 468 85 00 Fax: +90 312 467 94 95
ERKEM
İnşaat Sanayi ve Ticaret A.Ş
3.5. Granite Coverings :
Stair and threads will be covered with granite material.
3.6. Suspended Ceilings :
Only in WC suspended ceiling will be constructed. Suspended ceiling manufacturers names
are Tacer, Aspen, also we reserve the right to select the manufacturer and/or supplier of
each item depending on the technical, commercial and especially delivery conditions during
the material order stage based on availability and production schedule of the manufacturing
plants.
3.7. Painting :
All building internal walls will be painted.
3.8. External Wall Painting :
External walls of all buildings will be constructed with painted sandwich panels .
3.9. Aluminum Balustrade :
Internal stair rails will be manufactured by aluminum material.
4. Perimeter Walls :
Perimeter walls will be constructed according to the to the structural and architectural design
of the buildings.
All the walls will be paint with acrylic paint internal and external sides.
2/9
Tunus Cad. No. 76/5 Kavaklıdere 06680 Ankara / Turkiye Tel: +90 312 468 85 00 Fax: +90 312 467 94 95
ERKEM
İnşaat Sanayi ve Ticaret A.Ş
ELECTRICAL DESIGN BRIEF:
The electrical systems will be builted in accordance with the current edition of the following
satandarts :
All wiring will be in PVC conduits and cable tray. Routing of power cables will be selected to
minimize the effect of magnetic fields on other equipment.
Normal Power Distribution
The primary utility feeders will come below groud in a concrete duct-bank off the local
electric otority loop distribution system.
There will be load break switchgear located in the main Electrical Room located in the
Transformer building.
For the Al Rasheed Theater, 2000 kW mechanical and 1800 kW electrical power was
accepted as power. According to the IEC 60439-1 standards 1x4000kVA transformer and
3x1250 kW standby generator was selected.
The building will house a 1*4000 kVA transformer in the Transformer Building.
Our desing will be based on power density calculations as required by the Electrical rules for
accupancies and other Electrical equipment load taken in addition to the base load
All Electrical conductors are to be copper .
In generaly all conductors are to be cable in PVC conduit and cable tray.
Every Hall will be equipped with a 220V / 380V main electrical pane
Low voltage distribution cables will be designed to be multi-core copper conductors , PVC
insulated and flame retardant PVC sheathed.
Low voltage and low current cables installed in the same cable tray a steel separator shall
be used between them.
Low voltage distribution cables, lighting, socket, control equipment, feeder and all cabling
system
ELECTRICAL PANELS
Main panel will be free-standing type and manufactured of 2mm sheet steel with
electrostatic paint.
Lighting and receptacle panels shall be surface mounted type and manufactured of 1,5mm
sheet steel with electrostatic paint.
All panel incoming and outgoing feeders will be protected against shot-circuit and overload
by miniature circuit breakers or molded case cicuit breakers of suitable rated current
capacity.
All panel will have reserve space of 20% for future expansion.
ESSENTIAL POWER DISTRIBUTION
A new essential power feed will be run from the essential panel located in all corridor in the
cable tray system that is being supplied from the Transformer unit essentisl plant.
The main service will terminate in a splitter and will feed the following automatic transfer
switches.
3/9
Tunus Cad. No. 76/5 Kavaklıdere 06680 Ankara / Turkiye Tel: +90 312 468 85 00 Fax: +90 312 467 94 95
ERKEM
İnşaat Sanayi ve Ticaret A.Ş
Transfer switch for life safety loads
 Transfer switch for life safety with exit signage
 Fire alarm network system
Transfer switch for non-life safety loads
 Essential power for specific equipment such as free Hall
 Building Automation control system
 General exhoust fans
 Sanitary pumps
 Storm water pumps
 Sum pumps
 Security system
 Telephone and data system
 Domestic hot water system
 Domestic cold water system
The generator will be 3*1250 kW stand by rated. Generator will be housed in suitable
sound attenuated enclosure.
Emergency power will meet the minimum operation requirements for a period of no less the
8 hours.
All emergency wiring is to be wire in conduits or multi-conductor cables.
The emergency transfer switch will be 3 phase , 3 pole , contactor style with electronic
controller, bypass-isolation , generator start signal and load-dump relays.
FIRE ALARM
The building will be provided with an addressable single stage fire alarm system with battery
charger and standby batteries.
The main fire alarm control panel will be located in security&information building or entrance
hall information desk to the building.
The fire alarm detection and addressable loop wiring will be class A.
Horns will be provided throughout the building with combination horn-strabes used .
Visual strabes will also be utilized in areas of high ambient noise including all areas.
Primary means of detection will be via manual pull stations. Smoke and heat dedector will
be provided.
