Survey
* Your assessment is very important for improving the work of artificial intelligence, which forms the content of this project
* Your assessment is very important for improving the work of artificial intelligence, which forms the content of this project
Department of Minerals and Energy South Africa Danish Cooperation for Environment and Development (DANCED), Denmark BULK RENEWABLE ENERGY INDEPENDENT POWER PRODUCERS IN SOUTH AFRICA January 2001 Preface This report presents the findings of a project entitled “Independent Power Production (IPP) in South Africa with an Emphasis on Bulk Electricity Generated through the Harnissing of Renewable Energy Sources”. The project was carried out in 2000 for the Department of Mines and Energy (DME), South Africa, and the Danish Cooperation for Environment and Development (DANCED), Denmark. DANCED and DME agreed on this activity in order to identify barriers to the use of grid connected renewables for bulk power production and to suggest means that the DME could use to remove these barriers. It was DANCED and DME’s intention to thus support the energy policy direction laid out in the White Paper on Energy Policy of December 1998. The team comprised: Dr Jorgen Boldt, Ramboll (Team Leader from July 2000) Mr Jorgen Hvid, Ramboll (Team Leader until July 2000) Mr Lars Monsted, Ramboll Dr Terry Olier, IEEC, Thailand Ms Alix Clark, EDRC, University of Cape Town Mr Justice Mavhungu, EDRC, University of Cape Town Mr Anton-Louis Olivier, e3, Cape Town Dr Douglas Banks, RAPS, Pretoria Mr Jason Schäffler, RAPS, Pretoria Mr Frank Hochmuth, MEPC, Cape Town Mr Steve Thorne, Energy Transformations, Cape Town Disclaimer: Views or opinions of the authors expressed herein do not necessarily confirm or reflect those of the DME or Danced Table of contents Summary ........................................................................................................................ 7 1. Background .............................................................................................................. 29 1.1. The Rationale ..................................................................................................... 29 1.1.1. Economic and social development .............................................................. 29 1.1.2. Environmental benefits ............................................................................... 30 1.1.3. Justification for preferential status .............................................................. 31 1.2. Background to Project ....................................................................................... 32 2. South African energy policy and renewable IPPs.................................................... 34 2.1. A historical review............................................................................................. 35 2.1.1. Pre-regulations ............................................................................................ 35 2.1.2. First power act ............................................................................................. 35 2.1.3. Establishment of Eskom .............................................................................. 36 2.1.4. Monopoly of Eskom .................................................................................... 36 2.1.5. First restructuring of Eskom ........................................................................ 36 2.1.6. Post-Apartheid era: NER founded .............................................................. 36 2.1.7. Splitting up of Eskom.................................................................................. 37 2.2. South African Energy Policy ............................................................................. 37 2.3. Renewable energy policy................................................................................... 38 2.3.1. The Energy White Paper ............................................................................. 38 2.3.2. Renewable energy according to the Energy White Paper ........................... 39 2.3.3. The renewable energy strategy of the DME................................................ 40 2.3.4. Non-utility generation ................................................................................. 41 2.4. The international Framework Convention on Climate Change ......................... 42 2.4.1. South Africa’s position towards climate change ......................................... 42 2.4.2. State of the art of the CDM mechanism ...................................................... 44 2.4.3. The potential role of the CDM in the promotion of renewables ................. 45 2.4.4. CDM benefits for renewable IPPs ............................................................... 45 2.4.5. Requirements to policy framework and regulatory framework .................. 46 2.5. Policy barriers and deficits ................................................................................ 47 3. Legal, institutional and regulatory set-up of the power sector................................. 50 3.1. Overview ........................................................................................................... 50 3.1.1. Governance structure................................................................................... 50 3.1.3. ESKOM governance ................................................................................... 53 3.2. The restructuring of the electricity supply industry........................................... 54 3.2.1. Government’s plans for power sector reform ............................................. 54 3.2.2. Possible impacts of EDI reform on bulk renewable energy generation ...... 63 3.2.3. Possible impacts of ESI reform on bulk renewable energy generation....... 64 3.3. Stakeholders....................................................................................................... 69 3.3.1. Government ................................................................................................. 69 3.3.2. State-owned and companies and municipalities.......................................... 70 3.3.3. Commercial Companies .............................................................................. 70 3.3.4. Regulatory bodies ........................................................................................ 71 3.3.5. NGOs and research organisations ............................................................... 71 3.3.6. Unions ......................................................................................................... 72 3 3.4. Present legal and regulatory deficits .................................................................. 72 3.4.1. Regulation of access to electricity markets and customers ......................... 73 3.4.2. Guidelines for access to grid ....................................................................... 74 3.4.3. Establishment and enforcement of wheeling rules and tariffs .................... 74 3.4.4. Control of ownership issues by the competition board ............................... 74 3.4.5. Renewable energy Power Purchase Agreements ........................................ 74 4. Renewable energy resources .................................................................................... 76 4.1. Renewable energy technologies suitable for independent power producers ..... 76 4.1.1. Introduction ................................................................................................. 76 4.1.2. Wind ............................................................................................................ 76 4.1.3. Biomass ....................................................................................................... 77 4.1.4. Hydro........................................................................................................... 77 4.1.5. Solar ............................................................................................................ 78 4.2. Comparison of renewable energy technologies for suitability as IPPs ............. 79 4.3. Renewable energy resource assessment ............................................................ 80 4.3.1. Background ................................................................................................. 80 4.3.2. Wind ............................................................................................................ 81 4.3.3. Biomass ....................................................................................................... 82 4.3.4. Hydro........................................................................................................... 85 4.4. Resources with potential for the future.............................................................. 88 4.4.1. Solar ............................................................................................................ 88 4.4.2. Wave Energy ............................................................................................... 89 4.4.3. Energy from Waste...................................................................................... 89 5. Non utility experiences in South Africa................................................................... 90 5.1. Background ........................................................................................................ 90 5.2. Existing non-utility generators .......................................................................... 91 5.2.1. Small hydropower ....................................................................................... 91 5.2.2. The sugar industry ....................................................................................... 95 5.2.3. The wood and pulp industries ..................................................................... 96 5.2.4. Non-renewable generators........................................................................... 98 5.3. Renewable energy IPPs under development ..................................................... 99 5.3.1. Darling Independent Power Producer (DARLIPP) ..................................... 99 5.3.2. Bethlehem Hydro ...................................................................................... 104 5.3.3. Krokodilpoort hydro .................................................................................. 108 5.3.4. Other .......................................................................................................... 108 5.4. Barriers and other factors influencing IPP development in South Africa ....... 111 5.4.1. Conflicting messages................................................................................. 111 5.4.2. Tariffs ........................................................................................................ 111 5.4.3. Project developer profile ........................................................................... 112 5.4.4. Demand for generation capacity ............................................................... 112 5.4.5. Stranded Assets ......................................................................................... 113 5.4.6. Power purchase agreements ...................................................................... 113 5.4.7. Financing: Equity ...................................................................................... 114 5.4.8. Financing: Debt ......................................................................................... 