LIGO Change Request
Date: January 5, 2006
Change Request No.: CR-060001
WBS Element and Title: Project Controls Support to Prepare for NSF Baseline Review
Originator: C. Wilkinson
Telephone: 509-783-3052
CCB Sponsor: S. Whitcomb
Technical Change Description: Added resources to support NSF Baseline Review
Extend existing contract with ARES corporation to supply temporary, additional project controls support. The
temporary personnel will help prepare baseline cost and schedule as well as project management documents for
the NSF review of the Advanced LIGO baseline planned for May 2006. The requested amount is up to $90,000.
There is no increase in budget if unused funds in the Advanced LIGO Project management account are used to
cover this request.
Budget Impact: $0
Budget Calculation: 5 Full Time Equivalent months (840 hrs) @ ~$107/hr = $89,880
The time will be split between a risk management expert and generic project controls support personnel.
The Advanced LIGO project management budget contains an allocation for a deputy systems engineering hire.
That hire will not occur before the end of January. The unused allocation for October 2007 through January 2006
is $90,000. This request asks approval to apply the unused funds toward another application in the same account.
Schedule Impact: Extra support is needed to prepare in time for a NSF review planned for May 2006.
Concurrence Signatures:
Technical and Engineering Support:
Date:
Detector Support:
Date:
Advanced LIGO Development:
Date:
Data and General Computing:
Date:
Hanford Observatory:
Date:
Livingston Observatory:
Date:
Project Controls Manager:
Date:
Date:
Approval/Disposition (CCB Chairman):
CIT/MIT
LIGO Laboratory
Form CR-01 (4/03)
LIGO Change Request
CIT/MIT
LIGO Laboratory
Form CR-01 (4/03)