Pre-commissioning Checklist
Primary Systems - Substation
Instrument transformers physical checks and tests
Post current transformers; bar primary and current transformers and voltage transformers
Substation
Equipment no.
Manufacturer
Voltage
Rating(s)
Serial no.
Click here to enter text.
Click here to enter text.
Click here to enter text.
Click here to enter text.
Click here to enter text.
Click here to enter text.
Performed by
Service no.
Date
Click here to enter text.
Click here to enter text.
Click here to enter a date.
1. Visual inspection – Post CT and VTs
Action/check
Acceptable criteria
Results
No cracks or defects
Click here to enter text.
All control cables wiring are correctly
labelled
Labelling is correct
Click here to enter text.
Control cabling and terminations are
correctly marked and complete.
Marking is complete and
correct
Click here to enter text.
Check secondary windings of all CTs
connected - Refer to PMI 4110 and
PDI 4003
Correct
Click here to enter text.
Check all cable terminations for tightness
Terminations are tight
Click here to enter text.
Check for any oil leaks (oil filled CTs and VTs).
No oil leaks
Click here to enter text.
Oil level to mark
Click here to enter text.
Terminal marking is complete
and correct
Click here to enter text.
Inspect for cracks or other defects
Check oil level in oil filled current
transformers.
Verify terminal markings are correct
Initials
2. Visual inspection – bar primary and ring CT
Action/check
Acceptable criteria
Results
No cracks or defects
Click here to enter text.
All control cables wiring are correctly
labelled
Labelling is correct
Click here to enter text.
Control cabling and terminations are
correctly marked and complete.
Marking is complete and
correct
Click here to enter text.
Check secondary windings of all CTs
connected - Refer to PMI 4110 and
PDI 4003
Correct
Click here to enter text.
Terminations are tight
Click here to enter text.
Terminal marking is complete
and correct
Click here to enter text.
Inspect for cracks or other defects
Check all cable terminations for tightness
Verify terminal markings are correct
FAE 3406 June 2015
SDI 535
Page 1 of 3
Initials
3. Oil quality and DGA
Action/check
Check manufacturer’s certificate of oil quality
and DGA.
Note: Oil shall be re-tested at site, if the oil
quality is doubtful.
Acceptable criteria
Oil quality in tank is in
accordance with ETS 0009.
Results
Initials
Click here to enter text.
4. Electrical tests – bar primary and ring CT and post CTs
Action/check
Acceptable criteria
Results
Polarity test
(as specified in PMI 4110 and PDI 4003)
Serviceable
Click here to enter text.
Ratio test
(as specified in PMI 4110 and PDI 4003)
Serviceable
Click here to enter text.
Perform magnetising test on CTs
(as specified in PMI 4110 and PDI 4003)
Serviceable
Click here to enter text.
Acceptable criteria
Results
against primary busbar phasing.
As specified in PMI 4110 and PDI 4003
Serviceable
Click here to enter text.
Polarity test
Serviceable
Click here to enter text.
Ratio test
Serviceable
Click here to enter text.
Record results
Click here to enter text.
Initials
5. Electrical tests – VTs
Action/check
Initials
Voltage phasing - Identify phasing of VTs
Measure resistance primary and secondary
fuses
6. Functional checks for all types of CTs and VTs
Action/check
Acceptable criteria
Results
Serviceable
Click here to enter text.
Action/check
Acceptable criteria
Results
Perform power-frequency withstand voltage of
2kV for 1 min, given as follows:

All new wiring installed at site.

All wiring not tested for PFWV in factory.

All wiring disconnected and removed for
transport.
Note: If wiring has to be taken off or if electronic
devices are in circuits, these circuits shall not be
tested).
No disruptive discharge
Click here to enter text.
Check functionality of all associated
electrical circuits as specified in PMI 4110
and PDI 4003
Initials
7. Electrical tests – VTs
FAE 3406 June 2015
SDI 535
Page 2 of 3
Initials
Conducted/
tested/inspected
by and sign
FAE 3406 June 2015
Service no.
Witnessed by
and sign
SDI 535
Service no.
Reviewed/
reported by
and sign
Service no.
Page 3 of 3