114 5.4.9. Concessionary and venture finance ........................................................... 115 4 6. Financial and economic evaluation of renewable energy ...................................... 117 6.1. Introduction ..................................................................................................... 117 6.2. Financial aspects .............................................................................................. 117 6.3. Real cost of coal-fired power generation ......................................................... 118 6.3.1. Direct costs ................................................................................................ 118 6.3.2. Electricity tariffs ........................................................................................ 122 6.3.3. Subsidies and cross-subsidies.................................................................... 123 6.4. Externalities ..................................................................................................... 124 6.4.1. Direct accountable externalities ................................................................ 125 6.4.2. Indirect and global externalities ................................................................ 126 6.4.3. Total production costs of coal based energy ............................................. 127 6.4.4. Total production costs without subsidies and with externalities. .............. 127 6.5. Real costs of REIPPs ....................................................................................... 128 6.5.1. Mini hydro systems ................................................................................... 128 6.5.2. Industrial bagasse ...................................................................................... 129 6.5.3. Wind power ............................................................................................... 130 6.6. Comparison of costs ........................................................................................ 132 6.7. Power purchase regulation for distributed generators ..................................... 133 6.8. Employment aspects ........................................................................................ 137 7. Review of International Renewable Energy Policies............................................. 139 7.1. Introduction ..................................................................................................... 139 7.2. Incentives ......................................................................................................... 139 7.2.1. Production Incentives ................................................................................ 141 7.2.2. Investments subsidies ................................................................................ 142 7.2.3. Set-asides ................................................................................................... 142 7.2.4. Green marketing. ....................................................................................... 144 7.2.5. Power purchase agreements. ..................................................................... 145 7.2.6. Loan guarantees......................................................................................... 145 7.3. International Initiatives .................................................................................... 146 7.4. Country Experiences with Grid-Connected Renewable Energy Policies ........ 147 7.4.1. Denmark .................................................................................................... 147 7.4.2. Germany .................................................................................................... 148 7.4.3. India........................................................................................................... 149 7.4.4. Netherlands................................................................................................ 150 7.4.5. Spain .......................................................................................................... 151 7.4.6. Sweden ...................................................................................................... 151 7.4.7. United Kingdom (UK) .............................................................................. 151 8. Recommendations .................................................................................................. 154 8.1. Policy and legislation – immediate initiatives ................................................. 155 8.1.1. Recommendation 1: Renewable energy IPP set-aside programme ........... 155 8.1.2. Recommendation 2: Interim power purchase regulation .......................... 157 8.2. Policy and legislation – longer term initiatives ............................................... 158 8.2.1. Recommendation 3: Power purchase regulation. ...................................... 158 8.2.2. Recommendation 4: IRP inclusion of renewable energy IPPs .................. 158 8.2.3. Recommendation 5: Electricity information ............................................. 159 8.2.4. Recommendation 6: Capacity development, government......................... 159 8.2.5. Recommendation 7: Capacity development, civil society ........................ 160 8.3. Regulation – tariffs and grid connection ......................................................... 160 5 8.3.1. Recommendation 8: Transparent licensing. .............................................. 160 8.3.2. Recommendation 9: Technical grid connection code ............................... 161 8.3.3. Recommendation 10: Renewable energy tariff structure .......................... 162 8.4. Support activities ............................................................................................. 163 8.4.1. Recommendation 11: Long term barrier removal. .................................... 163 8.4.2. Recommendation 12: Investment capital for renewable energy ............... 163 8.4.3. Recommendation 13: Green power marketing.......................................... 164 8.5. Demonstration activities .................................................................................. 165 8.5.1. Recommendation 14: The Darling Wind Farm ......................................... 165 8.5.2. Recommendation 15: Mini-hydro ............................................................. 166 8.5.3. Recommendation 16: Cogeneration in sugar industry. ............................. 166 8.5.4. Recommendation 17: Cogeneration in wood/pulp industry...................... 166 6 SUMMARY There are significant benefits in diversified and small scale additions to the generation mix in improved quality of supply, diversification, better following the demand growth, technical (voltage relief etc), local job creation, and contributes to clean up the energy sector. Renewable energy technologies have proven their ability to provide grid power both in South Africa and internationally. South Africa is purposefully moving toward competition in the generation sector. In the South African regulatory regime, distinction must be made between different classes of independent power producers, which require different regulatory frameworks: large scale, green field, brown field and small scale (mostly renewable energy). We propose creating an annual window of about 200 MW for 5 years. The window would specifically target renewable energy independent power producers to sell into the grid at competitive prices under a temporary regulatory framework that takes into account the unique requirements of small IPPs such as: easy and appropriate grid access, known and cost based wheeling charges, and power purchase agreements. THE RATIONALE Renewable energy sources are environmentally clean sources with additional economic and social benefits. They have received considerable and growing attention around the world the last two decades, initially because they have strong potential for mitigating environmental impacts from electricity generation. The so-called bulk renewable energy independent power producers, delivering electricity to the national grids, are the focus of the present report. Economic and social development Renewable energy resources can be an important part of economic and social development strategies. If appropriate market conditions are created to ensure essential penetration of renewable energy technologies, most of the equipment may be produced in South Africa. The world market is rapidly increasing, so there is a large export potential. The possible impact on macro economy and employment is substantial. At the same time, many exporting South African companies have come under pressure from their overseas clients regarding environmental issues. The issue of employment is found important in many countries. Although no calculations have been made specific to South Africa, the following table summarises studies done elsewhere and shows the potential job creation benefits of a renewable energy strategy, when compared to either coal or nuclear power stations. 7 Resource Coal fired power plant Photovoltaics Solar thermal electricity Wind-generated electricity Biomass-derived electricity Hydro-derived electricity Information Source New York State American Wind Energy Ass. Danish Study World Watch Institute [man-years, same amount of energy] [jobs per mil. US$ invest.] [jobs per mil. US$ invest.] [jobs per TWh] 6,200 13.1 7.4 13 116 14,200 10.0 14 248 542 17.0-22.6 4.0 8 As many renewable energy technologies by nature are generating intermittent electricity, they are best suited for grid-connected electricity generation, so that the grid can function as back up in periods with low or no generation. Some renewable energy technologies are also suited for off-grid electricity supply, e.g. in hybrid mini-grids. A hybrid system is a combination of at least two different generators, one being intermittent (solar, wind), the other being firm (diesel, hydro). The latter functions as back up for the former and will therefore often be idle. The intermittent source usually has high initial costs and low operational costs. Because of the redundant capacity the total investment in a hybrid system is high. For this reason, private investors are unlikely to invest in such systems. Introduction of on-grid renewable independent power producers would help increase the prospects for off-grid solutions. As many technological and non-technological aspects are equivalent, a higher market volume for these technologies will encourage a larger number of investors and manufacturers. This will increase competition and in turn imply lower prices. The combined higher market volume of on-grid and mini-grid technologies will also imply that the critical volume for manufacturing the equipment in South Africa will be reached at an earlier stage. Furthermore, a larger market will strengthen the incountry technological support (education, operation and maintenance, availability of spare-parts etc.). All in all, by combining on-grid and mini-grid developments, the job creation potential is considerably improved. Environmental benefits Renewable energy technologies have undisputed positive impacts on local environments. More recently the interest has also been driven by a global effort to mitigate climate change. In 1997 South Africa ratified the international Framework Convention on Climate Change, one of the outcomes of the Earth Summit in Rio de Janeiro in1992 on sustainable development. A follow-up summit, the so-called ‘Rio+10 Summit 2002’, has been scheduled. South Africa has invited the United Nations to host this event. 