Building Safety Code Division
Department of Public Works
Weston Thomas A. Deleon Guerrero
Acting Building Safety Official
Topics

Creation of the Building Safety Code Division


Building Permits



Law and Regulations, Personnel, Duties and Responsibilities
When do I need a Permit? Application Process, Required Documents, What to
expect
Better, Stronger, Safer Construction (Mitigation)

Understanding of Load Path, Wind effects on your home

Designs, Installations, Materials, etc.
Information for the future

Pre-approved plans, Closing remarks
CREATION OF THE
BUILDING SAFETY CODE
DIVISION
Creation of the
Building Safety Code Division
(BSCD)

“Section 7111. Purpose. The purpose of this Building Safety Code is to secure
and promote the safety, health and general welfare of the people of the
Northern Marianas by providing standards for the location, design, material,
construction, enlargement, maintenance, use, occupancy, and moving of
buildings and structures in the Commonwealth.
This Code and its
implementing rules and regulations are dedicated to the development of
better building construction and greater safety for the citizens and residents
of the Commonwealth of the Northern Mariana Islands.”
–ARTICLE 1, PUBLIC LAW 6-45

Building Safety Code created and governed by the following

Public Law 6-45

CNMI Administrative Code, Title 155-10.1

Adoption of International Building Code, 2009 Edition
Building Safety Code Division
Personnel

Weston Thomas A. Deleon Guerrero, Acting Building Safety Official

Building Safety Code Division Administrative Staff



Yvonne B. Tenorio

Nadine B. Sablan

Consolacion Atalig
Building Safety Code Division Inspectors

Glen D. Palacios, Building Inspector Supervisor

Angelo Camacho, Building Inspector

John Peter Sablan, Building Inspector Trainee

Jacobe Fejeran, Building Inspector Trainee
Building Safety Code Division Technical Staff

Dennis D. Drew, Plan Reviewer

Edwin Tmarsel, Floodplain Administrator
General Duties and Responsibilities of the
Building Safety Code Division

Issue Building Permits, Special Substructure Permits

Construction Inspections

Issue Certificates of Occupancy

Community Outreach (Education) on the following topics:

Building Safety Code requirements

Fire Safety and Means of Egress (MOE)

Life Safety Requirements

Energy Efficiency

Better Building Practices

New Technology and Materials
General Duties and Responsibilities of the
Building Safety Code Division

Structural assessments on dilapidated, unsafe, blighted properties

In some cases, Condemn unsafe buildings for public safety

Annual Safety inspections

Issuance of Stop work orders, Notices of Violation

Examples:

Building without a permit

Not requesting proper inspections before moving forward

Not constructing according to plan
BUILDING
PERMITS
When do I need a BUILDING PERMIT?

A permit is required by the 2009 International Building Code as follows:


“Any owner or authorized agent who intends to construct, enlarge, alter, repair,
move, demolish, or change the occupancy of a building or structure to erect,
install, enlarge, alter, repair, remove, convert, or replace any electrical, gas,
mechanical, or plumbing system, the installation of which is regulated by this
code, or to cause any such work to be done, shall first make application to the
building official and obtain the required permit.” Section 105.1
In addition, the CNMI Administrative Code Title 155-10.1-040 states:

“It shall be unlawful to construct, enlarge, alter, remove or demolish, or change
the occupancy of a building, public or private, from one use group to another,
without first filing an application with the building safety official in writing and
obtaining the required permit therefore, except that ordinary repairs as defined in
Section 155-10.1-005 (d) which do not involve any violation of the Safety Code…”
Examples of when to obtain a permit

Changing the use of a residential home to a restaurant

Constructing a new building

Enlarging/Extending an existing building or existing home

Altering a Means of Egress system (Exit routes)

Repairing structural members/Load bearing members
When does the WHOLE BUILDING have to
come into compliance with the CNMI Building
Safety Code?

