Risk Management for Project
Sponsors
June 2011
1
What we’ll cover
•
•
•
•
Project Management Overview
Project Accountabilities
What is Risk Management
The Process of Risk
Management
• Common Risks
2
What is Project Management?
• Project Definition: A project is a
temporary endeavor undertaken to
create a unique product of service
• Project Management: The disciple of
planning, organizing and managing
resources to achieve the successful
completion of specific project goals and
objectives
3
Key Roles & Responsibilities
• Project Manager:
–
–
–
–
Manages project resources
Predicts cost and schedule
Reports to the sponsor
Says “no” to un-approved work
• Project Sponsor:
– The executive who owns the investment. “I want
this, & I’m willing to pay for it”
– Approves scope, priority, schedule & budget
– Manages user expectations
– Removes barriers
4
Why Project Management?
Project success rates for organizations
without effective project management
practices:
• 31% of projects are cancelled before
completion
• Only 12% are completed on schedule and
within budget
• Average cost overrun is 189%
• Average time overrun is 222%
(Source the Standish Group)
5
Have You Ever Heard This?
• How could we have spent $500k and have
nothing but a couple of deliverables from a
vendor?
• How did the project “all of the sudden”
become over budget when my weekly reports
said we were fine?
• The users designed this system and were in
on every decision. Now they hate the system
and are blaming IT
6
The Triple Constraint
“Good, fast, cheap. Pick any two!” - Project manager’s old adage
Risk
Schedule
Scope
Quality
Resources
Budget
7
Remember - Always
Scope, schedule &
budget
are linked.
If one changes,
one or both of the
others
must change
8
Sponsor Sets Priority
Pick one
• Project must be delivered
on time or
• Project must be within
budget or
• Scope is fixed
9
What is Risk Management?
The process involved with
identifying, analyzing &
responding to risk
• Maximize positive events &
minimize consequences of
adverse events
• Identify problems early focus on prevention
10
The Process of Risk Management
Sponsors must manage their investments:
• Create a safe environment - problems will happen
• Solicit feedback from users & other external sources
• Meet routinely with project manager to review
performance
 Review summary of quantitative performance
measures
 Expect results of routine risk assessments
 Follow-up on mitigating actions
 Require consistent and routine performance reports
• On high risk projects request independent reviews
11
How Do I Get Started?
• Have a knowledgeable person set
up & lead the process
• Train your staff
• Expect consistent & reliable
information
• Be consistent
• Review results with project
manager
12
Fleet Management System
(FMS) Project Dashboard
5/9/2011
Budget
Budget
$948,000
Budget for Fleet Management System
(FMS) (Includes Fuel)
Expended
$144,225
Actual expenses
Encumbered
$803,775
Encumbered amount
Major Accomplishments
•
•
•
•
Vendor has responded to the Fleet Management System Requirements
Configuration and Development Master lists have been finalized
AgileAssets Statement of Work has been submitted for ITD approval.
The Configuration effort for FMS has begun.
Upcoming Events
• Demonstration of the initial Fleet Management System will be
provided by AgileAssets to the FMS Core team.
• Development efforts for the FMS to Advantage interface is schedule to
begin early in May.
• The first milestone for a set of configuration items is scheduled for
completion in early June
Major Risks
• Matt S. has been assigned to perform the Business Administrator
function for FMS. Matt’s availability to perform this role may be
impacted by his other duties as the TAMS administrator.
• AgileAssets does not have a Project Manager assigned. They are
approximately 4 – 6 weeks out for having a replacement Project
Manager. IN the short term Kevin Green will perform this function.
Due
2/4/2011
4/25/2011
Milestone
PMO Planning documents
completed
Requirements and design
documents complete.
Risk
Remarks/Mitigations
The approval of the SOW has been
delayed. Configuration and
development work by AglieAssets
continues so the schedule impact is
relatively minor.
The system and functional requirements
Have been submitted to AgileAssets. In
addition, the AgileAssets PRD’s are
completed and the CML/DML setup.
5/13/2011
Fuel System replacement direction
decided
The decision has been delayed waiting
on a vendor demonstration of their
capabilities.
7/12/2011
Interface development, EMS
Conversion and system
configuration is 50 % complete
50% of the configuration and interface
development has been approved by the
Core team.
9/15/2011
Interface development, EMS
Conversion and system
configuration is 100 % complete.
All of the configuration and interface
development has been approved by the
Core team.
10/21/2011
Report development completed
Fleet management operational reports
have been approved by the core team
1/17/2012
Testing is completed
All testing from System through User
Acceptance has been completed.
3/12/2012
System implementation
The system is in the production
environment, the users have been
trained and are using the system to
manage the daily activities related to the
Fleet.