8 In his invitation, Minister of Environmental Affairs and Tourism, Mr Mohammed Valli Moosa, stated: “Our planet is suffering from a depletion of non-renewable natural resources. The loss of biodiversity, the unravelling of ecosystems, pollution of scarce water resources and the very air that we breathe, deteriorating health, climate changes as a result of global warming, and the corresponding threat to food production and the life in the sea are concerns that we all share.” Of South Africa’s total emissions of greenhouse gasses, 38% is attributed to electricity generation. A sustainable energy strategy addressing this challenge necessarily involves renewable energy and energy efficiency. International mechanisms are now being developed to facilitate the transfer of investments from industrialised countries to developing countries in renewable energy and related technologies. Foreign investors are already looking for project opportunities in South Africa. Justification for preferential status The justification for introducing policies favouring renewable energy can be defined at two levels, creating a level playing field and assigning special status. Currently the comparison between renewable energy and conventional generation is unfair because the environmental costs of conventional generation are not fully accounted for, neither in the future planning of resources nor in current pricing of generation output. In addition comparisons are often made between renewable energy generation and current electricity tariffs, instead of comparing the total costs of future generating resources. First of all, an equal level playing field has to be established. An equal level playing field consists of several components: Economy Renewable energy must be given equal economic opportunities. Some of the competing energy sources are often subsidised. All energy sources should be compared economically using the same standards, e.g. a market based economy without any economic incentives and disincentives (subsidies, taxes, tax exemptions etc.). Finance Traditional power utilities, by virtue of being well established, usually have ready access to less costly finance (low interest, long maturity), whereas typical renewable energy owners only can obtain much more expensive finance. Access to market The electricity grid is the market place. Renewable Energy should have at least the same access to the grid as other energy sources. The challenge is to develop a mechanism for grid connection, which is acceptable for both the seller and the buyer. 9 Organisation Traditional power plant operators are usually big corporations. They are very experienced and they can afford to acquire extra technical, economic, financial, and legal expertise. Small owners often cannot afford to acquire much expertise. By taking up a strong international IPP developer or utility as partner renewable energy independent power producers can compete on equal footing. The policy choice as to whether to provide additional support is in some cases related to whether the government wants small local enterprises to be able to enter this market or whether they want to leave it nearly exclusively to international joint ventures. It is clear in either case that renewable energy independent power producers can be successful if the competition with conventional generation is open, fair, and accounts for all the costs. Since all of these requirements are rarely met, a set-aside is a reasonable method to both level the playing field and gain valuable experience. In addition, renewable energy may be given a special status, including more incentives than other energy sources. The justification is that: Renewable energy sources are environmentally friendly. Using renewable energy will therefore reduce the economic burden of mitigating energy sector environmental impacts. Renewable energy sources are domestic energy sources, thereby saving foreign exchange and improving the security of supply. Disposal of biomass residues poses considerable environmental problems. Using the residues for energy production offers a solution to these problems. However, it may be necessary to keep some of the residues for soil protection. World wide, renewable energy is a fast growing industry. Being pro-active in this field therefore opens up opportunities for export industries. SOUTH AFRICAN POLICY ON RENEWABLE ENERGY The South African government pays strong attention to economic and social development, but it also addresses the interdependencies and synergies between development and the energy sector. Through these linkages the energy sector can greatly contribute to a successful and sustainable national growth and development strategy. The new government has adopted a macro-economic strategy, Growth, Employment and Redistribution (GEAR), which aims at promoting growth through exports and investment; and promoting redistribution by creating jobs and reallocating resources through the budget. The advantages of renewable energy are set out in the Energy White Paper (1998), particularly for remote areas where grid electricity supplies is not feasible. The Government believes that renewable energy can in some cases provide the least cost energy service, particularly when and environmental costs are included, and will therefore provide focused support for the development, and applications of renewable energy. Government policy is based on an understanding that renewables are energy 10 sources in their own right, are not limited to small-scale and remote applications, and have significant medium and long-term commercial potential. In 1998, the Department of Minerals and Energy produced two internal renewable energy strategy papers entitled "Towards an implementation plan" and also "An implementation action plan". The intent of these documents was to further develop the issues set out in the EWP. The Energy White Paper encourages the entry of multiple players into the generation market. Initially this policy will be implemented by obliging the national transmission system to publish National Electricity Regulator approved tariffs for the purchase of co-generated and independently generated electricity on the basis of full avoided costs. PERSPECTIVES WITH THE GLOBAL AGREEMENTS ON CLIMATE CHANGE South Africa ratified the United Nations Framework Convention on Climate Change in August 1997, just in time to formally participate in the important 3rd Conference of Parties in Kyoto, Japan. In keeping with their communication commitments as a party to the Convention, the SA Government undertook the preparation of an inventory of emissions. In 1990, the base year for emissions reporting, South Africa emitted an estimated (using a top-down method) total of CO2 equivalent an amount of 373,922 Gg/year for the 3 main greenhouse gasses, CO2, CH4 and N2O. This excludes the amount sequestered in woodlands and plantations (20,614Gg) in the same period. Of the emissions 38% is attributed to electricity generation and 89% of the CO2 equivalent is emitted in total from the energy sector. The Government’s view on Climate Change Policy was delivered in the National Assembly on 6th June 2000 by the Deputy Minister of Environmental Affairs and Tourism, Ms. R. Mabudhafasi. “SA’s ratification of the FCCC signifies government’s commitment to join the global community finding solutions to the escalating greenhouse concentrations in the atmosphere.” The Deputy Minister proceeded to list 3 areas where action would be taken including lighting and heating in homes, energy intensive industries and the export sector. She also pointed to “collective action” between minerals and energy, trade and industry, water affairs and forestry, transport, and agriculture culminating in a “Response Strategy which outline has been approved by Cabinet and is due for finalisation in December 2000.” The Clean Development Mechanism (CDM) is a mechanism that allows industrialised countries to invest in carbon mitigating efforts in the developing countries in order to supplement their domestic actions in meeting their commitments. CDM projects are obliged to contribute to sustainable development in reducing emissions. 11 It is most likely that the international market for carbon will establish the price paid for CO2. If this assumption proves correct, the price will be subject to variations of supply (how many and how big the projects) and demand (the interest of buyers and technology transferors, and proximity to emission targets and the end of commitment periods). A quick calculation using US$10/ton CO2 would, in a wind project developed in South Africa (coal powered electricity baseline), result in a carbon payment of US$ 0.01131/kWh (equivalent to SAR 0.08/kWh). Over the life of the project, this would imply a 20% offset of the capital cost of wind turbines. This constitutes a considerable benefit to a renewables project. Key to government policy implementation would be to remove barriers to the increased use of renewables and to set achievable goals for the contribution of renewable energy to the national energy mix. LEGAL, INSTITUTIONAL AND REGULATORY SET-UP OF THE POWER SECTOR ESKOM is the national electricity supplier of South Africa. In 1999, Eskom has split into an unregulated component (Eskom Enterprises) and a regulated component (Eskom). The electricity supply industry is regulated by the National Electricity Regulator, established by the electricity act of 1987. Its routine regulatory activities include licensing, tariff approval, handling of disputes and customer complaints, monitoring the quality of supply and service standards and others. The Department of Minerals and Energy prepares and suggests energy policy and legislation to cabinet for presentation to parliament. THE RESTRUCTURING OF THE POWER SECTOR The South African government is currently considering implementing great change into the electricity distribution industry and the electricity supply industry. The overall objective of distribution reform is to consolidate the highly fragmented industry, while the objective of the supply industry reform initiatives is to create a more efficient and effective power supply industry. Rationalisation of the Electricity Distribution Industry The South African electricity distribution industry is highly fragmented. There are substantial differences in the financial health of the 400 or so municipalities - many distributors are not even financially viable. There is currently a wide disparity in the prices paid by the various customer segments that cannot fully be explained by the costs associated with serving these segments. Economies of scale, skill and specialisation are not being captured by many of the small distributors. Furthermore, electrification needs are unevenly distributed across regions with some of the poorer regions having the greatest need. 12 To address these concerns, Government now plans to consolidate the distribution industry into a maximum number of financially viable regional electricity distributors. Emerging views are that six such regional entities should be established, with each containing a major economic centre. It is likely that the part of Eskom operating distribution