Pakistan: Second Power Distribution Enhancement Investment Program Tranche 1
Project Name
Second Power Distribution Enhancement Investment Program - Tranche 1
Project Number
47190-003
Country
Pakistan
Project Status
Active
Project Type / Modality of
Assistance
Loan
Source of Funding / Amount
Loan 3328-PAK: Second Power Distribution Enhancement Investment Program Tranche
1
Ordinary capital resources
US$ 380.00 million
Loan 3329-PAK: Second Power Distribution Enhancement Investment Program Tranche
1
Concessional ordinary capital resources / Asian Development Fund
US$ 20.00 million
Strategic Agendas
Inclusive economic growth
Drivers of Change
Partnerships
Sector / Subsector
Energy - Electricity transmission and distribution
Gender Equity and
Mainstreaming
No gender elements
Description
The proposed investment program's objective is to introduce advanced metering infrastructure
(AMI) in Pakistan's different distribution companies (DISCOs). An MFF is proposed for this
investment. There are nine DISCOs in Pakistan and the AMI roll-out to these DISCOs will be in
phases. In the first phase (tranche 1), two of LESCO's circles and IESCO's Rawalpindi region have
been selected for AMI roll-out. Once developed, the same will be replicated and implemented in the
remaining technically and commercially feasible regions or circles of the nine DISCOs.
Project Rationale and Linkage
to Country/Regional Strategy
AMI aims at: (i) reducing distribution losses and improving revenue collection, (ii) enhancing load
control and load management, (iii) providing automated consumption data collection of all
customers, and (iv) modernizing the electricity metering and billing system. The investment
program will provide funds for metering, communication and billing systems including installation
and supporting infrastructure.
Impact
Financial viability of the power distribution system improved (project-defined).
Project Outcome
Description of Outcome
Electricity revenues increased in the targeted regions of IESCO
and LESCO.
Progress Toward Outcome
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location
Smart Meters and communication equipment installed and
functional.
Data management system implemented and operational.
Operation manuals updated and monitoring procedure improved.
New billing and CIS systems implemented and operational.
Safeguard Categories
Environment
C
Involuntary Resettlement
C
Indigenous Peoples
C
Summary of Environmental and Social Aspects
Environmental Aspects
Expected to be categorized as "C". Expects no environmental impacts.
Involuntary Resettlement
Expected to be categorized as "C". Expects no resettlement.
Indigenous Peoples
Expected to be categorized as "C". Expects no land acquisition.
Stakeholder Communication, Participation, and Consultation
During Project Design
During PPTA, consultations with the poor and low-income groups will be conducted to include them in
the planning process. Risks and vulnerabilities for low income, women, poor and excluded groups will
be documented in consultation and participation of these groups.
During Project Implementation To be updated.
Business Opportunities
Consulting
Services
Consulting firms will be recruited for project monitoring and supervision, capacity development, and
communication strategy. The quality- and cost-based selection method (90:10) for firms will be used, following
ADB's Guidelines on the Use of Consultants (2013, as amended from time to time).
Procurement
The indicative procurement method for the turnkey contract will be international competitive bidding, following
ADB's Procurement Guidelines (2015, as amended from time to time). The project envisages advance contracting
for the turnkey contract and the consulting services. Retroactive financing of up to 20% of total financing will be
considered subject to preparedness of the project and availability of counterpart funds.
Responsible Staff
Responsible ADB Officer
Tareen, Adnan
Responsible ADB Department
Central and West Asia Department
Responsible ADB Division
Energy Division, CWRD
Executing Agencies
Ministry of Water & Power
Government of Pakistan
Safdar Mansion
16-D Blue Area Islamabad, Pakistan
Timetable
Concept Clearance
-
Fact Finding
-
MRM
23 Jan 2015
Approval
25 Nov 2015
Last Review Mission
-
Last PDS Update
22 Mar 2017
Loan 3328-PAK
Milestones
Approval
25 Nov 2015
Signing Date
19 Nov 2016
Effectivity Date
17 May 2017
Closing
Original
30 Jun 2019
Financing Plan
Total (Amount in US$ million)
Revised
Actual
-
-
Loan Utilization
Date
ADB
Others
Net Percentage
Project Cost
490.50
Cumulative Contract Awards
ADB
380.00
25 Nov 2015
Counterpart
110.50
Cumulative Disbursements
Cofinancing
0.00
25 Nov 2015
0.00
0.00
0.00
0%
0.00
0%
Loan 3329-PAK
Milestones
Approval
25 Nov 2015
Signing Date
19 Nov 2016
Closing
Effectivity Date
17 May 2017
Original
30 Jun 2024
Financing Plan
Revised
Actual
-
-
Loan Utilization
Total (Amount in US$ million)
Date
ADB
Others
Project Cost
20.00
Cumulative Contract Awards
ADB
20.00
25 Nov 2015
0.00
0.00
Counterpart
0.00
Cumulative Disbursements
Cofinancing
0.00
25 Nov 2015
0.00
Project Page
https://www.adb.org/projects/47190-003/main
Request for Information
http://www.adb.org/forms/request-information-form?subject=47190-003
Date Generated
17 June 2017
0.00
Net Percentage
0%
0%
ADB provides the information contained in this project data sheet (PDS) solely as a resource for its users without any form of
assurance. Whilst ADB tries to provide high quality content, the information are provided "as is" without warranty of any kind, either
express or implied, including without limitation warranties of merchantability, fitness for a particular purpose, and non-infringement.
ADB specifically does not make any warranties or representations as to the accuracy or completeness of any such information.