Survey
* Your assessment is very important for improving the workof artificial intelligence, which forms the content of this project
* Your assessment is very important for improving the workof artificial intelligence, which forms the content of this project
INFO5990 Professional Practice in IT Project Monitoring using Earned Value 1. Monitoring and Controlling A key role of the project manager (see PMBOK) is monitoring and controlling. To accomplish this it is helpful to idenitify variables called ‘key perfomance indicators’ (KPI). By monitoring the value of these indicators over time the manager can quickly carry out a ‘health check’ of the project to assertain whether or not it was on track. 2. Key performance indicators A popular method used for monitoring prject progress is called “Earned Value Management”. The basic performance variable chosen is called Earned Value. Three key values are calculated for each activity: The budget, also called the budgeted cost of work scheduled (BCWS), is that portion of the approved cost estimate planned to be spent on the activity during a given period. The actual cost, also called the actual cost of work performed (ACWP), is the total of direct and indirect costs incurred in accomplishing work on the activity during a given period. The earned value, also called the budgeted cost of work performed (BCWP), the proportion of the total budget represented by the work actually completed. Some managers use only 0 percent or 100 percent (done or not done) in determining earned value performance. Two key performance indicators are used to monitor progress, the cost performance index (CPI) and the schedule performance index (SPI). Table 1 defines all of the variables used in Earned Value management. Table 1 Variable Formula Explanation Planned value (PV) (“The budget”) PV= amount of Total budget intended to be performed by current date Earned value (EV) EV = amount of budgeted work completed so far Actual cost (AC) AC = Sum of costs incurred to date Cost variance (CV) CV = EV – AC Schedule variance (SV) SV = EV – PV Cost performance index (CPI) CPI = EV/AC Schedule performance index (SPI) SPI = EV/PV Estimate at completion (EAC) EAC = Original budget estimate / CPI The $ value of that fraction of the approved total cost estimate planned to be completed by the current date. PV used to be called “Budgeted Cost of Work Scheduled” (BCWS). An estimate of the $ value of the physical work actually completed by the current date. EV used to be called “Budgeted Cost of Work Performed” (BCWP).. The total $ value of all direct and indirect costs incurred in accomplishing the work done to date. AC used to be called “Actual Cost of Work Performed” (ACWP). Difference between the budgeted cost of work performed to date and the cost of the work actually performed. Difference between the budgeted cost of work performed to date and the cost of the work scheduled to be performed. Key performance indicator with regard to cost. Less than 1 is ‘bad’ (budget over spent) Key performance indicator with regard to schedule. Less than 1 is ‘bad’ (behind schedule) Estimate of eventual cost at the present rate of spending. Estimated time to complete (ETC) ETC = Original time estimate / SPI Week 5 Estimate of when the project will finally be completed if current rate of progress is maintained. G Kennedy, 2012 INFO5990 Professional Practice in IT 3. A simple example of project management In this example, there is only 1 resource and a fixed timeline. You can therefore assume that Effort = Schedule and Effort = Cost, which is rather simpler than the previous case. Suppose you are sitting a 2 hour examination consisting of 40 questions in this exam, each question has an equal value. You must answer every question. Consider how you can monitor your performance? First you should establish a budget for each question. Say you need to set aside 20 minutes at the end, 10 minutes for review and 10 minutes for contingency. So budget is 100 / 40 = 2.5 minutes per question. Now after 20 minutes has passed, you find you have completed 7 questions. Are you ahead or behind schedule? Do you need to take remedial action? Earned Value (EV) = 7 questions x 2.5 minutes = 17.5minutes Planned Value (PV) = 20 minutes (i.e. the budgeted amount of work performed after 20 minutes) Performance Variance (PV) = EV – PV = 17.5 - 20 = -2.5 minutes SchedulePerformaceIndex (SPI) = EV/PV = 17.5 / 20 = 0875 This tells you that you are currently behind schedule. You may think that you will finish the remaining 33 questions in 33 × 2.5 = 82.5 minutes, but this would not take into account the fact that the first 7 questions took longer than expected per question (2.86 minutes per question). So, since you have completed 7 questions in 20 minutes, it is safer to use this new productivity figure (20/7 minutes per question) to estimate future work on the project. Time to complete the remaining 33 question you should allow (33 × 20/7) + 20 for checking = 114.29 minutes Estimate at Completion (EAC) = 20 + 114.29 = 134.29 minutes, which is more than 14 minutes over time and over budget. 