facilities will be eventually transferred to these consolidated regional entities. Rationalisation of the electricity distribution industry will not in itself have considerable impact on the fate of bulk renewable energy generation in South Africa. The soon to be created regional distributors however will naturally become the main clients of generators producing power from renewable energy sources. Reform of the Electricity Supply Industry For some years now, the Government of South Africa has been considering significant change in the electricity supply industry. To date no decisions have been made but a likely model for reform has emerged. The likely reform path is illustrated in Figures 1 through 3 below. Under the Purchasing Agency model, Eskom dominates the electricity industry. Eskom controls Generation, Transmission and the unregulated Eskom Enterprises. Regional Electricity Distributors are in place. Any new generator entering the market sells power to Eskom. However, the new investments into the industry are not easily attracted because investors are concerned about the potential conflict of interest in Eskom, as owner of Transmission as well as various generation plants. Open, nondiscriminatory access is not guaranteed. Independent power producers entering this market would only do so on condition that long-term power purchase agreements are established. Eskom Holdings Eskom Generation Internal Pool Eskom Transmission Eskom Enterprises IPP RED 1 RED 2 RED 3 RED 4 RED 5 RED 6 Large customers Customers Figure 1: Purchasing Agency Model. Source: Adapted from Hunt & Shuttleworth (1996) 13 According to the Generation Oligopoly model, Eskom continues to control Generation and the unregulated Eskom Enterprises. Eskom Generation units are grouped into different clusters under the control of Eskom Holdings. These different operating divisions bid separately to sell power to the pool. Transmission is established as a separate state-owned company. An external power exchange is established. According to this model, Eskom may continue to exert market power through its various subsidiaries. Within this context, it is still unlikely that independent power producers would invest in large generation plants. Eskom Holdings Generation 1 Generation 2 Generation 3 Eskom Enterprises Power Pool IPP State-owned independent transmission company RED 1 RED 2 RED 3 RED 4 RED 5 RED 6 Large customers Customers Figure 2: Generation Oligopoly Model. Source: Adapted from Hunt & Shuttleworth (1996) According to the Wholesale Competition Model illustrated in Figure 3, Eskom is left with a highly diluted portfolio of generation assets (in addition to Eskom Enterprises). The remainder of Generation is separated into a number of competitive independent companies. These could be privatised through, for example, black economic empowerment provisions, a private equity offering or an initial public offering. 14 Eskom Holdings Generation 1 Generation 2 Generation 3 Eskom Generation Eskom Enterprises Power Internal Pool State-owned independent transmission company RED 1 RED 2 RED 3 RED 4 RED 5 RED 6 Large customers Customers Figure 3: Wholesale Competition Model. Source: Adapted from Hunt & Shuttleworth (1996) Retail competition could be introduced after this stage. It is unlikely, however, that this will happen for some time to come. Possible impacts of ESI reform on bulk renewable energy generation Unbundling In South Africa, unbundling initiatives could have significant impact on bulk generation of renewable energy. Unbundling would be complete in the model characterised by Figure II. Under the Generation Oligopoly model, Eskom no longer controls transmission. ‘Fair’ access to the transmission network can be assumed. Commercialisation and corporatisation It is likely that commercialisation and corporatisation initiatives will have significant effect on investment in renewables in bulk power markets because cost structure will become more transparent and cross subsidies will be reduced or eliminated. As Eskom moves towards more cost-reflective tariffs, investment in bulk renewable energy generation is likely to become increasingly achievable by independent power producers. Competition The introduction of wholesale competition to the South African power sector is not likely to favour renewables in bulk power markets. Compared with long-term bilateral power purchase agreements, short-term or spot markets make it more difficult to finance and develop all generation options and make renewables, where costs are often front-loaded because the costs are usually largely capital and cheap or free fuel costs, even more disadvantaged. Spot markets are particularly unfriendly to the development of “intermittent” renewable resources. The inability to generate power on demand is more of a drawback in spot markets, which places a premium on generators that can assure power availability during peak periods. When, and if retail competition is introduced into the power sector in South Africa, investment in bulk renewable energy generation is even less likely to be sustained, 15 unless a considerable “green power” market develops. This would be primarily because generators and regional distributors will be increasingly conscious about retaining customers, and the primary determinant of this is likely to be related to the tariff level (and perhaps service) offered. Privatisation Privatisation initiatives are unlikely by themselves to increase the market share of bulk generated renewable energy generation. Independent power developers face a highest cost of capital and a shorter repayment period than the vertically integrated utilities. Bulk renewable energy generators face other barriers in obtaining long-term power contracts. Transaction costs incurred to participate in the bidding process may favour certain technologies. Per megawatt, the costs of preparing a bid for a thermal project are less than for a renewable project. This is because of scale and a motivation for a special regulatory framework. RENEWABLE ENERGY RESOURCES South Africa is endowed with abundance in renewable energy resources most notably solar, biomass and wind. Exploitation of these resources for energy generation purposes has the potential to contribute up to 20% of national electricity production by 2020.The table provides a summary of renewable energy resource availability. Resource Total energy contribution (PJ/year) 1 Wind 6,2 Bagasse 2 47 1 Wood 44 3 Hydro 40 1 Based on total theoretical potential of total resource 2 Based on total energy value of current harvest 3 Harvestable potential The renewable energy technologies that are viable in the South African context in the medium term (5-10) years are: Wind Hydro Biomass (bagasse and wood waste) These are mature technologies that are well established internationally and South Africa has an ample resource base. In the longer term, the technology, which shows the highest technical potential, is solar thermal electric or solar PV (depending on the economics). South Africa has a very good solar energy resource that could enable low cost energy production as technology costs continue to decline. 16 Resource availability and potential is but one of the factors that determined the viability of grid connected renewables. In the very long run the availability and scope of the different resources renewables and non-renewable will become a stronger determinant. A range of factors must be considered before making a decision on the commercial viability of grid connected power production whether from renewable energy technologies or from other energy sources. These include factors such as sufficient demand for power from specific customers or a electricity pool, economies of scale, type of production (base load, peak load, intermittent or constant) and so forth. Developing a renewable energy powered power plant invariably requires indepth local assessment of the resource for a minimum of an annual cycle. This results in a further lengthening of the project development cycle. The biomass sector, wood, pulp and sugar mills; could skip this extended local resource assessment. In these sectors the resource availability is known and determined by a controlled agricultural production process. For large scale solar or wind plants however, on site measurements are still essential. Non utility generation experiences in South Africa Existing renewable energy generators The National Electricity Regulator (NER) has licensed most existing generating plants as electricity generators according to the Electricity Act of 1987. The Act requires plants that generate more than 5GWh/annum for resale as well as all municipal generators obtain an NER license. In 1995 the NER approached all the known cogenerators of electricity and the self-generating municipalities as well as Eskom as part of the licensing process. Private generating capacity was also identified in the process. A license is provided for a generating plant and not for an operator. Eskom therefore has been licensed for each of its power stations. The breakdown of the 50 currently licensed power stations is Eskom 24 plants Municipal 18 plants Private 8 plants Non-utility generation contributes 8.2% by power capacity (3272 MW licensed capacity) of South African electricity generation capacity. Eskom provides the remainder (39870MW licensed capacity), (NER “Electricity supply statistics for South Africa”1998). Of interest to this study are the 26 non-Eskom operated licensed plants, other existing plants which have the potential to be developed as IPPs (so called brownfield projects) as well as a number of new or ‘greenfield’ projects. There is no formal distinction made in South Africa between renewable and nonrenewable energy powered electricity generators in terms of generation licensing. Generators are listed and grouped according to fuel use such as coal, hydro or gas and utility or non-utility. It is however possible to separate out those generators that use a renewable energy fuel source such as biomass or small-scale hydropower. The NER has licensed 4 small hydro power plants operated by Eskom and 8 renewable energy based non-Eskom operated power plants. Of these 4 are bagasse burning sugar mills, 3 are municipal owned hydro power plants and one is a privately owned small hydro power station (Friedenheim Hydro). 17 Friedenheim hydro is the closest to an IPP that South Africa has at present. What makes Friedenheim hydro unique is that it sells the bulk of its power to a third party under a power purchase agreement and its own consumption is a small component of the power produced. All the other plants, be it a bagasse mill or a municipal hydro station, are owned by the purchaser of the power and only a small surplus is sold. The table below lists licensed renewable energy power produces in South Africa. These plants all have the potential of being turned into IPPs. Licensed renewable energy power producers Name Private hydro Friedenheim Municipal hydro Lydenburg Ceres Piet Retief Eskom Hydro Collywobbles First Falls Second Falls Ncora Gariap Vanderkloff Sugar mills TH Amatikulu TH Darnall TH Felixton TH Maidstone Transvaal Suiker TOTAL Licensed Capacity Maximum power produced Net energy sent out Private consumption Load factor MW MW MWh MWh % 3 2 14 434 1 041 73.7 2 1 1 2 1 1 6 000 413 2 900 0 0 0 34.2 8.6 33.1 42 6 11 2 42 6 11 2 257 544 36 792 67 452 12 264 0 0 0 0 70* 70* 70* 70* 12 13 32 29 20 174 10 7 22 20 174 43 775 27 388 79 935 79 582 628 479 43 775 27 388 79 935 44 917 231 721 51 44.7 41.5 45.4 - *Assumed The sugar mills show the best potential for IPPs. It is possible to increase electricity production from the present 30kWh/ton bagasse to 120kWh using the present steam based technology and to reach up to 460kWh/ton through advanced combined cycle gasification processes. The sugar industry is already aware of the potential for commercial power generation through the experiences in other sugar growing regions such a Mauritius. Potential and proposed IPPs At the time of writing the NER has received licence applications or pre application project descriptions from three potential renewable energy IPPs. Of these, DARLIPP (5-10MW wind) and Bethlehem Hydro (10MW) are at the feasibility phase of development and could be implemented within the next 1-2 years. The other project is Green Energy (30MW wave), which is still in a pre-feasibility phase. 