MSSL Quality
INTRODUCTION
Tony Dibbens PA Manager
April 2001
MSSL Quality
PLAN FOR THE VISIT
Introduction to MSSL (APD)
Project PA Structure for UVOT (MC)
Quality Management Overview
5.1 NASA (MK)
5.2 PSU (MC)
5.3 MSSL (APD)
MSSL UVOT PA Documents (APD)
PA Plan
Cleanliness Control Plan
Verification Plan
Configuration Control (CIDL)
Declared Components List
Declared Materials List
Declared Processes List
Discussion on Topics so far (ALL)
Tour of Facilities (ALL)
Conclusions and Recommendations (ALL)
Coffee, tea and lunch breaks to be taken as appropriate;
lunch is nominally 12.30 to 13.30
April 2001
MSSL Quality
April 2001
MULLARD SPACE SCIENCE LABORATORY
MSSL
Background
History of Site
UCL
MSSL Quality
April 2001
MSSL ORIGINS
Space science in Britain was initiated and the foundations for its
development were laid very largely by one man, the late Sir Harrie
Massey who was Professor of Physics and Head of the Department of
Physics at University College London from 1950 to 1975.
Sir Harrie Massie was asked by an official of the Ministry of Supply in
May 1953 whether he would be interested in using rockets available
from the Ministry for scientific research.
R.L.F. Boyd, a lecturer in the department who was carrying out
experimental research work on rates of electronic and ionic collision
processes in gases, using newly-developed probe methods, was
particularly enthusiastic about the opportunity, and thereafter he led the
UCL research effort.
It was from these beginnings that there grew up at University College
London a space research group which, 13 years later, became
the Mullard Space Science Laboratory.
MSSL Quality
April 2001
HOLMBURY HOUSE
Early in 1965 the electronics firm Mullard Ltd offered to donate to UCL
funds for the purchase of premises which could be converted into a
space science laboratory.
After an intensive search, at a time when suitable premises were hard to
find, Prof. Boyd found Holmbury House. Its previous owners included
the Hon. A.E Guinness who lived here in the 1930s and 1940s.
UCL took possession in 1965 and, as the alterations necessary for the
conversion to a laboratory were completed during 1966, the building
came progressively into use.
The Mullard Space Science Laboratory was opened formally on 3rd May
1967 by Dr F. E. Jones, then Managing Director of Mullard Ltd.
MSSL Quality
April 2001
MSSL
The Department undertakes front-line research in:
Climate Physics
High Energy Astrophysics
Solar Physics
Space Plasma Physics
Photon and Particle Detection Systems
MSSL Quality
April 2001
UCL MISSION STATEMENT
THE VISION: FAME THROUGH EXCELLENCE
Specifically UCL intends:

To be and to be acknowledged as, one of the greatest
metropolitan Universities in the world, serving local and
international needs.
 To be and to be recognised as, a world leader in teaching,
scholarship and research across the sciences and the arts.
 To be in the forefront in tackling mankind's environmental,
communication and health care problems.

To continue its founders' vision by providing educational
opportunities of the highest quality to all, regardless of
background.
