Survey
* Your assessment is very important for improving the workof artificial intelligence, which forms the content of this project
* Your assessment is very important for improving the workof artificial intelligence, which forms the content of this project
There is pleasure in the pain of refurbishing heritage buildings Vijay Badhwar B. Tech. M.I.E. Aust. C.P. Eng. Mikhail Kogan B.Sc. Eng. (Civil), M.Eng. (Structure) SUMMARY: The key to successfully refurbishing heritage-listed buildings is in the planning. Faced with an extreme challenge to provide 21st century functionality in the nearly 150-year-old Chief Secretary’s Building, spaces within the existing fabric were identified. These spaces accommodated new services and strengthening elements - for example - a void above the corridor ceilings not only provided an avenue for fresh air supply but also accommodated structural tie members to stabilize walls against earthquake loads. Even when structural intervention was necessary to strengthen an ailing arch, it was applied with sensitivity making the intervening elements visible and also reversible. The choice of a piped VRV refrigeration system for air-conditioning the building and maintained the background of highly ornate ceilings intact. The Engineering team exhibited best practice in the planning, selection and installation of engineering systems and components. This ensured that all work had minimum effect on the fabric of the heritage building while still providing an appropriate internal environment for the functions of Courts, the Industrial Relations Commission and the Governor of NSW. The project sets a benchmark in Australian engineering for the adaptive reuse of a significant 19th century heritage building. Figure 1. Chief Secretary’s Building elevation Figure 2. Typical plan 1. INTRODUCTION: The Chief Secretary’s Building (CSB), a significant heritage sandstone public building designed by Colonial Architect James Barnet, was built in 1880. The building was initially constructed as “a new and worthy building for the office of Chief Secretary of the Colony as well as providing offices for the Public Works Department”. It has landmark national significance and is a major state asset. The key requirements of the redevelopment project completed in 2005 were to provide modern day services and comply with current standards while preserving the building’s landmark heritage features. The Engineering Services group within the NSW Government Architect’s Office applied an innovative and at times unique approach to meet this challenge. for the Chief Secretary and also accommodated the Public Works Department. As the Chief Secretary’s role was of considerable political and administrative influence, the building was marked as being of state and national significance. It was customary then that important office bearers occupied one floor above the entrance level. The sloping site allowed Barnet multiple main entrances – at level two (Macquarie Street) for the Chief Secretary, a public entrance from Bridge Street and the lowest from Phillip Street for the Public Works. The executive offices on level three were similarly arranged along the street frontage while their subordinate staff worked across the corridor towards the rear courtyard. The building’s facades, finishes, furnishings and artworks are of exceptional architectural significance which lend due importance the building deserved in the 19th century. While the CSB construction experienced building 2. HISTORICAL SIGNIFICANCE The CSB, as implied by its name, was an office Page 1 supports the timber-framed walls and pitched roof from street sides. The street facade is a mansard type roof. There is a sandstone spandrel parapet on top of the facade wall. The roof towards the north is pitched and clad with copper sheeting, while on the south, the roof is flat with waterproofing membrane. The timber roof structure comprises of king post trusses, underpurlins and rafters. The central part of the Barnet Wing has six storeys and a two-level dome above with steel frames with bow trusses supporting timber framing and boards. The dome and attic on level five were later additions. There were external toilets towards the rear 3. BUILDING STRUCTURE: The Chief Secretary’s Building is sited in the courtyard which were connected to the main north-eastern part of Sydney CBD along Bridge building with links that were subsequently Street between Macquarie and Phillip Streets. The demolished. The corridors consist of double brick arches with site slopes down in east-west direction. The building consists of two main blocks/wings: a space in between. The upper arch supporting the • Barnet Wing (which includes original Barnet floor is very flat. The original building was gas lighted and building and Vernon Mansard addition) and • Vernon Wing (which includes original Vernon naturally ventilated. extensions and levels above Phillip’s Lane). The Barnet Wing is connected to the Vernon 4. REDEVELOPMENT STRATEGIES Wing at each level above Phillip Lane. Over time Following the adage in relation to works on there have been some alteration and refurbishment heritage structures ‘to do only as much as needed and to do as little as possible’, dictated the to the building (lift, engineering services etc). The building is a five-storey structure, ‘U’ shape strategies for adaptive reuse. There was an configuration