 2.2 Existing Facilities
The physical plant consists of four structures totaling 48,427 Gross Square Footage (GSF)
and 31,814 Net Assignable Square Footage (NASF).
The Appalachian Laboratory building
(#900) houses the main research laboratories on site. Additionally, the campus includes
a greenhouse, garage, and chemical storage building (Illustration 2.1 and 2.5). Table 2.1
summarizes each physical structure at the AL campus, including construction dates, GSF,
(NASF), and condition code.
Each of the three levels of the main building (Building #900) are shown in illustrations 2.2, 2.3,
2.4 for a visual overview of the existing program.
1. AL Building Lobby
The overall condition of the facilities is satisfactory with the exception of the greenhouse.
The greenhouse, considered one of the research laboratories, requires major renovation or
replacement within the next few years (Figure 3) Failure of the greenhouse plumbing system,
which includes heating and cooling environmental controls, will force this facility to close,
adversely impacting the research of multiple AL faculty.
See Table 2.1 for more information.
900
Appalachian Laboratory Building
The main building contains a classroom used for meetings and presentations;
Interactive Video Network (IVN) room; administrative offices; faculty offices; graduate
student offices; small conference room; library; laboratory support rooms; building
and computing service areas; and research laboratories for water chemistry, soil and
plant ecology, wildlife sciences, quantitative landscape ecology, watershed hydrology,
stream ecology, forest ecology, general ecology, molecular ecology, and stable isotope
research. A bridge within the three-story atrium connects the two-story administrative
wing with the laboratory wing.
901
2. AL Greenhouse
AL Chemical Storage Building
The Chemical Storage Building provides safe, secure storage for faculty samples,
hazardous materials and lab gasses. It is currently in satisfactory condition.
902
AL Greenhouse
Built within a year of main building. Currently used by 2 researchers. Two water tanks
with sensors feed the greenhouse and generator. Piping and heating is deteriorating
and will require replacement within 5 years. The internal shading system within the
greenhouse needs to be replaced.
3. AL Greenhouse - Deteriorating plumbing system
III-10
903
AL Garage
This structure provides grounds maintenance equipment storage. Currently the facility is in
satisfactory condition.
TABLE 2.1*
Building
Number
900
Building
Name
Appalachian
Laboratory
AL Chemical
Storage
AL
Greenhouse
Garage
901
902
903
AL
Totals
Total
GSF
42,843
Building
NASF
26,631
363
0.62
Year
Constructed
1999
320
0.88
1999
145,817
1
14,582
4,226
3,799
0.90
1999
1,919,290
4
191,929
855
840
0.98
2000
76,950
1
5,130
48,287
31,590 Efficiency
Replace
Value
19,275,237
21,340,344 Condition
Code
1
Renovation
Cost
1,927,524
2,134,034
* Information for Table 2.1 was obtained from UMCES SGAP 2011.
III-11
TABLE 2.2
The table below references the building condition codes from the previous Table 2.1. The percentages shown reflect
the number of buildings with that particular code assigned to it.
AL Building Condition (GSF) Code 4 25% Code 5 0% Code 3 0% Code 2 0% Code 6 0% Code 1 75% Building Condition Code:
1.
Satisfactory
Suitable for continued use with normal maintenance.
Remodeling – A
Requires restoration to present acceptable standards without major room changes, alterations, or modernization.
The approximate cost of remodeling is not greater than 25% of the estimated replacement cost of the building.
Remodeling - B
Requires major updating and/or modernization of the building. The approximate cost of remodeling is greater than 25% but not
greater that 50% of the estimated cost of the building.
Remodeling - C
Requires major remodeling of the building. The approximate cost of remodeling is greater than 50% of the
remodeling/replacement cost of the building.
5.
Demolition
Should be demolished or abandoned because the building is unsafe or structurally unsound, irrespective of the need for the spa ce
or the availability of funds for replacement. This category takes precedence over categories 1, 2, 3, and 4.
6.
Termination
Planned termination or relinquishing or occupancy of the building for reasons other than unsafeness or structural unsoundness,
such as abandonment of the temporary units or vacating of leased space. This category takes precedence over categories 1, 2, 3,
and 4.
2.
3.
4.
III-12
'?''
LEGEND
X01, X03,or X04 - Building Service Area
Y04 - MeChanical Area
110 - Classroom
115 - Classroom Service
635 - Food Facility Service
310- Office
• W06, W02,W04 or W05 - Circulation
AL Building- Existing Program Level 01
NOT TO SCALE
EBN
-t........
LEGEND
X01, X03,or X04 - Buildnig Service Area
Y04 - MechanicalArea
350 - Conference Room
•710 - CentralComputing/Telecomm
•720 - Shop & Shop Service
310- Office
• W06, W02, W04 or WOS- Circulation Area
315 - Office Service
250 - Research/Nonclass Laboratory
•255 • Research/Nonclass Laboratory Service
AL Building·Existing Program Level 02
NOT TO SCALE
ffi,.
..
J
0
L
1
'
-
r• ,..,. ,
'+
-·.•
·r
·· ·-
.•..,.
1
-
,
.,,
""
..
r
,
,....
-'
·
· ·
F
n
"W
r-'
'·
·c
l
_.,_
I ·
1--"'
v
:
'
!
[
, _ __
:
•
i.
.•.
:
•
:
•:
LEGEND
: L ====
X01. X03,or X04 - Buliding Service Area
Y04 - Mechanical Area
430 - Open Stack Study Room
310- Office
• W06, W02, W04 or W05- Circulation Area
====d
315 - Office Service
250 - ResearcWNonclass Laboratory
•255 • Research/Nonclass LaboratO<)' serv1ce
lliUSft'auon 2.6
AL Building- Existing Program Level 03
NOT TO SCALE
EBN
Appalachian Laboratory Exterior Buildings
Building 901
Greenhouse
Zone2
Greenhouse
Zone1
Mechanical
Room
..
Greenhouse Zone 3
Building 002
LEGEND
!lU
• 5S5 ·Greenhouse
SeNice
• 740 · Vehi:le Storage
-760
H.;;, rdouc
Ya!i!i.,r:.i¥
I
Chemical
storage
Building
Buildinq 903
Y04 - MechanicalRoom
AL Ancillary Buildings 901. 902 and 903.
NOT TO SCALE