18 Apart from the renewable energy IPPs under development a number of non-renewable energy based power projects have been submitted to the NER for licensing or as preapplication descriptions of potential IPPs. It is clear that the proposed renewable energy IPPs are of a smaller scale than the non-renewable energy power plants. This fact that small IPPs tend to be based on renewable energy technologies is due to the relatively small economies of scale that can be achieved by these technologies. It is likely that once a project such as Darling is established that many other potential IPPs will be identified and developed. The table below lists the medium term (510years) potential for renewable energy IPPs based on a qualitative analysis of the electricity sector and likely electricity generators Short-term potential renewable energy IPPs in South Africa Technology Wind Present generation 0 Potential Export date 2002 Potential Export Capacity 5-50 MW Constraints Hydro 67 MW 2000 100-150 MW Few good sites available Bagasse 59 MW 2002 400-600 MW Cost of upgrading Wood & Pulp TOTAL 279 MW 405 MW 2002 300 – 500 MW 800 – 1 300MW Cost of upgrading High cost of generation Barriers and factors influencing IPP development in South Africa A number of factors influence the development of IPPs in South Africa. These include: Conflicting messages Although the Energy White Paper sets a policy direction of encouraging ‘ the development of renewable and environmentally sound electricity generation technologies’ and to’ encourage more players to enter the generation industry in order to develop a competitive power’ market’, the Electricity Act protects Eskom’s monopoly interests. The National Electricity Regulator has not established the conditions necessary to increase and encourage competition by for example implementing regulations to enable long-term power purchase agreements. Tariffs The main factor that is keeping new private generation development at bay is the low cost of Eskom’s electricity at present. The incremental operational expenditure cost of new generation ranging from hydro to coal and gas is estimated in the range of R 0.14- 0.18/kWh. Compared with Eskom’s current average tariff of R0.12 (1999 Eskom Annual Report), this leaves little scope for recovering capital costs. Looking at the medium term, especially at when Eskom generation surplus is expected to end (2005-2010) it is inevitable that electricity tariffs will increase. The increased average tariff has been estimated at about R 0.25-0.4/kwh by 2010. This paints a completely different picture. A whole range of generation technologies and IPP will be competitive at this range of tariffs. 19 Another consideration is the need to wheel power from the IPP through the transmission network to a customer. The transmission network is controlled by Eskom, which in the absence of an established wheeling tariff is at liberty to use arbitrary wheeling charges to prevent grid access. Project developer profile The development of an IPP is a business venture and should therefore be driven from the commercial and business sectors. In South Africa there is at present little interest or involvement of the commercial sector in the development of IPPs. The reason for this is that under present circumstances IPPs are not a viable business venture. The country lacks the appropriate legal and regulatory framework, the electricity sector is in a state of flux due to imminent restructuring and there is no significant bulk demand for power. Trying to develop an IPP under these conditions incurs long and costly project lead times with no immediate returns. Demand for generation capacity The strongest incentive to bring new generation capacity online is a present or foreseen power shortage. That situation does not exist in South Africa at the moment. In fact South Africa currently has an excess of electricity potential to the order of 8 000 MW. Looking into the future it is expected that South Africa will require new base load power between 2005 and 2010 and peak power earlier than that. Stranded Assets The potential threat that undercutting Eskom poses is that of stranded assets. If more and more capacity is brought online selling power at a rate below that of Eskom eventually demand to Eskom will decrease to such an extent that it will have to reduce its generation levels and even shut down a power station. This fully or partially shut down power station becomes a stranded asset. In reality there is quite a bit of scope for bringing new capacity on line without stranding any Eskom assets. As long as the increment at which new power is added remains small compared to Eskom total generating capacity the stranding impact is negligible. Adding a 5-10 MW to the system of close to 40 000Mwis unlikely to attract much notice Financing: Equity International utilities with green energy targets or quotas and IPP developers are keen to invest in commercially viable sustainable energy projects. The money is there; we just need to get the right projects. Power purchase agreements Critical to the successful development of an IPP in an electricity market such as South Africa is securing a power purchase agreement. A PPA is a contractual commitment to buy the power produced by the IPP subject to certain conditions. Power purchase agreements establish real revenue flows, which are considered by lending institutions and investors in making financing and investment decisions. In the absence of a fully functional merchant power market and excellent 20 information on energy production and demand, power purchase agreements will remain necessary financing pre-requisites. The Electricity Act of 1987 provides for the National Electricity Regulator (NER) to licence all electricity generators above the threshold generation of 5 GWh/year. Financing: Debt South Africa has a well functioning and very competitive banking sector. Most of the larger banks have project finance divisions, which specialise in the financing of projects such as IPPs. These banks will be more than willing to provide finance to IPP projects provided that the security and comfort of a power purchase agreement can be provided Concessionary and venture finance An alternative to conventional project finance is to ‘subsidise’ the project through concessionary financing. Fortunately for the renewable energy sector there is a growing market for concessionary and venture financing available for sustainable energy projects. This can range from Global Environmental Facility (GEF) funds to bilateral climate change programmes such as AIJ/CDM and from development banks such as the DBSA or venture funds such as the REEF and energy investment services such as E&Co. FINANCIAL AND ECONOMIC EVALUATION OF RENEWABLE ENERGY The ”White Paper on Energy Policy for the Republic of South Africa” (1998) stated the Government’s expectations on electricity pricing: “Price signals should result in economically optimal investments in electricity infrastructure and consumption of electrical energy. Government is of the view that this will generally be achieved through the use of cost-based electricity tariffs which include capital replacement costs (long-run marginal costs).” On this background, the aim of the project has been to determine the Long Run Marginal Cost (LRMC) for traditional coal-fired generation and compare this with the LRMC of renewable energy independent power producers. The most likely future generating resources are coal based. As such this is the appropriate comparison point for LRMC. If South Africa includes nuclear projects in future generation options; this would be the more appropriate LRMC comparison. The last few years have resulted in excess capacity. At the same time the South African Rand has devalued considerably. For these reasons, the present study has found that international data on investment costs provide a more realistic estimate of the LRMC than historical data from South Africa. 21 The real cost of coal-fired power generation in South Africa has been estimated at (ZARcents per kWh): LMRC of coal-fired electricity generation in South Africa Capital cost O&M Fuel Total cost Without desulphurisation and NOx equipment With desulphurisation and NOx reduction equipment 8.6 2.8 2.6 14.0 12.9 3.8 2.6 19.3 For non-utility electricity generation the White Paper on Energy Policy stated that the tariffs shall be approved “on the basis of full avoided costs”. “By including environmental costs into the pricing structure for further development of renewable and environmentally benign generation technologies such as hydro, wind, solar thermal, and waste incineration will also be encouraged”. The direct environmental costs of coal-based electricity generation in South Africa have been estimated to be in the order of 5 – 6 ZARcents/kWh. Including the impacts on the global climate would add extra 2 – 10 cents/kWh. The project has compared the real cost of coal-fired generation with renewable energy IPPs. The results are shown in the figure below: 22 Generation costs in ZARcents/kWh 40.0 30.0 20.0 10.0 Capital cost O&M Fuel Environ CO2 Total costs h N uc l ea rH ig rL ow ea N uc l Ba ga s se d W in H C oa l yd ro 0.0 Losses Total generation costs of various technologies. For each technology the column to the right presents the total cost. For some, the cost components are shown to the left. REVIEW OF INTERNATIONAL RENEWABLE ENERGY POLICIES Where renewable energy use has thrived around the world, favourable energy policies have been responsible for this growth. Governments have chosen to put supportive policies in place to overcome market entry barriers. Barriers to widespread use of renewable energy include: Traditional generation technologies such as coal appear cheaper because their environmental impacts are not fully included in the costs; 23 Renewable energy technologies are believed to hold the best promise for sustainable economic and social development because they minimise the hidden human costs of pollution; and Current reliance on carbon based fuels is causing changes to the earth’s climate which will prove catastrophic, wreaking social, environmental, and economic havoc. These policies make investments in renewable energy capacity attractive to power producers through either subsidies designed to offset hidden environmental subsidies of fossil fuels, or requirements for renewable energy power generation designed to force maturation of renewable energy technologies by successive cycles of use and improvement. In essence the justification for introducing policies favouring renewable energy is to create an equal or “level” playing field between all resource alternatives. It is not only important that renewable energy use be increased, but also that this growth is sustainable. Large subsidies can foster tremendous use of renewable energy, but since most subsidies are not sustainable, it is important for the technologies to become cost-competitive for sustainable and commercial markets to be developed. If the goal is to maximise renewable energy generation, then a fixed incentive or setaside should apply to all technologies. Set-asides are blocks of energy supply that are earmarked for renewable energy capacity. Competitive bids can be used to determine the energy supplier or standard offers can be set with energy suppliers meeting capacity on a first-come, first-serve basis. This minimises the incentive payments for maximum use of renewable energy, and it allows for future cost reduction of technologies which are currently too expensive to be deployed. If the goal instead is to deploy and begin commercialisation of certain technologies, then individual incentives or set-asides can be set for each technology. 