4. Using Key Performance Indicators to monitor project progress Table 2 illustrates how earned value calculations can be used to monitor the progress of a project. Let us suppose that the project has a total budget of $100,000 and is expected to be completed in 10 weeks. For simplicity suppose that the work breakdown structure is made up of ten equal sized “tasks” and that each task represents a tenth of the work budgeted. Let us say that each week we expect to complete one task, so that the planned value (PV) of the project will be exactly $10,000 each week. Now consider the calculations shown in Table 2 which represent the state of the project at the end of Week 1 and Week 2. As expected the planned value will be $10,000 and $20,000 respectively. Table 2 Earned Value Calculations Variable Week 1 Week 2 Planned Value (PV) at this date $10,000 (Task 1 finished) $20,000 (Tasks 1 and 2) Earned Value (EV) so far $7,500 (say 75% complete) $22,000 (Tasks 1 and 2, and 20% of Task 3 completed) Actual Cost (AC) so far $12,000 (salaries plus a new computer) $23,000 (salaries plus other sundry costs) Cost Variance (CV) EV – AC = -$4,500 EV – AC = -$3,000 Schedule Variance (SV) EV – PV = -$2,500 EV – PV = +$2,000 Cost Performance Index (CPI) EV/AC = 0.625 EV/AC = 0.956 Schedule Perfomance Index (SPI) EV/PV = 0.75 EV/PV = 1.10 Estimate at completion (EAC) 100,000/0.625 = $160,000 100,000/0.956 = $104,545 Estimated time to complete (ETC) 10 / 0.75 = 13.3 weeks 10 / 1.10 = 9.09 weeks Position at the end of Week 1 Suppose that Task 1 is only 75% complete, so that the Earned Value (EV) is only $7,500, but that due to circumstances the cost of achieving this is $12,000. Then as can be seen in the centre column, both the cost and schedule variances are negative, and both the cost performance index (CPI) and schedule performance index Week 5 G Kennedy, 2012 INFO5990 Professional Practice in IT (SPI) are less than one, indicating that the project is running over cost and behind schedule. If things continue as they are the project will run $60,000 over budget (EAC) and more than three weeks over time (ETC). In the light of the position at the end of the first week we can assume that the project manager will investigate matters. He may find that there are less resources are available than planned, or some staff have taken unplanned time off due more illness, or that resources have arrived late or that the project team is less efficient than had been thought. This may lead to some remedial action being taken to get the project back on track. Position at the end of Week 2 Suppose that by the end of Week 2 both Tasks 1 and 2 and 20% of Task 3 have been completed, giving an Earned Value (EV) of $22,000. Suppose actual costs so far total $23,000. The right hand column now shows us that the cost variance is negative and the cost performance index (CPI) is less than one, but closer to one than it was, so the project is closer to budget than the previous week, but will still run over budget if nothing else changes (EAC). On the other hand, the schedule variance is positive, and the and schedule performance index (SPI) is greater then one, so the remedial action has been effective and the project mat well be finished ahead of schedule (ETC). The graph lines in Figure 1 illustrate the position in the project described above at the end of the fourth week, assuming an Earned Value and Actual Cost of $38,000 and $45,000 respectively. The project appears to be still slightly over budget and. behind schedule. Figure 1 Earned Value Chart Estimate at Completion (EAC) = $118,421 at 10.5 years 120000 100000 $ Value 80000 Planned value (PV) 60000 Actual Cost (AC) 40000 Earned value (EV) 20000 0 1 2 3 4 5 6 7 8 9 10 Period Week 5 G Kennedy, 2012 INFO5990 Professional Practice in IT 5. Preparing a budget Table 3 shows how a budget can be prepared for a project that will use each of the resources listed to the extent shown in the table. Next, unit rates can be used to determine the cost of these resources. Project Management 3 5 5 5 Design 10 10 15 15 5 5 5 3 5 5 5 5 5 BUDGET 24-Jun 17-Jun 10-Jun 3-Jun 27-May 20-May 13-May 6-May 29-Apr 22-Apr 8-Apr 15-Apr Table 3 2 53 Project Manager 50 Analyst + Exp User + Trg Dev Build 15 15 5 10 10 20 45 2 Programmers + Trg Dev Test 25 25 25 115 Analyst + Exp User +Trg Dev +2 Programmers Communication 2 2 User Acceptance 3 7 Project Manager 10 10 20 Analyst + Exp User 290 Days Testing Days 15 15 25 25 30 30 30 30 30 30 15 15 People 3 3 5 5 6 6 6 6 6 6 3 3 6. Project status report template Figure 2 below, is an example of a pro-forma for a routine project report. Figure 2 Week 5 G Kennedy, 2012 INFO5990 Professional Practice in IT 7. Earned Value calculations and performance indicators Table 3 (over page) shows a spreadsheet for recording actual cost (AC) and determining earned value for a project with a duration of twelve months. Note that the figures for the months July to November are hidden simply to save space on the page. The spreadsheet represents the position at the end of the fifth month (May). The figures in the first seven rows and twelve columns (only seven visible) represent ‘the budget’ or planned value (PV) for each of the seven tasks over the twelve month period. The planned value summed month by month is shown in the “Monthly Planned Value (PV)” row, and the cumulative total in the row below that. At the