There are FOUR ways that the ENTIRE/WHOLE building must comply with the
codes. They are:
1.
When the USE of the building or structure is changed
2.
When the building or structure is INCREASED in FLOOR SPACE OR NUMBER OF
STORIES
3.
When ALTERATIONS OR REPAIRS are made in EXCESS OF 50% of the existing floor
space area in a 12 month period
4.
When ORDINARY REPAIRS EXCEED 25% of the existing floor space area in a 12
month period
1.
Ordinary repairs are not to include additions, alterations, replacement or relocation of
any standpipe, water supply, sewer, drainage, drain leader, gas, soil, waste, vent or
similar piping, electric wiring, or other work affecting public health, safety or welfare.
Many things need a permit,
WHEN DO I NOT NEED A BUILDING PERMIT?

The following are examples of when you do NOT need a permit:

Accessory structures used as sheds, playhouses, or similar uses PROVIDED THE
FLOOR AREA IS NOT GREATER THAN 120 square feet

Fences not over 6 feet

Retaining walls that are not over 4 feet in height measured from the bottom of the
footing to the top of the wall

Water tanks supported directly on grade and capacity is not greater than 5,000
gallons

Painting, tiling, papering, carpeting, cabinets, counter tops, and similar finishes

Swings and other playground equipment

“Structures traditional to the Chamorro or Carolinian cultures, such as pala-palas,
constructed primarily of natural materials indigenous to the Northern Mariana
Islands…”
APPLYING FOR A
BUILDING PERMIT
What do I need to submit?

Application Package

Application

Memorandum of Agreement

Affidavit

Site Map

Payment Voucher


Building permit fee is calculated by a fee schedule which is dependent on the TOTAL
CONSTRUCTION COST of the works to be performed
Additional Requirements

Zoning Permit/Clearance (From Zoning office)

Business License (For Commercial Buildings/Structures)

Lease Agreement (For Leased/Rented property)

Approved design plans (Blueprints)
BSCD Application Procedure

Receive Application Package with additional requirements


Applications must be complete in order to move forward
Application package

Received by BSCD

Blueprints given to Plan Reviewer

All Other documents given to Administrative staff for filing

Blueprints reviewed for compliance and safety check

Assuming everything is complete, in compliance, and fees are paid:

Building Permit issued

Document copies are made and given to owner

Construction may commence


Construction inspections to be scheduled accordingly with rate of construction
Certificate of Occupancy given after final inspection when building or structure is
completely finished
What to expect when application has
been turned in?


One (1) BUILDING SAFETY CODE DIVISION for whole CNMI to take care of:

New and renovated Single Family Homes

New and renovated Multifamily Homes (Apartments, Condos, etc.)

New and renovated Commercial Buildings

Existing Private and Government owned buildings or structures

Safety Inspections for all business in need of Annual Certificate of Occupancy

Inspections of abandoned, dilapidated, unsafe buildings or structures
Turn around time for application (Average):

Small Projects (Minor Renovations):
1-2 weeks

Medium Projects(Major Renovations/New Single Family home) :
2-3 weeks

Large Projects (New Buildings) :
3-4 weeks

Enormous Project (Resorts) :
5-12 weeks
BETTER, STRONGER,
SAFER
CONSTRUCTION
(MITIGATION)
ReCap of Typhoon Soudelor



Category 2 Storm

Sustained winds of about 105 mph

Gust Winds reaching about 215 mph
Effects:

Over 100 power poles down – several months to restore 100% of island wide power

About 160 homes completely destroyed

Over 1,000 homes affected ranging from minor damages to major damages

Island wide green debris, road blockage
Citizens and Residents

Little to no food

Little to no drinking water, general use water

Loss of personal property, financial income

Ration of fuel
How did CNMI homes fare against
Typhoon Soudelor?


Visual Investigation of damaged homes throughout Saipan:

Wood frame homes with corrugated tin:
Major damage – Destroyed

CMU wall homes with wood truss and Corrugated tin roofing: Minor Damage – Major Damage

Reinforced Concrete homes:
Affected – Minor Damage
Detailed damage assessment

Wood eaten by termites, inefficient or lack of bracing, fastener spacing

Lack of plywood sheathing, inefficient roof panel-to-truss connection

Inefficient Truss-to-wall connection, Inefficient Wall-to-floor connection

Large overhangs, lack of soffits, inefficient building envelope enclosure system
Understanding the wind effects on
Homes
Understanding Load Path
Where do I start Building Better,
Stronger, Safer?