24 There are many methods for governments to promote renewable energy. A summary is presented in the table below. Tool Production incentives Advantages Easy to implement, Easy for developers, Encourages renewable energy production. Disadvantages Does not directly address high first cost barrier. Can be abused if incentive too high. Investment incentives Overcomes high first cost barrier Encourages investment, not production Renewable Set-Asides Allows control over amount of renewable capacity added, Competitive bidding encourages cost reductions Power Purchase Agreements Long-term, standard agreements help developers and facilitate investment Environmental Taxation Correct energy prices including costs of environmental impacts provides a more level playing field for renewables Can be very bureaucratic. Bids may be controlled by one entity. May lead to lumpiness in installations. Difficult to achieve when the electricity supply industry is in the process of restructuring Taxes are often politically unfavourable Externality Adders Allows for full-cost Implementation does not accounting in power planning always follow planning Research, Development and Demonstration Builds long-term foundation for technological and industrial development Government Assisted Business Development Builds market infrastructure Green Marketing Allows choice in power purchases Difficult to pick a technological winner to invest RD&D in May be under-subscribed Of these, the methods that have been most successful in promoting large-scale renewable energy development are investment incentives, production incentives, and set-asides. Some options, such as environmental taxation, RD&D, and green marketing, have been helpful, but have not had the same impact. Other options, such as establishment of standard power purchase agreements, may be a necessary condition for renewable energy promotion, but they may not be sufficient. Some international finance institutions have launched global investment and market transformation initiatives. Otherwise, lessons learned form other countries are 25 worthwhile. The main report describes the experiences from United Kingdom, the Netherlands, Denmark, Germany, India, and Sweden. RECOMMENDATIONS There are five areas according to which the recommendations can be grouped. 1. Policy and legislation – immediate initiatives Recommendation 1: Renewable energy IPP set-aside programme Through a cabinet memorandum set aside approximately 200 MW of generation capacity for a transparent solicitation procedure to select the most competitive renewable energy projects to test and expand the prospects for the development of renewable energy IPPs in South Africa. Eskom Transmission shall be obliged to purchase the electricity generated. The Regional Electricity Distributors shall be enabled to purchase some of the generated electricity, if they so wish. Award of a power purchase agreement shall be an integral part of winning the bid. Eskom may be enabled to establish a fraction of the set-side itself, but independent power producers should establish most of the capacity. Recommendation 2: Interim power purchase regulation Develop an interim regulation regarding conditions for the grid-connection of power from small and distributed generators to facilitate the implementation of the set-aside programme (recommendation 1). 2. Policy and legislation – longer term initiatives Recommendation 3: Power purchase regulation. On the basis of the interim power purchase regulation (cf. recommendation 2) a regulation regarding conditions for the grid-connection of power from small and distributed generators beyond the set-aside programme should be developed. Recommendation 4: IRP inclusion of renewable energy IPPs Create a long-term plan for the inclusion of renewable energy IPPs into the electricity system. The plan should be based on an Integrated Resource Planning framework that explicitly considers environmental, social, and economic costs and benefits of resource alternatives. 26 Recommendation 5: Electricity information Make all essential power sector data publicly available (e.g. generation costs, future investments, and external impacts) through a central electricity information service. Recommendation 6: Capacity development, government Sustainable capacity development within DME and NER seems to be a crucial precondition for the longer-term success of renewable energy in the country. Other relevant government and non-governmental institutions may also need strengthening in this field. Recommendation 7: Capacity development, civil society Develop mechanisms to support potential owners of renewable energy IPPs and organisations promoting renewable energy. 3. Regulation – tariffs and grid connection Recommendation 8: Transparent licensing. Develop transparent and accountable licensing conditions together with more consistent IPP license procedures. Recommendation 9: Technical grid connection code Establish a national grid connection code, which specifies connection requirements appropriate to the size and other characteristics of the resource and does not impose inordinate financial or technical burdens. This includes synchronisation conditions and rules for sharing the connection installation costs. Recommendation 10: Renewable energy tariff structure To ensure a development of renewable energy IPPs beyond the set-aside programme, end-user tariffs should be set which reflect the following conditions: The avoided-cost principle should reflect the long run marginal cost of electricity, not only the short run marginal cost. IPPs situated close to loads should be credited for avoided line losses. This is in line with the transmission network charges of the proposed wholesale electricitypricing system (WEPS) as outlined in section 6.3.1 on transmission costs. Tariffs should be based on full cost accounting. Tariffs should include environmental externalities. In case this results in overrecovering of the expenses, the surplus income can be transferred to environmental mitigation measures. Third party access to the transmission system and the distribution systems should involve reasonable wheeling and banking tariffs defined by NER 27 4. Support activities Recommendation 11: Long term barrier removal. In parallel with the recommendations in the areas of demonstration and regulation, and based on the experiences from the concrete projects, proper long-term and general solutions to mitigate all essential barriers shall be systematically identified and implemented in order to further nourish the development of renewable IPPs. Recommendation 12: Investment capital for renewable energy The availability and accessibility of investment capital for small project developers should be improved. Innovative ways of accessing low-cost finance should be made available to IPPs. Several options have been developed internationally. A project should be launched to investigate such options and come up with recommendations in this area. Recommendation 13: Green power marketing Allow a “Green Power” option to cover the incremental costs of renewable energy power producers. The best option for a “green power” based electricity sale, within the time frame considered for this project, would be to recruit from industrial customers. 5. Demonstration activities Recommendation 14: The Darling Wind Farm Implement the Darling Wind Farm demonstration project. Recommendation 15: Mini-hydro Establish a mini-hydro power plant as a national demonstration project. Recommendation 16: Cogeneration in sugar industry. Establish a combined heat and power plant in a sugar industry using bagasse as fuel as a national demonstration project. Recommendation 17: Cogeneration in wood/pulp industry A combined heat and power plant in a wood or pulp/paper industry using wood residues as fuel as a national demonstration project. 28 1. BACKGROUND 1.1. The Rationale Renewable energy sources are environmentally clean sources with additional economic and social benefits. They have received considerable and growing attention around the world the last two decades, initially because they have strong potential for mitigating environmental impacts from electricity generation. The so-called bulk renewable energy independent power producers, delivering electricity to the national grids, are the focus of the present report. 1.1.1. Economic and social development Renewable energy resources can be an important part of economic and social development strategies. If appropriate market conditions are created to ensure essential penetration of renewable energy technologies, most of the equipment may be produced in South Africa. The world market is rapidly increasing, so there is a large export potential. The possible impact on macro economy and employment is substantial. At the same time, many exporting South African companies have come under pressure from their overseas clients regarding environmental issues. Successful implementation of ISO 9000 series has become an important part of export strategies and ISO 14000 series certifications are now being sought by firms around the world as environmental criteria become part of standard trade considerations. ISO 14000 series have explicit energy requirements including efficiency and non-polluting sources. The issue of employment is found important in many countries. Although no calculations have been made specific to South Africa, the following table summarises studies done elsewhere and shows the potential job creation benefits of a renewable energy strategy, when compared to either coal or nuclear power stations. Resource Coal fired power plant Photovoltaics Solar thermal electricity Wind-generated electricity Biomass-derived electricity Hydro-derived electricity Information Source New York State American Wind Energy Ass. Danish Study World Watch Institute [man-years, same amount of energy] [jobs per mil. US$ invest.] [jobs per mil. US$ invest.] [jobs per TWh] 6,200 13.1 7.4 13 116 14,200 10.0 14 248 542 17.0-22.6 4.0 29 8 As many renewable energy technologies by nature are generating intermittent electricity, they are best suited for grid-connected electricity generation, so that the grid can function as back-up in periods with low or no generation. Some renewable energy technologies are also suited for off-grid electricity supply, e.g. in hybrid mini-grids. A hybrid system is a combination of at least two different generators, one being intermittent (solar, wind), the other being firm (diesel, hydro). The latter functions as back-up for the former and will therefore often be idle. The intermittent source usually has high initial costs and low operational costs. Because of the redundant capacity the total investment in a hybrid system is high. For this reason, private investors are unlikely to invest in such systems. Introduction of on-grid renewable independent power producers would help increase the prospects for off-grid solutions. As many technological and non-technological aspects are equivalent, a higher market volume for these technologies will encourage a larger number of investors and manufacturers. This will increase competition and in turn imply lower prices. The combined higher market volume of on-grid and mini-grid technologies will also imply that the critical volume for manufacturing the equipment in South Africa will be reached at an earlier stage. Furthermore, a larger market will strengthen the incountry technological support (education, operation and maintenance, availability of spare-parts etc.). All in all, by combining on-grid and mini-grid developments, the job creation potential is considerably improved. In this connection, it is noteworthy that there is a large need for job creation in Western and Northern Cape, where the wind and solar resources are highest. 