PUBLIC ADDRESS SYSTEM
The public address (PA ) system will be installaed both to serve as generaly announcement
system during normal operation and an emergency announcement and evacuation system
in case of emergency.
LIGHTING
High efficiency luminaires will be provided as per the recommendations of the IES.
Primary interior shall be illuminated with recessed fluorescent fixture and spot lighting
equipment with 4*18 lamps. The fixtures will be controlled with local switches.
4/9
Tunus Cad. No. 76/5 Kavaklıdere 06680 Ankara / Turkiye Tel: +90 312 468 85 00 Fax: +90 312 467 94 95
ERKEM
İnşaat Sanayi ve Ticaret A.Ş
Area Light Level
AREA
Hall
Entrance
Meeting rooms
Corridors
Washrooms
Storge
Mech./Elec.Room
CCTV room
LUX LEVEL
100 / 250W
250W
200W
50W
200W
200W
300W
200W
The VIP and Theater hall area luminaries will suit architectural elements.
Washrooms will be finished and mounted luminaries and decorative cove lighting
appropriate for its environment.
Shower area luminaries are to be compact fluorescent down lights with lenses suitable for
wet environments.
Service rooms will be lit with chain hung or ceiling mounted direct parabolic fluorescent
luminaries with wire guards.
Stairwells will be illuminated by applique armature light fixtures equipped with 75W lamps.
Emergency lighting will be provided to meet building code and will be provided in electrical
and mechanical rooms. Battery packs will be installed in CCTV rooms , main electrical room
and main mechanical room.
Emergency lighting will be provided by the essential power distribution system throughout.
Outdoor lighting will be mounted 3m galvanized steel poles.
At external wall, there will be no lighting.
Exit door will be wall mounted luminaire.
Decorative ligting will be provided for wall painting with LED system
STRUCTURAL CABLING AND TELEPHONE / DATA SYSTEM
In office areas , telephone and data outlets are designed per desk according to the furniture
design.
All telephone outlets except the wall types are terminated with RJ45 ( Cat6 ) type sockets.
All Data outlets except the wall types are terminated with RJ45 ( Cat6 ) type sockets.
Wireless communication of Telephone and data comminication for generaly area.
All active equipments for data and telephone system are NOT included in our offer.
GROUNDING SYSTEM
An grounding system will be provided in the main electrical room. All transformer neutrals
will be connected to the grounding bar and common cable connected back to the system
ground.
Grounding will be provided following IEEE standard and Electrical safety standarts.
Separated communication ground will be provided off of the building ground system.
LIGHTNING PROTECTION
Active lightning conductor used for lightning protection.
Lightning protection will be designed and installaed in accordance NF C 17-102 installation
code for lightning protection systems.
Perimeter ground loop with 3m ground roads will be installed of the building groud area.
5/9
Tunus Cad. No. 76/5 Kavaklıdere 06680 Ankara / Turkiye Tel: +90 312 468 85 00 Fax: +90 312 467 94 95
ERKEM
İnşaat Sanayi ve Ticaret A.Ş
The lightning ground grid will be connected to the building electrical ground grid at a
minimum of 2 locations.
CCTV
The CCTV room estimated to have approximately 1 rack , 2 19” color monitor each rack
and system is estimated to have lood of 2kW.
In this Project 24 pieces internal camera and 16 pieces external camera will be used.
Probolic fluorescent fixtures fixtures equipped with 2*18 lamps and a wire guard will be
suspended ceiling mounted and will provide an average light level a of 200 lux.
Emergency lights connected to the emergency system and will be of the same type as
mentioned above.
COMMUNICATION – SECURITY SYSTEM
Rough in PVC conduit, cable tray and junction box system will be provided for the
communication system and security system .
Include an allowance for security devices such as CCTV system.
All Electrical installation works related , lightning protection , Grounding , conduit , cable
trays , cable , structured cabling network , MATV , wiring devices ( Switch – Sockets ) ,
Panelboards , interior and Exterior lighting any installation work are assumed as finished
without defect.
THEATRE PROFESSIONAL SOUND SYSTEMS
Digital 48 Channel Audio Mixer and 96 Channel 96kH 24 Bit AES Digital Recorder , Matrix
Processor , Touchpanel
THEATRE PROFESSIONAL LIGHT SYSTEM
4k 4000 Channel DMX Light Mixer , Gateway DMX Output Module , DVI 21” LCD Monitor ,
Professional DMX Moving Head Spot and Wash
THEATRE PROFESSIONAL DIGITAL SURROUND SYSTEMS
Dolby CP 650 Digital Surround Prosessor
STAGE PLATO EQUIPMENT
SOUND STUDIO EQUIPMENT
TURNKEY FRONT END LABORATORIES FILM PROCESSING MACHINE
TURNKEY RELEASE LABORATORY HIGH SPEED PRINTER
THEATRE PROFESSIONAL PRODUCTION SYSTEMS
In order to explain
Point 11 : Telecine HD
We will provide a PERENITY 2K – HD. This scanner allow you to scan in reel 2K
(2048x1556) as well in HD (1920x1080). The PERENITY is upgradable to 4K.
