Download Article Name - bryongaskin.net

Survey
yes no Was this document useful for you?
   Thank you for your participation!

* Your assessment is very important for improving the workof artificial intelligence, which forms the content of this project

Document related concepts

Earned value management wikipedia , lookup

Construction management wikipedia , lookup

PRINCE2 wikipedia , lookup

Transcript
Publication Quizzes Questions, Answers, Distractors, and Reference Submission
Submittor’s/Reviewer’s Name:
Article Name:
Critical Chain Buffer Sizing: A Comparative Study
Question
1
Question Text
Which of the following statements
best describes the purpose of the
critical chain project
management?
2
The Critical Chain Project
management is developed using
which of the following theories:
Which of the statements is of
possible mechanisms to reduce
project delays:
3
4
5
Which of the following is the
emphasis of the CCPM in a
project duration:
Which of the following statements
best describes the project buffer:
6
Which of the following statements
best describes the feeding buffer:
7
Which of the following statements
best describes the sizing of the
project buffer:
8
Critical Chain Project
Management builds schedules
using which of the following:
Correct Answer
Improve critical
chain stability and
increase the
probability of
achieving a
promised project
duration
The theory of
constraints
Don’t allow
multitasking and
resources
interruptions
Resource
behavior
A .safety margin
that acts as a
protection of the
project due date
Extra times placed
whenever a non
critical activity
joins the critical
chain
The size of the
project buffer can
depend on the
desired probability
for completing the
project schedule
Finished to start
(FS)
Distractor 1
Improve the
product quality
Distractor 2
Trade off between
risks and benefits
Distractor 3
Ensure cost
,quality and
schedule were
met as expected
Page Reference
1
Theory of total
quality
management
Use activities due
date
Theory of SIX
SIGMA
Theory of capital
asset pricing
model
Put more
resources
1
Project scope
Cost overrun
Gantt chart
1
Extra times put in
the critical path
Increase of project
duration by 10%
Increase of project
budget by 10%
2
Extra times put in
the beginning of
each task
Extra times placed
in every critical
task
Extra times placed
at the beginning of
the execution
phase
2
The size of the
project buffer
should be
adequately
determined based
on the scope
complexity
Start to finish (SF)
The size of the
project buffer can
depend on the
time to market
requirement
The size of the
project buffer can
never be
determined
because of too
many uncertainty
2
Finished to
Finished (FF)
Start to Start (SS)
2
Allow multitasking
1
Remember, if you are a reviewer commenting on the questions/answers/distractors that have been submitted by another Publications Quizzes
volunteer, please turn on/enable your Track Changes feature. If you have questions, please contact [email protected] or dial her at PMI,
+1 610 356 4600 extension 1033.
Publication Quizzes Questions, Answers, Distractors, and Reference Submission
9
10
CCPM builds buffers in non
critical activities using which of
the following logic:
What is used to evaluate the
impact of the CC/BM scheduling
logic:
11
Which of the following indicators
measure the impact of CC/BM
scheduling logic:
12
Which of the following statements
is true:
13
Given the formula n(FB’s) /
n(CC), which of the following
statements is true:
14
Given the formula n(FB’s) / N,
which of the following statements
is true:
15
Which of the following statements
is correct:
Both As late as
possible and Start
no earlier than
Both
Morphological
Impact Measures
and Time Impact
Measures
Number of feeding
buffers by the
number of
activities in the
critical chain; AND
number of feeding
buffers by the
number of
activities of the
project schedule
Project buffers
generally
produced more
impact in project
duration than
feeding buffers
n(CC) is the
number of
activities in the
critical chain
N is the number of
activities of the
project schedule
CCPM stands for
Critical Chain
Project
Management
As late as
possible
Start no earlier
than
As soon as
possible
4
Time Impact
Measures
Morphological
Impact Measures
Monte Carlo
Impact Measures
5
Number of feeding
buffers by the
number of
activities in the
critical chain
Number of feeding
buffers by the
number of
activities of the
project schedule
Number of
activities in the
critical chain by
the number of
feeding buffers
5
Feeding buffers
generally
produced more
impact in project
duration than
project buffers
n(CC) is the
number of
activities in the
critical path
N is the number of
months allocated
to the project
Both project and
feeding buffers
produced same
impact in project
duration
Neither project nor
feeding buffers
had any impact in
project duration
11
n(FB’s) is the
project buffer
n(FB’s) is the task
buffer
5
N is the total
budget allocated
to the project
5
Monte Carlo
Simulation is a
tool to define
product quality
Monte Carlo
Simulation is a
tool to define
benefits
N is the number of
resources
allocated to the
project
Monte Carlo
Simulation is a
tool to define
costs overun
1
How would you rate the content of this article? Beginner Content Intermediate Content Advanced Content
Intermediate to Advanced Content
Remember, if you are a reviewer commenting on the questions/answers/distractors that have been submitted by another Publications Quizzes
volunteer, please turn on/enable your Track Changes feature. If you have questions, please contact [email protected] or dial her at PMI,
+1 610 356 4600 extension 1033.
Publication Quizzes Questions, Answers, Distractors, and Reference Submission
How would you rate the readability of this article? Easy to Read Difficult, at times, to Read Impossible to follow
Difficult at times to read
Remember, if you are a reviewer commenting on the questions/answers/distractors that have been submitted by another Publications Quizzes
volunteer, please turn on/enable your Track Changes feature. If you have questions, please contact [email protected] or dial her at PMI,
+1 610 356 4600 extension 1033.