HE FEE Boards production status
26th May 2016
Mandakini Patil
1
Production of the boards
• Pulser Boards (ver3.1) Fabrication :
4 completely assembled boards were ready at Peninsula, Bangalore on 21st May
• BV converter PCBs :90 boards ready and delivered to TIFR on 24th May
• SiPM control boards : PCB work initiated –PCBs ready by 26th May and assembly
after that , to be delivered by May end
• Test stand work in progress : Test boards for SiPM control boards
will get ready by next week
• Pin diode boards PCBs: 300 PCBs at TIFR (made by Yashna circuits Mumbai)
in house assembly for 5 boards will be done by Pathare
• QIE Adapter boards : 50 completely done, will be available by Month end
26th may 2016
Mandakini Patil
2
Test stand setup at TIFR, Mumbai
• Test setup for the SiPM Boards testing and the Pulser boards testing
is getting ready and we are testing 3 old SiPM boards
• Tested an old SiPM control board and are having some issues reading ADC1
correctly but will sort it soon, tested I2C communication to ADC2,DAC1 and
DAC2 and even probed the voltages on the scope and they are all ok.
• The Load Resistance board to test SiPM control board will be ready tomorrow
• 3 Pulser boards (ver3.1) tested, using the Backplane and ngCCM control
emulator and clock Emulator
• The first step of board checking for any inherent shirts was done at Bangalore
itself after assembly at all the FEASTMP_CLP dcdc voltage outputs and all OK
26th May 2016
Mandakini Patil
3
Testing of the 3 Pulser Boards
• After plugging in the boards ,the firmware for ver3.1 HE_Pulser_ASIC.pdb was
updated using FlashPro11.6 tool
(in the FlashPro Programmer settings Vpump-3.3V must be ticked)
• After the successful firmware updating ,using Raspberry pi,the I2c commands
were given to make the LED ON
• Adjusted the amplitude with the I2C data transaction and LED responded
accordingly
• Could not shine the LED light to the pindiode, as we don’t have the
QIE Adapter and QIE boards anyway.
• Waiting for the full fledged test of the 4th Pulser board ver3.1 to Fnal , to give a
Go Ahead for production of pulser boards
26th May 2016
Mandakini Patil
4
Aluminium Boxes status
• 5 Al Boxes dispatched last week and arrived at CERN ( Tina Vernon
acknowledged)
• Another set of 5 Boxes parts all ready and some hole tapping work is on
• For these 5 boxes, the modifications will have to be made after returning from
CERN in July and later incorporated here as well for the remaining boxes too
• Hopefully the updated design will be available soon too for the production boxes
• The next batch of 5 ore more boxes will be therefore sent after July ..Is it OK..?
26th May 2016
Mandakini Patil
5
Conclusions and Plans
• 3 Pulser Boards ver 3.1 tested fro all dcdc outputs and LED lighting and even regulated the LED light with the I2C
commands and they are functional as expected
• SiPM control boards calibration test board underway
• QIE Adapter boards, Pin diode boards , SiPM control boards, BV converter boards production are all under way
• Inter connecting hirose cables (2 HiRose Coaxial connector H.FL75-2LP-084H-A-500 H.FL75-2LP-084H-A- 5006
both ends female) procurement being done,
but delivery may be after july only
• Will carry with us the fully tested 10 SiPM control boards, 10 BV converter boards and 3 Pulser boards with us
to CERN by June 15th 2016
26th May 2016
Mandakini Patil
6
Extra Slides
28th April 2016
Mandakini Patil
7
TIFR Pulse Stand using backplane
28th April 2016
Mandakini Patil
8
TIFR Pulse Stand using backplane
28th April 2016
Mandakini Patil
9
TIFR Pulse Stand using backplane
28th April 2016
Mandakini Patil
10