Download Capacity Market

Survey
yes no Was this document useful for you?
   Thank you for your participation!

* Your assessment is very important for improving the workof artificial intelligence, which forms the content of this project

Document related concepts

Grey market wikipedia , lookup

Market (economics) wikipedia , lookup

Economic equilibrium wikipedia , lookup

Supply and demand wikipedia , lookup

Transcript
LTTR, FCM, RPM, MRTU: Do More
Acronyms Mean Better RTO Markets?
An Overview of Various RTO Capacity Constructs and their
Impact on Load Serving Entities
www.ces-ltd.com
Issue: The Missing Money
• In an average year, some peaking generation will only run a few
hours a year.
• For most commodities, infrequent utilization/purchase of a
resource/product may be a signal that the resource/product is
not needed.
• Electricity is different: we must keep the lights on, so must hold
onto some infrequently utilized resources.
• In today’s energy markets:
– If a generator does not run, it does not get paid
– ISOs need a way to repay this “missing money” to keep enough
generation on hand.
www.ces-ltd.com
2
How to Recover the Missing Money
• Scarcity Pricing Only: To ensure that sufficient investment is
made in supply, a market can be designed such that during
those infrequent periods of unusually high demand, prices are
also permitted to go unusually high.
• Capacity Market: To combat market power concerns, the
energy price is mitigated and generally assumed to only cover
short-term variable costs, and a second revenue stream via a
capacity construct is developed to cover long-term fixed costs.
• Hybrid: This approach combines a capacity construct with
relaxed energy market mitigation and/or limited administrative
price setting.
www.ces-ltd.com
3
Previous Capacity Market Approach
• Unforced Capacity (UCAP) market
– Generators assigned an Unforced Capacity value based on
the generator’s forced outage rate
– ISO’s goal was to procure enough unforced capacity to meet
the expected load forecast plus a sufficient Installed Reserve
Margin (IRM) to ensure a loss of load probability less than
one in ten years.
• Loads must procure sufficient capacity to cover
unforced capacity obligation or pay deficiency charge
– Capacity could be acquired through:
• Bilateral contracts
• Auctions (loads needed only procure the delta between their
requirement and bilateral contracts)
www.ces-ltd.com
4
Previous Capacity Market Issues
• Auctions resulted in very low ($5/mw-day) or very
high clearing prices ($160/mw-day) with little in
between
Case 1: Capacity less than
Installed Reserve Margin: Capacity
Clears at Deficiency Rate
Case 2: Capacity greater than
Installed Reserve Margin: Capacity
Clears very low
180
160
140
120
100
80
60
40
20
0
Demand
Supply
0.95
www.ces-ltd.com
0.97
1
1.05
5
Previous Capacity Markets
• The Good:
– Loads can easily fulfill obligations through long term bilateral
contracts
– Multiple options to make up for capacity requirements
beyond bilateral contracts
• Monthly, multi-monthly, and daily auctions
• The Bad:
– Price volatility increases long term investment risk
– RTO wide clearing price results in low price for capacity, but
does not recognize localized capacity shortages
– Low prices have caused high marginal cost units in areas
like New Jersey and Southeastern Mass to retire, requiring
expensive out of market Reliability Must Run (RMR)
contracts
www.ces-ltd.com
6
Case Study: PJM’s RPM Approach
• Capacity acquired through annual, forward auctions
– Centralized procurement
– Auctions cleared based on resource offers, demand obligation, and
reliability metrics
• Auctions contain a Variable Resource Requirement (aka
“Demand Curve”)
– Values capacity above the installed reserve margin requirement
– Sets clearing price at intersection with supply curve
• Locational clearing prices
– Locational Deliverability Areas (LDAs) defined based on
transmission import capability into local areas
– Each LDA’s clearing price may contain an adder over the system
price, if additional capacity is needed in the LDA
www.ces-ltd.com
7
Variable Resource Requirement
• RPM includes a Variable Resource Requirement (aka “Demand
Curve”) that will establish the market clearing prices in each
LDA
• Clearing prices set at the intersection of the supply curve and
Variable Resource Requirement
• Curve is intended to value capacity above the Installed Reserve
Margin requirement, theoretically resulting in lower capacity
