Work plan of KNU for ATF2
 Men power
E-S Kim
S-H Shin
H-S Kim
Y-S Hwang
H-J Kim
I-M Hwang
: ATF2 Beam dynamics
: Design and fabrication of IP-BPM and S-band BPM
: Fabrication of IP-BPM
: Design and fabrication of IP-BPM electronics (Graduate student)
: Design and fabrication of IP-BPM electronics
: Experimental studies in ATF partly (New post-doc from March 2007)
 Budgets
- KNU has budgets of FY2006 to FY2008 for the R&D of ILC accelerator (~2000MYen/Y).
- KNU will also submit proposals for R&D of ILC accelerator to KOSEF and KRF
in March 2007. We expect that the budgets in FY2007 will be increased more than the
present and thus we need to consider another R&D items that may be performed after
completion of S-Band BPM.
- KNU R&D peoples for ILC accelerator and detector have a R&D meeting in 6th Dec..
After this meeting, we may inform more detailed accelerator R&D plans in FY2007.
Work plan of KNU for ATF2
(R&D items)
 Beam dynamics R&D
 Studies of final optics and beam tuning in ATF2
 Experimental studies in ATF
 Instrumentation R&D
 IP-BPM
- Body : design / fabrication / electrical testing
- Electronics : design / fabrication /electrical testing
 S-band BPM
- Body : design / fabrication / electrical testing
Work plan of KNU for ATF2
(Schedule)
 IP-BPM
- body : design (S-H Shin) until Dec. 2006 at KEK
: fabrication (S-H Shin, H-S Kim)
starts in Dec. 2006 at Korea
- Electronics : design (Y-S Hwang ) (5 Jan. -25 Feb. at KEK)
: fabrication (Y-S Hwang, H-J Kim)
starts in March 2007 at Korea
 S-band BPM
- body : design (S-H Shin) (1. Feb.~28 Feb. 2007 at KEK)
: fabrication (S-H Shin, H-S Kim)
starts in March 2007 at Korea