Roof System?


Wall System?


CMU (Hollow Block), Wood Frame wall, windows, doors, other openings etc.
Floor Connection System?


Wood Truss, Lateral Truss Bracing, Roof Sheathing, Tin Roof Panels, etc.
Wall to floor connection
Other things to think about

Overhangs, Soffits, Ventilations, lengths, etc.
Start with Building A Better ROOF

Start with the ROOF

Use Washered Roofing Nails with an Annular Ring Shank at least 3 inches in length

Space at 6 inches on center (o.c.) throughout the perimeter of the roof

Space at 12 inches on center
throughout the interior field
Start with the ROOF

Building a better truss system

Make sure at the very least to use 2 x 6 Treated Lumber

2 x 4 Lumber or smaller do not have the structural capacity for the loading conditions in the CNMI
Start with the ROOF

Building a better truss system

Use Metal Connector plates on both sides or ½” Custom
Cut Plywood rather than left over 2x2 lumber

Use metal HURRICANE TIES/STRAPS to connect the roof
system

Ensure that installation is correct

Use the correct fastener (nails or screws) and the
correct number of fasteners

Do not create eccentricities by adding double bottom
chords

Otherwise, connect bottom chords together so that it
becomes one beam

Space the truss systems no further than 4 feet apart
from each other

Space purlins no further than 24 inches apart from each
other


Preferrably 16 inches O.C.
Place a lateral brace on either end of the roof system to
aide with lateral forces
Next, Build Better WALLS

For Wood Frame Walls

Space wall studs no further than 24 inches
on center

Preferrably 16 inches On Center (o.c.)

Place double top plates rather than single
top plates

Install ‘NOGGINS’ or ‘FIREBLOCKING’ in
between all wall studs

Fasten perimeter of ½” or 5/8” plywood,
gypsum board, or cement board at 6
inches o.c.
Next, Build Better WALLS

For Concrete Masonry Walls

Space vertical reinforcements (rebar)
no more than 24 inches on center

Grout all cells with reinforcements

At a minimum, grout every other CMU
cell

Ensure that ALL CMU cells within 24
inches of the corners of masonry walls
are grouted

Ensure that horizontal reinforcements
are placed a minimum of every 3
layers

Ensure that vertical reinforcements
are doweled into the new foundation
slab

A minimum of 4 inches into an existing
foundation slab
Also, create better FLOOR
CONNECTIONS

Ensure that the walls
are securely fastened
to the floor/
foundation slab

Install “J Bolts” of at
least 1/2 inch at a
maximum of 6 feet
on center


“J Bolts” must be
securely fastened
within
the
concrete slab or
wall footing
Use
HURRICANE
TIES/STRAPS
to
secure walls to floor
How else can I Build Better, Stronger,
Safer?

Make sure to follow the Manufacturer Installation guides

Do not retrofit or alter installation

If possible, purchase TYPHOON SHUTTERS in order to protect openings such
as windows and doors

Shorten the span of the overhang

6 – 12 inches is ideal

Ensure that the underside of the overhang (soffit) is enclosed with the proper
fire rated material

Request the help and advice of the Building Safety Code Division even when it
is not required
INFORMATION FOR
THE FUTURE

Typhoon Shelter plans (Professionally engineered) available for the charge of
copies (less than $20) at BSC office

Currently 2 available house plans (Basic Designs-load compliant) available for
the charge of copies at BSC office

Planning for 6 more house plans to be made available with 2-3-4 bedrooms,
professionally engineered

Working with hardware stores to bring in new material, technology, and
required construction hardware

Outreach to community on better, stronger, safer will commence in the near
future


Outreach to all villages on different days for the purpose of educating
homebuilders on better building practices
Be sure to inform Building Safety Code Division of any works to be performed
prior to commencing work
Building Safety Code Division

2ND FLOOR JOETEN OLEAI COMMERCIAL BUILDING

OFFICE HOURS: 7:30AM – 4:30PM, MON – FRI

Tel. (670) 234 – 2726 / 2296

Fax. (670) 235 - 2732

[email protected]
Thank you.
QUESTIONS??