costs in the long run, due to minimizing the boom / bust capacity
cycle
• Curve is based on the daily cost for a new combustion turbine,
minus the revenues a combustion turbine would earn from the
Energy and Ancillary Services Markets
www.ces-ltd.com
8
PJM’s Variable Resource Requirement
1.6
1.4
Multiple of Cost of New Entry
Clearing Price established
By intersection of VRR and
1.2
Supply curve
1
0.8
0.6
0.4
Supply Curve
0.2
0
-10
-8
-6
-4
-2
0
2
4
6
8
10
Percentage Point Change From Installed Reserve Margin
Load required to purchase more than
Installed Reserve Margin (104.5% in this case)
www.ces-ltd.com
9
Locational Deliverability Areas
• RPM adds a locational component to PJM capacity
pricing:
– Each “Locational Deliverability Area” under RPM is subject
to a locational price adder, inflating an LDA’s price over the
RTO price
– LDAs are defined based on transmission capacity transfer
capability into an area
– LDA price will only be higher than the remaining RTO if
additional, more expensive capacity is needed within the
LDA
www.ces-ltd.com
10
Locational Deliverability Areas
www.ces-ltd.com
11
RPM Auctions
• Under RPM, PJM will conduct forward auctions.
– Auctions held three years in advance of the planning year
– Auctions held for an entire planning year (June 1 to May 31)
• Unlike the current capacity market, load does not
directly participate in RPM auctions
– PJM administratively bids load into the auctions via the
demand curve
– Loads will ultimately pay zonal capacity prices based on the
auction clearing prices
– Bilateral contracts will provide a credit against the capacity
prices, but the credit may not equal the capacity charge
www.ces-ltd.com
12
Auction Results
• First RPM auction was held in April, 2007
– Auction prices apply for the 2007/2008 Delivery Year
• Load Prices as a result of the auction:
Locational Deliverability Area
Load Price
($/mw-day)
Eastern MAAC (NJ, Eastern PA,
Delmarva):
$177
Southwestern MAAC (DC,
Baltimore):
$140
Remainder of PJM:
$41
www.ces-ltd.com
13
Forward Procurement: Good or Bad?
• Three year forward auction provides:
– Ability for new generation to offer into the market and be
guaranteed a capacity price
– Certainty for PJM that it will have sufficient installed capacity
• Forward auction also:
– Limits ability for load serving entities to arrange bilateral
capacity
– Adds risk to generation owners to offer full amount of
capacity into the market, which can result in a premium on
the generator’s offer
www.ces-ltd.com
14
Locational Capacity Pros and Cons
• Arguments for:
– Engineering reality of the electric grid is that generation can’t
all be built in the same place and transmission relied upon to
deliver to any location.
– Sends price signals to locate generators in the proper areas
or build transmission into constrained areas
Doesn’t LMP
already do this?
www.ces-ltd.com
15
Locational Capacity Pros and Cons
• Arguments against:
– If a location is constrained, it will already be subject to higher
LMP prices and higher capacity prices only serve to punish
the load in that area further.
– If the previous construct allowed obligation to be met with
remote resources, entities that believed they had satisfied
their obligation for the long-term may find that the resource
they contracted with no longer satisfies the requirement.
www.ces-ltd.com
16
Transmission Impacts
• The forward capacity markets are intended to help
bolster transmission upgrades
– PJM’s RPM allows transmission upgrades to be offered into
the market to increase the transmission capacity into
constrained Locational Deliverability Areas
– Locational price differences will help justify economic
upgrades developed by PJM
• The key is that transmission planning still needs to
occur on a longer horizon
– RTO’s cannot count on these capacity markets along to
develop the system!
www.ces-ltd.com
17
Other RTO Solutions
• ISO-NE:
– Forward Capacity Market, similar to PJM
• Contains locational component
• Three year forward procurement
– Descending clock auction
• MISO:
– Hybrid approach that pairs a bilateral based decentralized
capacity construct with a formalized scarcity pricing
mechanism.
– Theory is that capacity markets with forward procurement
and longer commitment periods are attempts to emulate in
an administrative fashion the outcomes that should occur
from a competitive market.
– Called “Reliability Through Markets (RTM)”
www.ces-ltd.com
18
Questions?
Erik Paulson
Director of Regulatory Affairs, PJM
[email protected]
215-875-9440
www.ces-ltd.com