1. Power Demand Summary
Power Requirements
Project
Development
Scheduled
Completion Date
Connected Load
in (KVA)
Maximum Demand
in (KVA)
Estimated
Consumption in
(KWH/Yr)
Phase 1
Phase 2
Ultimate
2. Record the Distribution Voltage within the facility in Volts
3. Provide details of any arc furnace, electrochemical processes, rectifier leads, and other
equipment that could cause a power disturbance.
4. Special Electrical Requirements
Motor Type
Horsepower
Voltage
Largest Motor
H.V. Motor
L.V. Motor
5. Emergency Power Supply
 Indicate the maximum period of time the production process
can be sustained without power supply.
 Describe the type of emergency power supply to be installed
by the investor.
S: Adonis / SAR / Power Demand Summary
Rating
KVA
Page 1 | 3 (SAR - Attachment 3)
Firm Name :
Attachment 3 : Power Demand Summary
Project Name :
Date:
6. Equipment Details: Motive Power Load
Type of
Motor
Quantity
Type of
Starter
H.P.
Maximum
number of
starts per
hour /a/
Total H.P.
Power
Factor
KVA
/a/ Ignore motors less of than 10 H.P.
7. Welding Load
Type of Welder
8. Arc Furnaces
Quantity
Total
S: Adonis / SAR / Power Demand Summary
Total KVA
Process
Heating
ElectroChemical
Rectifier
Type of
Equipment
Usage Pattern &
Control
Load in KVA
Total
Page 2 | 3 (SAR - Attachment 3)
Firm Name :
Attachment 3 : Power Demand Summary
Project Name :
Date:
9. General Power Summary
Load
Total
KW
Maximum
Demand
Connected
Load
KVA
KW
KVA
 Lighting
 Motive Power (Table 6)
 Welders (Table 7)
 Process Heating etc. (Table 8)
 Space Heating
 Air Conditioning
 Water Heating
 Cooking -- General Purpose
 Total
10. Indicate the expected overall power factor of the connected load.
11. If power factor is lower then permissible minimum (0.85), indicate what provisions for P.F.
improvement are being made.
12. Provide, as an attachment, the specifications and single line diagram of switchgear
and protective relaying equipment to be installed by the investor.
13. If emergency standby generation is to be installed by the investor, provide details
(including single line diagram) of interlocking proposed to avoid paralleling with utility
supply.
S: Adonis / SAR / Power Demand Summary