in plan, with load bearing walls in underutilized building which could be sandstone and brickwork. The floors are mostly redeveloped for government accommodation timber framed with some use of steel beams. within the heritage constraints. It was determined Hardwood timber joists, 275mm deep x 75mm that Industrial Relations Commission and courts wide at 450mm centres, span either from wall to would be appropriate users of the building. wall or onto iron beams. In the central area in the Economic appraisals were undertaken to provide north, the joists run east to west onto iron beams. only basic facilities such as air-conditioning, Where there are balconies underneath, the joists electricity, communication, security and fire span north–south sitting on the walls. In the east safety with Early Warning Interaction System and west corners of the building the joists span (EWIS) and smoke detection. Strategies were developed early to earmark areas east-west. The floor joists support 65mm thickness of for vertical travel of services while horizontal concrete pugging on boards sitting on timber spaces had been identified in the corridor ceiling. battens secured to the sides of the joists. The For structural strengthening works it was appropriate to keep them floor construction is a 30mm thick tongue and considered inconspicuous – inside ceiling spaces – without groove boarding. The timber lath and plaster ceiling is attached to being obtrusive. In a different application of separate ceiling joists 145mm deep x 48mm wide visual rectification (at Phillip Lane arch), it was at 450mm centres and supported from the floor decided to make the rectification works structure in parts. conspicuous and reversible. The iron beams are I sections strengthened with 12mm thick plates riveted to the flanges. 5. ENGINEERING CHALLENGE The Level five floor was built during The significant engineering challenge was to reconstruction of offices and the dome. The floor comply with present day standards, fit out the consists of softwood timber joists and steel building with leading technologies and an internal beams. There is no pugging and timber lath and environment suitable for its functions without plaster ceiling attached directly to the underside impacting on heritage features and finishes. of the floor joists. The floor structure partly delays and cost overruns, the Public Works Department pressed for more space. Barnet’s successor as the Government Architect, Walter Liberty Vernon, undertook design for more space and thus came extensions to the CSB along Phillip Street. Vernon’s embellishments to the original building in the form of mansard roof and a grandiose dome added to the building’s importance. The CSB underwent major alterations and additions after the Public Works Department moved out from the premises in 1968. Spaces were created for divorce courts and new lifts. Page 2 • Figure 3. Grand spaces of exceptional heritage significance The decorative timber finishes, ornate embossing on walls and numerous features throughout provided significant challenges and meant that every detail had to be individually investigated and thoroughly planned to minimise impact on heritage fabric. The upgrade required sealing to prevent noise and dust encroachment, the inclusion of full air-conditioning and significant upgrades in electrical, communications, security, hydraulics and fire-engineering to modern standards. 6. DESIGN Surveys by specialists in the areas of structural, mechanical, electrical and hydraulics engineering identified limitations with the existing structure and upgrade requirements. The main issues were identified as follows: 6.1 Structural Engineering Although massive in appearance, the CSB footprint in the form of ‘U’ exposes the structure to eccentric forces resulting from lateral loads such as from earthquake forces. The vulnerability of walls is further exacerbated as the floors do not provide the required restraint at intermediate levels, virtually making them free-standing for their entire height. Similar concerns subject to earthquake loads apply to elements such as parapets, balustrades, pediments, architectural ornamentations etc. The complicated plan geometry and an irregular vertical configuration of the building as a whole significantly affect its performance during an earthquake. Computer modeling of CSB was not undertaken as from earlier experiences it was known not to give satisfactory results for masonry structures. Significant Weaknesses in Main Structure • Load-bearing un-reinforced masonry walls extending to the full height of the building – approximately 27m (five storeys) and six storeys in central part. According to AS3826 this type of building should be limited to three storeys with all floors connected to walls. The gross floor area at each level exceeds 300m2 recommended by AS3826. • Roof timber frames do not have bracing at roof and ceiling planes and so can not act as diaphragms. • Roof timber frames do not have any connection to the masonry walls. • Floor timbers do not connect to the masonry wall and do not have enough stiffness to act as horizontal diaphragms. • Masonry parapet walls and chimneys have an h/t ratio (height to thickness) greater than 3:1. • Masonry pediments at roof level and over entrance are prone to instability. • Settlement of an arch over Phillip Lane due to its inherent flat profile and large