1.1.2. Environmental benefits Renewable energy technologies have undisputed positive impacts on local environments. More recently the interest has also been driven by a global effort to mitigate climate change. In 1997 South Africa ratified the international Framework Convention on Climate Change, one of the outcomes of the Earth Summit in Rio de Janeiro in1992 on sustainable development. A follow-up summit, the so-called ‘Rio+10 Summit 2002’, has been scheduled. South Africa has invited the United Nations to host this event. In his invitation, Minister of Environmental Affairs and Tourism, Mr Mohammed Valli Moosa, stated: “Our planet is suffering from a depletion of non-renewable natural resources. The loss of biodiversity, the unravelling of ecosystems, pollution of scarce water resources and the very air that we breathe, deteriorating health, climate changes as a result of global warming, and the corresponding threat to food production and the life in the sea are concerns that we all share.” 30 Of South Africa’s total emissions of greenhouse gasses, 38% is attributed to electricity generation. A sustainable energy strategy addressing this challenge necessarily involves renewable energy and energy efficiency. International mechanisms are now being developed to facilitate the transfer of investments from industrialised countries to developing countries in renewable energy and related technologies. Foreign investors are already looking for project opportunities in South Africa. 1.1.3. Justification for preferential status The justification for introducing policies favouring renewable energy can be defined at two levels, creating a level playing field and assigning special status. Currently the comparison between renewable energy and conventional generation is unfair because the environmental costs of conventional generation are not fully accounted for, neither in the future planning of resources nor in current pricing of generation output. In addition comparisons are often made between renewable energy generation and current electricity tariffs, instead of comparing the total costs of future generating resources. First of all, an equal level playing field has to be established. An equal level playing field consists of several components: Economy Renewable energy must be given equal economic opportunities. Some of the competing energy sources are often subsidised. All energy sources should be compared economically using the same standards, e.g. a market based economy without any economic incentives and disincentives (subsidies, taxes, tax exemptions etc.). Finance Traditional power utilities, by virtue of being well established, usually have ready access to less costly finance (low interest, long maturity), whereas typical renewable energy owners only can obtain much more expensive finance. Access to market The electricity grid is the market place. Renewable Energy should have at least the same access to the grid as other energy sources. The challenge is to develop a mechanism for grid connection, which is acceptable for both the seller and the buyer. Organisation Traditional power plant operators are usually big corporations. They are very experienced and they can afford to acquire extra technical, economic, financial, and legal expertise. Small owners often cannot afford to acquire much expertise. By taking up a strong international IPP developer or utility as partner renewable energy independent power producers can compete on equal footing. The policy choice as to whether to provide additional support is in some cases related to whether the government wants small local enterprises to be able to enter this 31 market or whether they want to leave it nearly exclusively to international joint ventures. It is clear in either case that renewable energy independent power producers can be successful if the competition with conventional generation is open, fair, and accounts for all the costs. Since all of these requirements are rarely met, a set-aside is a reasonable method to both level the playing field and gain valuable experience. In addition, renewable energy may be given a special status, including more incentives than other energy sources. The justification is that: Renewable energy sources are environmentally friendly. Using renewable energy will therefore reduce the economic burden of mitigating energy sector environmental impacts. Renewable energy sources are domestic energy sources, thereby saving foreign exchange and improving the security of supply. Disposal of biomass residues poses considerable environmental problems. Using the residues for energy production offers a solution to these problems. However, it may be necessary to keep some of the residues for soil protection. World wide, renewable energy is a fast growing industry. Being pro-active in this field therefore opens up opportunities for export industries. In a comprehensive approach, such advantages should be balanced against disadvantages, e.g. biomass fuel is a local fuel (costly to transport), and renewable energy generators are usually not as reliable as fossil fuel generators. 1.2. Background to Project The Danish Co-operation for Environment and Development (DANCED) was established in 1993 as a follow-up to the United Nations Conference on Environment and Development (UNCED) held in Rio de Janeiro in 1992. The overall objective of DANCED is to contribute to restoring the global environment in accordance with the recommendations of UNCED (Agenda 21). DANCED is managed by the Danish Ministry of Environment and Energy in co-ordination with the Ministry of Foreign Affairs. Support to the area of sustainable energy has been on the DANCED agenda since 1995. In the 1996 Danida/DANCED Strategy for Danish Regional Environmental Assistance in Southern Africa, "Sustainable Exploitation of Energy Sources" was specified as a potential area for support. "Sustainable energy" is one of the four identified themes for DANCED support in the South Africa - Danish Country Programme for Environmental Assistance 1998-2002 (1998). The Department of Minerals and Energy (DME) is serving as the "lead agent" for the development of future activities for possible DANCED support. DME and DANCED have been actively exploring support to the energy sector in South Africa since the start of the programme in 1995. The following initiatives have been undertaken: 32 DANCED Programme Formulation Mission, January 1995; Sustainable Energy Programme Appraisal Mission, 30 September - 13 October 1995; Input into the South African "Energy Policy Discussion Document" on renewable energy, November 1995; Energy Study Tour to Denmark, May 1997; Development of the REFSA Project, July 1996 - September 1997; Development of the Phase I Sustainable Energy and Environmental Development (SEED) Projects, 1996 - October 1998; Energy Efficiency in Low Cost Housing Component of the Midrand "Green City" Project, July 1997 - July 1998. In 1999 DME and Danced agreed to initiate a project entitled “Background Research Mission on Independent Power Production (IPP) in South Africa with an Emphasis on Bulk Electricity Generated Through the Harnessing of Renewable Energy Sources”. The objective was to clearly describe the current state of independent power production (IPP) in South Africa with specific emphasis on the identification of barriers to the development of bulk (grid connected) renewable energy. From this, clear recommendations for a possible strategy for progress should be elaborated, if deemed both appropriate and necessary. The project started with a scoping mission 14 – 27 March 2000. During this mission a methodology was developed and the composition of the consulting team was finalised. The Team has had the following members: Jorgen Boldt, Ramboll, Denmark (Team Leader). Replaced Jorgen Hvid, also Ramboll, in July 2000. Terry Oliver, International Institute for Energy Conservation (IIEC), Bangkok, Thailand. Frank Hochmuth, MEPC (Minerals & Energy Policy centre) Associate, Johannesburg. Alix Clark, independent consultant, Cape Town. Until August 2000 with the Energy & Development Research Centre (EDRC), University of Cape Town. Justice Mavhungu, Energy & Development Research Centre (EDRC), University of Cape Town. Anton-Louis Olivier, energy & environmental management (e3), Menlopark. From September 2000 with the UNEP Collaborating Centre on Energy and Environment (UCCEE), Denmark. Steve Thorne, Energy Transformations, Cape Town. Douglas Banks and Jason Schäffler, Rural Area Power Solutions (Pty) Ltd (RAPS), Pretoria. Lars Monsted, Ramboll, Denmark 33 2. SOUTH AFRICAN ENERGY POLICY AND RENEWABLE IPPS The emerging energy supply industry in the Transvaal and Southern Rhodesia at the beginning of the last century was non-regulated and private. A number of independent power companies existed in the time period from 1882 until 1900. Most of these companies operated power stations for a dedicated purpose: the provision of streetlights, or the provision of power to mines. Power systems were not networked but isolated from each other. It is interesting to note that at that time South Africa was already technologically up to standard with the rest of the world: Kimberley had electric streetlights before these were introduced in London. Initially, the use of electric power was largely restricted to illumination and driving small mining equipment. However, in the beginning of the 20th century, the power requirements of the mining companies increased because of increased challenges in the exploitation of gold deposits and availability of new technology. This eventually led to the establishment of the Victoria Falls and Transvaal Power Company Limited in 19061. The VFP bought out a number of independent power companies such