Download FS-LGE-2015-002 Facilities Study Report (Modified)

Survey
yes no Was this document useful for you?
   Thank you for your participation!

* Your assessment is very important for improving the work of artificial intelligence, which forms the content of this project

Document related concepts
no text concepts found
Transcript
INDEPENDENT, INNOVATIVE, RELIABLE TRANSMISSION MANAGEMENT SERVICES
FS-LGE-2015-002
Facilities Study Report (Modified)
January 22, 2016
Study & Preliminary Report Completed By:
LG&E and KU Transmission
Report Prepared By:
TranServ International, Inc. (ITO)
Firm Network Service
OASIS # 80661550
TranServ International, Inc.
3660 Technology Drive NE
Minneapolis, MN 55418
Phone: 763.205.7080
Louisville Gas & Electric/Kentucky Utilities
FS-LGE-2015-002 Facilities Study Report
January 2016
Page 2 of 7
Legal Notice
Neither TranServ International, Inc. (TranServ), nor Louisville Gas & Electric Company /Kentucky
Utilities Company (LG&E and KU) nor any person acting on or in the behalf, makes any warranty,
expressed or implied, with respect to the use of any information or methods disclosed in this
document, or assumes any liability with respect to the use of any information or methods disclosed
in this Report. Recipients of this Report release TranServ and LG&E and KU from any liability for
direct, indirect, consequential, or special loss or damage whether arising in contract, warranty,
express or implied, tort or otherwise, and regardless of fault, negligence and/or strict liability.
Louisville Gas & Electric/Kentucky Utilities
FS-LGE-2015-002 Facilities Study Report
January 2016
Page 3 of 7
1. Executive Summary
A Facilities Study was performed by LG&E and KU for the following request:
Table 1
Request Details
Assign
Ref
POR
POD
MW
TS
Increment
TS Type
Request
Type
Start Time
Stop Time
Q-Time
80661550
LGEE
LGEE
34
YEARLY
NETWORK
ORIGINAL
2015-05-31
23:00:00 CS
2017-12-31
23:00:00 CS
2015-01-02
10:08:09 CS
TranServ as Independent Transmission Organization (ITO) completed a Transmission Service
Request (TSR) System Impact Study (SIS). This study identified constraints to providing the
requested service that resulted in the need for both direct assignment facilities and network
upgrades. Therefore, the Facilities Study Agreement was issued.
The LG&E and KU Open Access Transmission Tariff (OATT) states that the Facilities Study will
include a good faith estimate of (i) the cost of Direct Assignment Facilities to be charged to the
Eligible Customer, (ii) the Eligible Customer’s appropriate share of the cost of any Network
Upgrades, and (iii) the time required to complete such construction and initiate the requested
service.
LG&E and KU Transmission initially performed a Facilities Study for the subject request that was
submitted to the customer in July 2015. After review of the Facilities Study report the customer
recommended an alternate solution to mitigation of the identified constraints. In accordance with
19.6 of the OATT, the Facility study was reopened. This report details the required new Facilities
and Facilities upgrades identified through evaluation of the proposed option. TranServ has
reviewed the Facilities Study results and draft Facilities Study Report from LG&E and KU and
prepared this final report in accordance with the LG&E and KU OATT.
Louisville Gas & Electric/Kentucky Utilities
FS-LGE-2015-002 Facilities Study Report
January 2016
Page 4 of 7
2. Facilities Study Results from LG&E and KU
TranServ completed a TSR SIS and identified the following thermal and voltage constraints in
Table 2-1 for providing the requested transmission service for the subject request. LG&E and KU
performed a Facilities Study and determined that mitigation of the thermal and voltage constraints
can be achieved through installation of direct assignment facilities and network upgrades.
Table 2-1
Mitigation
Needed
By
Facility to Mitigate
CORYDON
69 TO HILAND M
69
2015S
1025:TRMCLFROCJEF
2015S
RIVRVW COAL
2015W
MORGNFLD
OVRL N T
2016S
69.000 TO
69.000 1
OVRL N T 69.000 TO RVRVW CL TP
69.000 1
RIVRVW COAL 69.000 TO RVRVW
CL TP 69.000 1
MORGNFLD 69.000 TO
OVER S T
69.000 1
DIXON
69.000 TO NEBO