point loads from above. • Connection to Vernon Wing above Phillip Lane has resulted in twisting and cracking in both wings and is detrimental to the structure. Australian Standards The underlying design principle of AS1170.4, “Earthquake Loads”, is based on an estimated 90% probability of the ground motions not being exceeded in a 50 year period. “Buildings that are designed to contain a large number of people” are classed as Type II and “buildings that are essential to post-earthquake recovery” are classed as Type III in accordance with Australian Standard AS1170.4 Earthquake Loads. The Chief Secretary’s Building is classed as Type III for its Heritage Significance and capacity to contain a large number of people. The main structure of building does not comply with requirements for either Type II or III structures. Another Australian Standard AS3826 applies to ‘Strengthening existing buildings for earthquake’. The CSB building structure also does not comply with its ‘Deemed-to-satisfy requirement’ specified in clause 2.3. It was considered that without major interference to the fabric of the structure, compliance to AS1170.4 as a new building or even application of AS3826 with a reduction of earthquake loads to 33% could not be achieved. Accepting a lower standard of earthquake protection to minimise disturbance to the exceptional heritage significant items in the building and strengthening of only the critical items was considered. These critical items were: • Tie whole building at roof level by connecting roof structure to masonry walls and providing bracing/diaphragm. • Connect large wall elements to floor beams to avoid collapse. • Carry out strengthening of the chimneys, parapets, pediments and slender wall panels. • Take any opportunity in future alteration/repair work (such as new lift, stairs, services etc.) to improve the capability Page 3 of building structure to withstand the threshold load as a minimum. Figure 4. Phillip Lane arch strengthening; inset: finite element analysis • Carry out rectification of the arch over Phillip Lane. Following finite element analysis of the arch, individual stones were identified for the level of stress each one carried. Several options were prepared which included: a) relieving the arch of loads from above, b) prestressing the arch, c) repair by carbon fibres to enhance arch’s tensile capacity, d) providing an external support to the arch by steel rods. Option d) was adopted in consultation with the Heritage Architect and the Heritage Council as it contrasted as rectification and was also reversible. The earthquake strengthening works were limited to avoid a major collapse as it is not mandatory to apply the current Australian Standard on existing structures as AS3826 is not listed in the Building Code of Australia. Nevertheless, due care was applied to design the earthquake strengthening for the building, applying it more rigorously to elements that are prone to catastrophic collapse (such as chimneys, balustrades etc) and tieing elements elsewhere. Majority of earthquake strengthening works were inconspicuous – turning floors into diaphragms by providing plywood sheets; connecting the east and west parts of the structure through steel connections in the corridor ceiling arch and introducing cross bracing. The balustrades, however, needed more work as cracks at several locations were noticed, being in an exposed part of a building and liable to become wet and subject to extremes of temperature. Besides injecting epoxy to repair the cracks, the balustrades were tied to steel struts to safeguard against collapse. The struts, in turn, were connected to the wall framing of the mansard structure. The struts were not easily noticeable as these were placed behind the balustrades. The procedure was also in line with the conservation strategy as the whole process is reversible. 6.2 Services The original building services were open fireplace heating, gas lighting, natural ventilation and basic water and drainage systems. The major areas of the building had timber flooring and ornate plaster ceilings fixed to a common set of floor joists providing minimum or no ceiling void spaces. Concrete corridor floors were not reinforced but relied on brick arch support, making any addition of modern services extremely difficult. An extensive upgrade was required to ensure compliance with current standards and meet modern functional needs. New services were installed throughout the building including, electrical, communications, data, fire safety, security, mechanical, hydraulics, lifts, an elevated link to 50 Phillip Street and a glazed courtyard canopy. During investigation of existing services, records were found that showed a single piped system, approximately 125 years old, that conveyed both sewer and stormwater from the building to discharge into a Sydney Water Sewer main in Phillip Street. When the existing system was examined via a CCTV survey, the pipe was found to be unsuitable for re-use for either sewer or stormwater. The only solution was to install new dedicated sewer and stormwater systems. The original single pipe system reticulated from the building via the adjoining laneway connecting Phillip and Macquarie Streets. Heritage paving stones were known to be located below the road surface of the laneway and no disturbance of the laneway was allowed. Additionally, the courtyard within the