Point 19 :
1) Film processing machine
6/9
Tunus Cad. No. 76/5 Kavaklıdere 06680 Ankara / Turkiye Tel: +90 312 468 85 00 Fax: +90 312 467 94 95
ERKEM
İnşaat Sanayi ve Ticaret A.Ş
We can't provide in only one machine the processing of COLOR NEGATIVE, COLOR
POSITIVE and B&W. It will be 3 equipment, 1 for COLOR NEGATIVE, 1 for COLOR
POSITIVE and 1 for B&W NEGATIVE and POSITIVE. So MINIPLEX has been replaced by
EASYPLEX ECN2 (COLOR NEGATIVE), EASYPLEX B&W and EASYPLEX ECP2D
(COLOR POSITIVE).
2) Wet & Dry Contact Printer
The MINIPLEX is now A TCI1635WD.
3) Optical Printer
The MOVIECLONE is now named TAI
4) Cleaning Machine
We provide an ULTRACLEAN with HFE
5) Color Analyser
CHROMA III
MECHANICAL WORKS DESIGN BRIEF:
GENERAL
7/9
Tunus Cad. No. 76/5 Kavaklıdere 06680 Ankara / Turkiye Tel: +90 312 468 85 00 Fax: +90 312 467 94 95
ERKEM
İnşaat Sanayi ve Ticaret A.Ş
Mechanical works will compose of plumbing, fire extinguishing, compressed air and HVAC
installations.
All material and equipment will be supplied and installed in a state-of-art condition, following
the Turkish Standart norms and common technical ethics.
DOMESTIC HOT& COLD WATER SYSTEM
The ground floor of Administrative building, to be held under the present project,
additional basement floor mechanical room will be based, and here also there will be
reinforced concrete water tank serve for the firefighting and domestic water.
Domestic water system is built by galvanized welded steel pipes. Sanitary plumbing is built
by PVC pipes.
City water system
filling the
water concrete water
tank ensuring the
network is
adequate water pressure mains, if the pressure is not enough booster pump is placed in the
building to provide need for water.
The cold-water will be serving by the booster tank that will be placed at the mechanical
room.
The water will be used at the administrative building, the exhibition areas of both the needs
of WC. The pipes that will serve o that area will be PPRC pipes not welded type. The
system will also serve water to water pool and outdoor parking in front of the building in front
of the green area.
Hot water needs at the WC will be serve by the Electrical water heater that is put into
the toilet.
Water pool water will be filter by the 1 each filter at the mechanical room. The other cleaning
process will be made people.
Outdoor parking in front
provided irrigation hose.
of
the green area; taps were
placed; the
space
will
be
WASTE WATER SYSTEM
Both administrative building, the exhibition areas dirty toilet water will be discharge by 3
mm wall thickness PVC pipe and fittings materials.
In addition, waste water in the mechanical room will be discharge with pump that is installing
to one pit.
RAIN WATER SYSTEM
Roofs from rain water will be discharge outside of the buildings freely by using plasticbased filters and 3 mm wall thickness PVC pipe fittings materials.
8/9
Tunus Cad. No. 76/5 Kavaklıdere 06680 Ankara / Turkiye Tel: +90 312 468 85 00 Fax: +90 312 467 94 95
ERKEM
İnşaat Sanayi ve Ticaret A.Ş
FIRE FIGHTING SYSTEM
Fire Fighting system includes only inside of building and consist of 1 piece electrical booster
pump and enough pieces fire hose cabinets.
Maximum distance between the two fire hose cabinet is 40 mt. Either administrative building
or expo center area, 50mm diameter and 20 mt length fire hose will be used in fire hose
cabinets.
Electrical booster pump will be put in the mechanical housing and this pump will pump the
cold water; using collector consist of galvanized welded steel pipes and fittings materials
piping system, flooding to fire hose cabinets, system will be in pressure continuosly.
HVAC SYSTEM
VRV system (Qtc: 200 kW) will be used for administrative building. For the expo center
area, Roof Top Units (Qtc: 4.080 kW) will be used for the cooling. Climatized air in the roof
top unit will be circulated with galvanized air channels.
Either VRV or Roof Top Units will use electric energy for heating and cooling.
For the Meeting Rooms climatization will be supplied by Split A/C Units.
Also, for the WC’s in either administrative building or expo center area exhaust fans will be
used for exhusting and absorbing air, and to supply climatized air in negative presure.
9/9