Download Fast tracking

Survey
yes no Was this document useful for you?
   Thank you for your participation!

* Your assessment is very important for improving the workof artificial intelligence, which forms the content of this project

Document related concepts

Earned value management wikipedia , lookup

Construction management wikipedia , lookup

PRINCE2 wikipedia , lookup

Transcript
Chapter 6:
Project Time Management
IT Project Management, Third Edition
Chapter 6
1
Importance of Project Schedules
• Managers often cite delivering projects on time as
one of their biggest challenges
• Average time overrun from 1995 CHAOS report
was 222%; improved to 163% in 2001 study
• Time has the least amount of flexibility; it passes
no matter what
• Schedule issues are the main reason for conflicts
on projects, especially during the second half of
projects
IT Project Management, Third Edition
Chapter 6
2
Project Time Management
Processes
• Project time management involves:
–
–
–
–
–
Activity definition
Activity sequencing
Activity duration estimating
Schedule development
Schedule control
IT Project Management, Third Edition
Chapter 6
3
Activity Sequencing
• Involves reviewing activities and determining
dependencies
– Mandatory dependencies: inherent in the nature of
the work; hard logic
– Discretionary dependencies: defined by the project
team; soft logic
– External dependencies: involve relationships
between project and non-project activities
• You must determine dependencies in order to
use critical path analysis
IT Project Management, Third Edition
Chapter 6
4
Project Network Diagrams
• Project network diagrams are the preferred
technique for showing activity sequencing
• A project network diagram is a schematic
display of the logical relationships among, or
sequencing of, project activities
IT Project Management, Third Edition
Chapter 6
5
Figure 6-2. Sample Activity-on-Arrow
(AOA) Network Diagram for Project X
IT Project Management, Third Edition
Chapter 6
6
Figure 6-3. Task Dependency Types
IT Project Management, Third Edition
Chapter 6
7
Sample PDM Network Diagram
IT Project Management, Third Edition
Chapter 6
8
Activity Duration Estimating
• After defining activities and determining their
sequence, the next step in time management is
duration estimating
• Duration includes the actual amount of time
worked on an activity plus elapsed time
• Effort is the number of workdays or work
hours required to complete a task. Effort does
not equal duration
• People doing the work should help create
estimates, and an expert should review them
IT Project Management, Third Edition
Chapter 6
9
Schedule Development
• Schedule development uses results of the other
time management processes to determine the
start and end date of the project and its
activities
• Ultimate goal is to create a realistic project
schedule that provides a basis for monitoring
project progress for the time dimension of the
project
• Important tools and techniques include Gantt
charts, PERT analysis, critical path analysis,
and critical chain scheduling
IT Project Management, Third Edition
Chapter 6
10
Sample Tracking Gantt Chart
IT Project Management, Third Edition
Chapter 6
11
Critical Path Method (CPM)
• CPM is a project network analysis technique
used to predict total project duration
• A critical path for a project is the series of
activities that determines the earliest time by
which the project can be completed
• The critical path is the longest path through
the network diagram and has the least amount
of slack or float
IT Project Management, Third Edition
Chapter 6
12
Simple Example of Determining
the Critical Path
• Consider the following project network
diagram. Assume all times are in days.
C=2
start
1
A=2
2
B=5
4
E=1
3
6
D=7
5
finish
F=2
a. How many paths are on this network diagram?
b. How long is each path?
c. Which is the critical path?
d. What is the shortest amount of time needed to
complete this project?
IT Project Management, Third Edition
Chapter 6
13
Figure 6-8. Determining the
Critical Path for Project X
IT Project Management, Third Edition
Chapter 6
14
More on the Critical Path
• If one or more activities on the critical path takes
longer than planned, the whole project schedule
will slip unless corrective action is taken
• Misconceptions:
– The critical path is not the one with all the critical
activities; it only accounts for time. Remember the
example of growing grass being on the critical path
for Disney’s Animal Kingdom Park
– There can be more than one critical path if the lengths
of two or more paths are the same
– The critical path can change as the project progresses
IT Project Management, Third Edition
Chapter 6
15
Using Critical Path Analysis to
Make Schedule Trade-offs
• Knowing the critical path helps you make schedule tradeoffs
• Free slack or free float is the amount of time an activity
can be delayed without delaying the early start of any
immediately following activities
• Total slack or total float is the amount of time an activity
may be delayed from its early start without delaying the
planned project finish date
• A forward pass through the network diagram determines
the early start and finish dates
• A backward pass determines the late start and finish dates
IT Project Management, Third Edition
Chapter 6
16
Techniques for Shortening a
Project Schedule
• Shorten durations of critical tasks by adding
more resources or changing their scope
• Crashing tasks by obtaining the greatest amount
of schedule compression for the least
incremental cost
• Fast tracking tasks by doing them in parallel or
overlapping them
IT Project Management, Third Edition
Chapter 6
17
Crashing and Fast Tracking
Original
schedule
Shortened
duration thru
crashing
Overlapped
Tasks or fast
tracking
IT Project Management, Third Edition
Chapter 6
18
Many Horror Stories Related to
Project Schedules
• Creating realistic schedules and sticking to them
is a key challenge of project management
• Crashing and fast tracking often cause more
problems, resulting in longer schedules
• Organizational issues often cause schedule
problems.
IT Project Management, Third Edition
Chapter 6
19
Controlling Changes to the
Project Schedule
• Perform reality checks on schedules
• Allow for contingencies
• Don’t plan for everyone to work at 100%
capacity all the time
• Hold progress meetings with stakeholders and
be clear and honest in communicating schedule
issues
IT Project Management, Third Edition
Chapter 6
20