CSB was also of heritage importance and only minimal disturbance was permitted. The challenge was to separate the existing single combined system and to find a suitable reticulation route to Phillip Street that would not impact the critical heritage restraints and the options were severely limited. The only location available to create an external services corridor was below the existing footpath that ran between the building’s Southern external wall and the courtyard retaining wall. Because of the limited space allowed owing to structural footing restraints, extensive services coordination was required as electrical and hydraulic services had to share the common trench. Geotechnical surveys involved bore holes being taken from areas below the buildings floor structure and the courtyard to determine the suitability of boring at certain depths without structurally impacting upon the buildings stability. Extensive co-ordination with other service providers such as Telstra were carried out to ensure the proposed bores would clear all the services below the street and footpath, while ensuring connections could be achieved at the required levels at either end of the thrust bores. Finally two thrust bore holes extending below Phillip St and the eastern side of the building to Page 4 the new service corridor near the courtyard were decided on. The bores provided a 330mm and 440 mm diameter conduit to install the new stormwater, water and sewer to service the site. Localised boring was also carried out below the buildings floor structure where service pipes were required to pass below heritage slate and marble tiled floors. Existing services pipes in a variety of materials and configurations including plastic (PVC) were fixed to the external walls and within the building detracting from the buildings appearance. Hot water was supplied where required via discretely located compact slimline instantaneous electric heaters, as natural gas was not an option for an energy source owing to the impact of gas flues penetrating the buildings external walls. • Environmentally sustainable design principles were adopted throughout the project and a range of low-energy solutions of lighting sources and air-conditioning systems were implemented including a state of the art air-cooled reverse cycle heat recovery Variable Refrigerant Flow (VRF) system employing environmental friendly R410A refrigerant. This system was different from the conventional four-pipe system which are on average 250mm diameter. Instead the VRF system utilised 25 mm diameter pipes with 20 mm insulation. This system is also energy efficient as it cools and heats simultaneously, extracting heat from one part to supply where it is needed. Figure 5. Corridor ceiling arch – used as a fresh air duct and to accommodate structural members for earthquake strengthening • Use of confined ceiling void space above corridors as a major services thoroughfare. • Development of a fire-engineered solution within the timber flooring to meet BCA fire requirements, maintaining fire isolation between floors and smoke zoning between rooms. The existing east and west stairs had to converted to fire stairs and pressurised. The supply of fresh air on every floor was achieved through the corridor arch duct that was connected on each end to the vertical risers. In case of a fire, the corridor arch duct would go into reverse mode to suck air out from the fire-affected floor. • Searching investigation of the building’s construction was undertaken to minimise impact on heritage finishes to find: ¾ cable access pathways for wiring electrical and security services i.e. reuse of both disused gas flues built into walls from wall mounted gas lights and pipes and old conduits associated with earlier building refurbishments; ¾ access routes in the limited void spaces to install new hydraulic services, particularly gravity pipes; ¾ positioning the plant room on the roof area where it would be inconspicuous behind a 1.6 metres high parapet • Use of large diameter core boring under significant on-ground floor finishes to provide access for a wide range of engineering services. 7. CONCLUSIONS The Chief Secretary’s Building is a major NSW Government asset both in its heritage status and as accommodation for the provision of public The adaptive reuse of the Chief services. Secretary’s Building has ensured that it remains a landmark public building of national heritage significance. The building is now home to the Industrial Relations Commission’s Courts and the NSW Governor’s Office. Both are appropriate and distinguished uses for a building of this significance. In recognition of a work of conservation excellence the NSW Government Architect’s Office has recently been awarded the National Trust’s foremost Heritage Award, Conservation Built Heritage for a project over $1 million. 8. ACKNOWLEDGMENTS Design team at NSW Government Architect’s Office: Terry King, Project Architect; Christine Scantlebury, Hydraulic Engineer; Ian Gordon, Electrical Engineer, San Mai, Mechanical Engineer. 9. REFERENCES Chief Secretary’s Building Conservation Management Plan 2002 Heritage Design Services Department of Public Works & Services Jackson Teece Chestterman Willis Consultants Pty Ltd, Conservation Architect Wendy Thorp, Historian and Archaeologist October 1994 Chief Secretary’s Building, Conservation Plan for the Minister of Planning Page 5