69.000
1
HILAND M
OVER S T
69.000 TO
69.000 1
2016S
2017S
2017S
2017S
2017S
OVRLND N
2017S
OVRL N T
2017S
OVRLND N
2017S
RVRVW CL TP
2017S
UNIONTWN
2017S
ASHYBURG
2018S
ADVENT MINE
2019S
ONTON
2019S
ASHBY EL
2020S
SEBREE
2020S
2834:WILMATGRVWIL
2020S
DODGE HL
2023S
STURGIS
2023S
POOLE
2024S
Louisville Gas & Electric/Kentucky Utilities
FS-LGE-2015-002 Facilities Study Report
January 2016
Page 5 of 7
2.1 Direct Assignment Facilities
There are direct assignment facilities required at Morganfield to accommodate the installation of
a 69 kV radial circuit from the delivery point to Morganfield substation.
Table 2-2 breaks down the required projects, and provides cost estimates and anticipated inservice dates:
Table 2-2
Cost
($k)
Anticipated In-Service
Date
Install a 69 kV exit at Morganfield for the new line (radial 69).
434
5/2017
Install 69 kV metering for the Riverview Coal load.
350
5/2017
Relocation of existing 69 kV and 161 kV lines to accommodate
new 69 kV radial.
500
5/2017
Construction
The cost estimate for direct assignment facilities is $1,284,000 USD.
2.2 Network Upgrades
TranServ completed a TSR SIS and identified thermal and voltage constraints for providing the
requested transmission service for the subject request. LG&E and KU performed a Facilities
Study and determined that mitigation of the thermal and voltage constraints can be achieved
through installation of network upgrades in combination with the direct assignment facilities
discussed in the section above. Table 2-4 breaks down the facilities which can be mitigated
through network upgrades. The numbers in the Mitigation column correspond to the project
descriptions in Table 2-5. Table 2-5 also includes the cost estimate for each mitigation and the
anticipated in-service date.
Table 2-4
Mitigation
Needed
By
Mitigation
2015S
1
1025:TRMCLFROCJEF
2015S
4
RIVRVW COAL
2015W
2
2016S
2
2016S
2
RIVRVW COAL 69.000 TO RVRVW CL TP 69.000 1
2017S
2
MORGNFLD
2017S
1
2017S
1
2017S
1
Facility to Mitigate
CORYDON
69 TO HILAND M
MORGNFLD
OVRL N T
DIXON
HILAND M
1
69
69.000 TO OVRL N T
69.000 1
69.000 TO RVRVW CL TP 69.000 1
69.000 TO OVER S T
69.000 TO NEBO
69.000 1
69.000 1
69.000 TO OVER S T
69.000
Louisville Gas & Electric/Kentucky Utilities
FS-LGE-2015-002 Facilities Study Report
January 2016
Facility to Mitigate
Page 6 of 7
Mitigation
Needed
By
Mitigation
OVRLND N
2017S
OVRL N T
2017S
OVRLND N
2017S
RVRVW CL TP
2017S
UNIONTWN
2017S
ASHYBURG
2018S
ADVENT MINE
2019S
ONTON
2019S
ASHBY EL
2020S
SEBREE
2020S
2834:WILMATGRVWIL
2020S
5
DODGE HL
2023S
1
STURGIS
2023S
1
POOLE
2024S
1
1
3
Table 2-5
Mitigation
1
A. Install high side breaker on existing Morganfield 161/69 kV
transformer.
B. Install second Morganfield 161/69 kV transformer.
2
Mitigation is achieved through 69 kV distribution radial
3
Install capacitor bank near Ashbyburg
4
Existing operating guide.
5
Two year acceleration of an existing project.
Total:
Cost
($k)
Anticipated InService Date
6,014
A. 05/2016
B. 05/2017
0
05/2017
450
05/2017
0
N/A
0.422*
05/2020
6,464.42
*Total cost of the project is estimate to be $4,500 USD. The cost of the two year advancement
is estimated to be $422 USD.
The total cost estimate for network upgrades is $6,464,420 USD. The Transmission Customer’s
share of the Network Upgrades cost is $0 USD.
2.3
Project Completion Timeframes
The time frame required for Engineering, Procurement, and Construction of the necessary
facilities is provided in the Tables 2-2 and 2-4 above. It is anticipated that the majority of the initial
projects will not be completed until 2017, which is beyond the 2015 and 2016 need dates
discussed above. The Transmission Customer’s load is currently served from a radial, which
eliminates the possibility of an operating guide. As such, the maximum load that can be served at
Louisville Gas & Electric/Kentucky Utilities
FS-LGE-2015-002 Facilities Study Report
January 2016
Page 7 of 7
the Transmission Customer’s existing delivery point is approximately 31 MW (98% power factor)
during the interim period. This load level was tested assuming that the breaker on the high side
of the Morganfield 161/69 kV transformer could be in place prior to Summer 2016.