Common Cause/PA Website Project
Common Cause of Pennsylvania
• Who are they?
• Volunteer based
nonpartisan nonprofit
advocacy organization
• What do they do?
• Inform constituents of PA
of the issues that affect
Pennsylvanians
• Work to strengthen
public participation in the
political process
• Goals
• Continuing growth and
spreading their message
across the state
The Problem
• CC/PA would like to have control of their
own website
• Currently run by national chapter of CC
• Would like maintain a new website in
house which can be controlled by
volunteers
• New website will support their goals by
increasing their visibility
Stakeholder Analysis
• Team 8
 Project Managers
 SME - Suzanne Cummings
• James Eisenstein
 Project Sponsor
• Barry Kauffman
 CC Executive Director
• Ruth Frits
 Web Developer
• Entry Level & Interns
 Resources
Initial Financial Analysis
Final Financial Analysis
Cost variance = Earned Value – Actual Cost = $62,181.28 - $55,519.00 = $6662.28
Schedule Variance = Earned Value – Planned Value = $62,181.28 - $66,622.80 = -$4441.52
Cost performance Index = Earned Value / Actual Cost = $62,181.28 / $55,519.00 = 1.12
Schedule Performance Index = Earned Value / Planned Value = $62,181.28 / $66,622.80 = 0.933
Estimate at Completion = Budget at Completion / Cost Performance Index = $111,038.00 / 1.12 = 99141.07
Earned Value Chart
150000
• Under Budget
BAC
100000
EAC
$
PV EV
AC
50000
0
0
3
6
Month
6.45
• Behind Schedule
Milestones
Milestone
Date
Initiating
Completed scope draft
10/27/05
Assemble project teams, define roles
completed
10/20/05
Completed initiating stage
10/20/05
Planning
Completed schedule
11/10/05
Completed planning stage
11/11/05
Executing
Completed CMS development
11/25/05
Completed Templates
11/14/06
Completed site design
11/23/05
Completed website construction
11/30/05
Completed security development
1/19/06
Completed executing stage
1/19/06
Deployment
Completed deployment stage
2/2/06
Milestones Continued
Rollout
Date
Modify items as necessary
2/13/06
Completed Pilot
2/13/06
Completed stakeholder review
2/14/06
Deploy production system complete
2/20/06
Completed rollout
2/21/06
Completed deployment stage
2/21/06
Controlling
Status reports
16th of every month
Stakeholder status report
Every Wednesday
Status reports to client
Every other Wednesday
Completed external testing
3/13/06
Completed unit testing
3/13/06
Completed external testing
3/17/06
Completed integration testing
3/17/06
Completed external testing
3/20/06
Completed testing stage
3/21/06
Training materials complete
3/28/06
Completed documentation
3/28/06
Completed controlling stage
3/28/06
Closing
Project concluded
4/4/06
Project Risk Management
• Technology Risk
Medium Probability / High Impact / Risk Factor of 4
No confirmation to see approval of hardware
No relationship between sponsor and Kintera
• Financial Risk
High Probability / High Impact / Risk Factor of 7.2
Non profit organization / Not certain of volunteer’s
experience
No budget could make the project unfeasible
• People Risk
Medium Probability / High Impact / Risk Factor of 3.2
Working on project without getting to know clients
Manager and team realize misunderstanding of
customer’s expectations
Project Risk Management (cont’d.)
• Market Risk
Medium Probability / High Impact / Risk Factor of 3.2
Displeased over the control of their presence on the
Internet
Website draws more users and members to
organization
• Structure/Process Risk
High Probability / Low Impact / Risk Factor of 2.4
National level of organization take over CC/PA
website
Customized website distinguish unique identity
Project Quality Management
Standards:
• Website works on all browsers
• Accessible to all users: website can be used by
the disabled
Requirements:
• Completed project meets all specifications
and satisfies all needs: the website must
accomplish the desired goal and meet all
expectations
• System available 24/7: the website is available
at all times, except during updates or
reconstruction
• System available to all users: anybody can use
and view the website
• System is easy to find/navigate: website is
linked to the main Common Cause website;
website is easy to find through web searches and
easy to navigate
Lessons Learned
• Contact stakeholders early in
the project and stay in contact
• Define scope more clearly
• Have resource availability
defined in writing