MSSL Quality
April 2001
MSSL’s INVOLVEMENT IN SWIFT UVOT
Funded by PPARC on basis of repeat of XMM-OM
Cost-capped mission
Memo of Understanding between PPARC and NASA
Under overall control of Penn State
Very tight schedule
MSSL Quality
April 2001
RECENT MSSL PROJECTS
ESA Missions
NASA Missions
Other Agencies
MSSL Quality
April 2001
ESA MISSIONS
GIOTTO
SOHO
CLUSTER I and II
XMM - Optical Monitor
XMM - RGS
SPIRE (FIRST)
BEAGLE 2
MSSL Quality
April 2001
NASA MISSIONS
CASSINI
GOES SXI
JPEX
SWIFT UVOT
Solar B FPP
MSSL Quality
April 2001
OTHER AGENCIES
Solar A (Yoko)
MARS 96
Solar B EIS
RESIK
Japan
Russia
Japan
Russia
MSSL Quality
April 2001
MSSL QUALITY - 1
MSSL General
Project Specific
MSSL Quality
April 2001
MSSL QUALITY - 2
Two levels of quality management at MSSL:-
MSSL PA Manager:
Responsible for MSSL PA system
Project PA Manager:
Responsible for a specific project
MSSL Quality
April 2001
MSSL QUALITY - 3
Quality Manual
Processes
Procedures
Configuration Control
ESD
Handling of CCDs
Documents On-line
Cleanroom
MSSL Quality
April 2001
MSSL CLEANROOM - 1
The Facility (Audited by LMSS & NASA)
Cleanliness Levels
Monitoring
Gowning
Training
Maintenance
MSSL Quality
April 2001
MSSL CLEANROOM - 2
Cleanroom Documents:
MSSL Cleanroom
Cleanroom Gowning Procedures
Cleanroom Operating Procedures
Particulate Contamination Monitoring
Molecular Contamination Monitoring
MSSL Quality
April 2001
MSSL DOCUMENTS
SEE HANDOUT
MSSL Quality
April 2001
PROJECT SPECIFIC DOCUMENTS
PA Plan
Cleanliness Control Plan
Verification Plan
Configuration Control (CIDL)
Declared Components List
Declared Materials List
Declared Processes List
MSSL Quality
April 2001
SWIFT-UVOT PA PLAN
Document Number – MSSL/SWT-UVOT/PA001
1.
2.
3.
4.
5.
6.
7.
INTRODUCTION
DOCUMENTS
GENERAL REQUIREMENTS
QUALITY ASSURANCE
RELIABILITY ASSURANCE
SAFETY ASSURANCE
COMPONENT QUALITY, SELECTION & PROCUREMENT
ASSURANCE
8. MATERIALS AND PROCESSES SELECTION AND CONTROL
9. CONFIGURATION MANAGEMENT AND CONTROL
10. ACCEPTANCE REVIEW, ACCEPTANCE DATA PACKAGE
MSSL Quality
April 2001
SWIFT-UVOT CLEANLINESS CONTROL PLAN
Document Number MSSL/SWT-UVOT/PA002
1.
2.
3.
4.
5.
6.
INTRODUCTION
APPLICABLE DOCUMENTS
CONTAMINATION SOURCES – GENERAL
CLEANLINESS REQUIREMENTS SPECIFICATION
CLEANLINESS CONTROLS
OPERATION
MSSL Quality
April 2001
CONFIGURATION MANAGEMENT
A discipline applying technical and administrative
direction and surveillance to do the following:
1. Identify and document the functional and physical
characteristics of configurable items(CI)
2. Control changes to the CI and their documentation
3. Record and report change processing and
implementation status
4. Audit CI to verify conformance to their documentation
and other contract requirements
MSSL Quality
April 2001
SWIFT-UVOT CONFIGURATION CONTROL
Change Control Data Bases (ECR/NCR)
Configuration Item Data List (CIDL)
MSSL Quality
DATA PACKAGES
Preliminary Design Review
Critical Design Review
Test Readiness Reviews
Delivery Review Board
Acceptance Data Package
Input to Operation Manuals
April 2001
MSSL Quality
April 2001
SOFTWARE QUALITY ASSURANCE - 1
Requirements
– A software requirements definition for the UVOT ICU has
been produced (MSSL/SWT-UVOT/SP/001.01)
Architecture
– The software architecture/design will be guided by ESA
software engineering standards (ESA-PSS-05-0 issue 2)
and will be available after delivery
Design reviews
– Formal QA shall only be performed on software that
interfaces to the spacecraft
MSSL Quality
April 2001
SOFTWARE QUALITY ASSURANCE - 2
Verification
– The UVOT ICU/DPU software verification matrix shall
be written by the UVOT software lead (with input from
MSSL)
Configuration Control
– Configuration control has been implemented using
CVS. It will be the responsibility of MSSL up until
delivery. It shall then be transferred to PSU.