4/5/2012
Project close
All project documentation is completed.
13
Sample Metrics
Central Issuance Weekly QA Status Report – 04/15/2011
Role of Quality Assurance (In a Nutshell)




Act as quality liaison and champion for business between ITD and L1.
Define and execute ITD and L1 Integration test scenarios based on design specifications.
Assist ITD personnel in creation of supporting documentation and process.
Prepare for formalized User Acceptance Test pass.
Integration Metrics
Defect Discovery Rate
As hoped, L1’s defect discovery rate
appears to have peaked on 4/6 and is
now trending downward as build quality
continues to improve. The ITD defect
discovery rate continues to remain
relatively constant as reactionary
integration bugs are discovered and fixed
by the team.
ITD Integration Phase Execution Status
Testing “Feature” Area
Priority One Scenarios
Capture Workstation
IDSuite
Interim Documents
Permanent Prints
Special IDs
Undercover Issuances
Image Server Mig.
LE Data Feed
Reporting Console
ITD Web Apps
L1 Web Apps
Test Status
Test Complete
Test Complete
2nd Pass Complete
Test Complete
2nd Pass Complete
2nd Pass Complete
1st Pass Complete
Test Complete
nd
2
Pass Complete
1st Pass Complete
Test Complete
Test Complete
Historic Integration Phase Bugs by Priority




Priority
Priority
Priority
Priority
1:
2:
3:
4:
Must fix immediately
Must fix before entering UAT phase
Fix if time allows
Out of project scope (new functionality)
14
The Process of Risk Management
15
Common Risks
16
Schedule & Budget Slippage
Symptoms:
• Schedule slips but you are assured it will
made up
• Lack of quantitative basis for schedule –
“Feeling good about how we’re doing”
• Schedule and budget never change
• Scope increases but there is no change to
budget or schedule
17
Schedule & Budget Slippage
Consequences:
• Projects delivered late and over budget
• Lack of user satisfaction
• Inadequate funding
• Credibility
• Resource conflicts
18
Schedule & Budget Slippage
Mitigating actions:
• Approve scope, schedule & budget estimates
BEFORE you start
• Insist on quantitative basis for schedule &
budget projections
• Focus on the future, not the past
• Predict schedule & cost routinely
• Always have a contingency fund
19
No Definition of Done
Symptoms:
• No time to plan- “we have to get started”
• Resistance – “We know what we want!”
• Repeated surfacing of unexpected additional work
• No understanding of expected benefits
• Disagreement among stakeholders about what
they are getting
• Insist on exit criteria for major milestones - If there
are no Exit Criteria, how will you know you’re
done?
20
No Definition of Done
Consequences:
• Needed work is not visible or adequately
planned
• User dissatisfaction- “They didn’t give me
anything I asked for”
• The project just keeps going
and going and going
21
No Definition of Done
Mitigating actions:
• “Done” must be documented and approved
before the schedule and budget are set
• Should include:
– Product Description
– Expected benefits
– Proof of success
• Define what the project is NOT going to do
22
Ineffective Sponsor & Project Manager
Symptoms:
• Priorities are vague and the project lacks focus
• Resource needs are unclear or don’t they
participate
• Project schedule & budget either do
not exist or are not based on quantitative
information
• Scope is undefined, unclear & unpredictable
• Critical decisions pend for a long time
23
Ineffective Sponsor & Project Manager
Consequences:
• Schedule slippage
• Unnecessary work performed
• Cost overruns
• Users have not updated their business
practices & are not prepared for the new
product
• Poor staff morale
• Reputations are harmed
24
Ineffective Sponsor & Project Manager
Mitigating actions:
• Ensure sponsor has an interest in the
project’s success - fiscal & program
responsibility
• Skilled project manager – not operations
manager
• Require & review metrics to measure
quality, budget & schedule
• Don’t just hope things will get better- take
action
25
Incomplete Requirements
Symptoms:
• There aren’t any 
• Non-measurable, vague – can’t
be tested
• Are not aligned with project
objectives or definition of done
• Vendor cost estimates are not
consistent
26
Incomplete Requirements
Consequences
• Low quality product that does not meet the
user’s needs
• Numerous change order requests resulting in
schedule slippage & budget overages
• Constant conflict between state & vendor
• Blame game
27
Incomplete Requirements
Mitigating Actions
• Take time to Plan, Define Done, Set one priority scope, schedule or budget
• Utilize skilled staff/contractor- This is HARD!
• Process maps, use cases etc.
• Utilize templates – Requirements traceability
matrix
• Ensure final product satisfies the requirements
28
Shannon Barnes
PMO Manager
Idaho Transportation
Department