right hand end of the table, the column “To Date Planned Value” replicates the planned value amounts, this time summed by task. The key row in the table is “Monthly Actual Cost (AC)”, which gives the actual costs recorded for the project month by month. These figures come from such accounting records as invoices, cheques and salary details. The cumulative total of these ‘actuals’ is given in the row below. To the far right of the table, the values in the column “Planned % complete” represent the % of each task that according to the project schedule should have been completed by the end of May. The next column, “Actual % complete” is the key column. It contained estimates of % of each task actually complete at the end of May. The project manager has to assess these figures by examining the work actually done and comparing with the specifications of the respective tasks, for example by estimating what proportion of a program or prototype system has been completed, or the extent to which testing is finished. At the extreme right of the table are two columns headed “Earned Value”. The first of these is headed RP (Rate of Performance) and is the ratio of actual % work completed to planned % work completed 1. Thus, for Task 7 of this project, RP = 50%/75% = 0.5/0.75 = 0.6667. The second column headed EV represents the earned value of the work complete. In this example it was planned to complete 75% of Task 7 (planned value $8,000) by the end of May, but this work was actually only 50% complete, so the earned value (EV) is 66.667% of $8,000 = $5,333 ( final column). Once these figures have been entered into the spreadsheet it is possible to calculate a number of “Key performance indicators” (KPI) that can be used by the project manager to determine at glance whether the project is on track or behind schedule. The three rows labelled Earned Value (EV), Planned Value (PV) and Actual Cost (AC) “…to monthend” simply replicate rows above and are included for convenience only. The rows Cost Variance (EV-AC) and Schedule Variance (EV-PV) indicate “on track” if positive, behind schedule if negative. The rows Cost Performance Index (EV/AC) and Schedule Performance Index (EV/PV) indicate “on track” if values 100% or greater behind schedule if less than 100%. The two final rows showing “Estimated Cost at Completion” and “Estimated Time to Completion” give the project manager a feel for the likely outcome if nothing is done and the project continues at the present rate. Clearly if it is behind schedule the possibility of remedial action should be considered. It is possible that any ‘bad’ performance figures could be the result of random variations (‘hiccups’) rather than a major trend, in which case the project may ‘come right’ by itself. One rule of thumb is the “seven run rule”, which says that is seven successive data points are above or below the mean then it is unlikely to be due to random variation. By making use of earned value calculations such as those shown here the project manager is in a good position to take action if necessary before the project is too far behind schedule. Figure 1 (over page) show the Earned Value Chart. It can that “Actual Costs” are slowly climbing away from the budget line and “Earned Value” is slipping below, so that the project can be expected to end up over budget and behind schedule. 1 This is an sophistication proposed by Brenda Taylor, who suggested that earned value (EV) should be calculated as percentage complete only of percentage planned to be complete. Week 5 G Kennedy, 2012 INFO5990 Professional Practice in IT Table 3 Duration (months) Earned Value Calculations - May 12 Activity Jan 1. Plan and staff project 4,000 2. Analyze requirements 3. Develop ERDs 4. Design forms, reports 5. Design database tables 6. Design forms, reports and queries 7. Construct working prototype 8. Test/evaluate prototype 9. Incorporate user feedback 10. User acceptance testing Monthly Planned Value (PV) 4,000 Cumulative Planned Value 4,000 Monthly Actual Cost (AC) 4,000 Cumulative Actual Cost Cumulative Earned Value Project Earned Value (EV) to monthend Project Planned Value (PV) to monthend Project Actual Cost (AC) to monthend Cost Variance (EV - AC) Schedule Variance (EV - PV) Cost Performance Index (EV/AC) Schedule Performance Index (EV/PV) Estimated Cost at Completion (Planned Cost/CPI) Estimated Time to Completion (Planned Time/SPI) Week 5 To date Feb 4,000 6,000 Mar 6,000 4,000 Apr 4,000 6,000 May Jun 4,000 8,000 4,000 10,000 2,000 10,000 14,000 11,000 10,000 24,000 11,000 10,000 34,000 12,000 12,000 46,000 15,000 53,000 43,333 43,333 46,000 53,000 -9,667 -2,667 81.76% 94.20% 16,000 62,000 ... ... ... ... ... ... ... ... ... ... ... 0 ## 122,308 … 12.74 … Dec 1,000 4,000 5,000 100,000 G Kennedy, 2012 Plan Val. 8,000 12,000 8,000 10,000 8,000 Planned % Compl. 100 100 100 100 75 Actual % Compl. 100 100 100 100 50 Earned Value RP 100% 100% 100% 100% 67% EV 8,000 12,000 8,000 10,000 5,333 43,333 INFO5990 Professional Practice in IT Figure 2 Earned Value Chart 90,000 80,000 70,000 Value ($) 60,000 50,000 Earned Value Actual Cost Planned Value 40,000 30,000 20,000 10,000 0 1 2 3 4 5 6 7 8 Month Week 5 G Kennedy, 2012 INFO5990 Professional Practice in IT Week 5 G Kennedy, 2012