as the Rand Central Electric Works and the General Electric Power Co Ltd. By 1915, four thermal power stations had a total installed capacity of 160 MW. The Power Act introduced on 28 May 1910 by the Transvaal Colonial Government limited the future existence of the VFP. It authorised the expansion of the company, but provided for the state's expropriation of all electricity companies after a period of 35 years. This is most likely the first interference of the government in the provision of electricity for control reasons. From then on, government became increasingly involved in the provision of electric power. The government commissioned studies to assess the country's electrification prospects and passed an electricity act in 1922. This was shortly followed by the establishment of The Electricity Supply Commission (ESCOM) in 1923, which was made responsible for establishing and maintaining electricity supply on a regional basis. The above story is not unique to South Africa. All over the world, the development of power supply followed similar events. Electricity was seen to important to the industrial development of nations to leave it totally to the private sector. However, there are two things that need to be considered: The then governments were able to act very swiftly because they were mostly not democratically elected, i.e., they were able to operate in a business-like manner. The power relationship between government and the private sector was very different than it is today. Today, a well-regulated private power sector has internationally proven to be the best vehicle for the provision of sustainable and reliable power supply service. Modern 1 Source: Eskom heritage publication. The Power company was actually first called Victoria Falls Power Company Limited because it had the intention of harnessing the power of the Victoria Falls, a concept that was soon abandoned. 34 governments do not choose to become involved in the operations of power supply companies, but focus on channelling the drive into the direction needed by the country through appropriate regulatory frameworks. 2.1. A historical review 2.1.1. Pre-regulations In the beginning electricity was generated and supplied without any regulation. Available end-user energy consisted of primary energy sources such as coal, wood etc. Electricity was slowly introduced when the discovery of gold on the Witwatersrand in 1886 led to Johannesburg installing an electricity reticulation system in 1891. In 1889, the company Siemens & Halske was granted the concession to supply electricity to Johannesburg and Pretoria. This company also obtained a concession to transmit electricity to the mines of the Witwatersrand in 1894. South African mining companies realised that the power generated by steam engines for street lighting was inadequate for their needs. They joined forces to build small "power stations" to supplement existing supplies of electricity. The notion of a central electricity undertaking gained the support of businessmen, engineers and others. This culminated in the establishment of the Victoria Falls Power Company Limited (VFP) on 17 October 1906. Shortly after the Anglo-Boer War, expert opinion recommended that large centralised power stations would supply more reliable and cheaper electrical power than small dedicated power stations. Power became rapidly and increasingly more important and by 1915 four thermal power stations collectively had a total installed capacity of more than 160 megawatts. South African Energy Policy grew out of a need to control the operation of the first ever power company that operated in South Africa, the VFP. 2.1.2. First power act The Power Act, introduced on 28 May 1910 by the Transvaal Colonial Government, limited the future existence of the VFP. The Act authorised the operational expansion of the VFP, but provided for the State’s expropriation of the company, or any other electricity undertaking, after a period of 35 years. The State viewed the provision of electricity as a public service under its authority. Charles Hesterman Merz, a universally recognised expert in power station design and electrification of railways, visited South Africa in 1918 and 1919 to assess the country’s electrification prospects. A government-appointed committee investigated the implications of the Merz Report. The findings of this committee led to government passing the Electricity Act in September 1922. 35 2.1.3. Establishment of Eskom The government announced in the Government Gazette of 6 March 1923 the establishment of The Electricity Supply Commission (Escom), effective from 1 March 1923. The Commission was responsible for establishing and maintaining electricity supply undertakings on a regional basis. Electricity supplied to government departments, railways and harbours, local authorities and industry was to be efficient, cheap and abundant. In 1925, the Commission obtained four power supply licences. A year later it commissioned two coal-fired power stations. Two years after that, it commissioned two more coal-fired power stations. Despite the serious consequences of an economic depression (c. 1930), Escom’s electricity sales increased though power supply system expansion was delayed. However, the discovery of new gold fields to the west of the Witwatersrand and a rise in the gold price brought new life to the electricity supply industry. Demand from new gold fields in the Orange Free State, and applications from towns, mines and industries for electrical power supply, led to the expansion of Escom’s licensed area by 41 000 square kilometres. 2.1.4. Monopoly of Eskom In accordance with conditions first stipulated in the Power Act of 1910 and included in the Electricity Act of 1922, in 1948 Escom expropriated and took over all assets of the VFP. The monopoly of Escom, later called Eskom, started. Increasing electricity demand from industrial growth challenged Escom in the post-war period. Between 1945 and 1955 the capacity of Escom’s power stations more than doubled. Eskom established a national power network in the 1960s. This network was destined to link the Transvaal power stations with the Cape Province undertaking. 2.1.5. First restructuring of Eskom In 1985, Escom was restructured to meet the electricity demands of a changing South Africa. In 1986 the last White Paper on energy policy was published in the apartheid era. An Electricity Council (appointed by the government) replaced the Electricity Supply Commission (Escom). In 1987, Escom was renamed Eskom. 2.1.6. Post-Apartheid era: NER founded The general approach to policy formulation changed. It and places greater emphasis on transparency, inclusiveness and accountability. In response to democratisation, a number of negotiating processes began spontaneously within the energy sector, usually in stakeholder-based forms such as the Liquid Fuels Industry Task Force and the National Electrification Forum. Government's wish to integrate these and provide policy stability led to it formally launching the energy policy white paper process in 1994. The Government released the Energy White Paper in 1998. 36 Already by 1992, almost one million more people were receiving an electricity supply and 260 electrification projects were underway. Eskom decided that a reduction in the real price of electricity would stimulate economic growth in South Africa. Eskom’s efforts resulted in the lowest tariffs in the world. Low incomes meant people could not afford electricity and therefore used other heating fuels. This contributed to natural vegetation degradation, and increased respiratory diseases from generation air pollution At a National Electrification Forum (NELF) meeting in 1994, the Government adopted a recommendation to replace the Electricity Control Board with a National Electricity Regulator (NER). A levy imposed on electricity generators funds The NER. All customers of electricity pay the cost. Customers of electricity therefore pay for the protection that they receive from the NER, and the general body of taxpayers is relieved of this obligation. (More information about the NER is in chapter 3) The NER was empowered to ensure the orderly, effective generation and distribution of electricity throughout South Africa. Eskom took over the distribution responsibility in a number of municipalities. It continues to devote attention to improving the quality of supply, metering and billing systems. Since 1995, about 800 more households have been connected every working day. 2.1.7. Splitting up of Eskom In February 1999, the Minister for Public Enterprises and Eskom’s Chairman announced that Eskom would be restructured into two main divisions. Eskom’s new strategic intent is “To be a pre-eminent African energy and related services business, with global stature.” Eskom Enterprises was relieved of any regulatory requirements and is positioned to take Eskom’s influence into Africa. Organised labour accepted this restructuring in August of 1999. 2.2. South African Energy Policy The South African government policy pays strong attention to the development of the energy sector, but it also addresses the interdependencies and synergies to other economic sectors. Through these linkages, the energy sector can greatly contribute to a successful and sustainable national growth and development strategy. The new government has adopted a macro-economic strategy, Growth, Employment and Redistribution (GEAR), which aims at promoting growth through exports and investment; and promoting redistribution by creating jobs and reallocating resources through the budget. GEAR replaced the first reform programme devised by the new government, the Reconstruction and Development programme. Energy policy has been recognised as an important factor contributing to economic growth and employment creation aims. The rural electrification targets of the Reconstruction and Development programme are an example of energy policy and social and economic development linkages. The Government corporate governance 37 protocol for state-owned entities, including the energy sector, takes the focus further by including a programme on the restructuring and privatising of national assets. The privatisation drive and the opening up of the South African economy have created a much more complex environment of energy supply, demand and pricing that demand more intricate energy sector decisions. Because the South African economy is opening up, international factors now more transparently influence the energy sector. Significant shifts have occurred in international energy policies since the oil crises. South Africa is gaining valuable information from these international learning curves. Perhaps the most significant international shift is using greater supply diversification and flexibility to achieve energy security. As a consequence the international energy sector is relying increasingly on market-based pricing. To compete in this context, South Africa is intensifying its commercialisation efforts the energy sector. The creating effective and competitive energy markets in a previously monopolistic environment requires setting up regulatory regimes in a speedy and sophisticated manner. The regional integration of South Africa's energy decisions, regulations and operations is an important consideration. In the Southern African region, the Southern African Development Community (SADC) has decided to adopt an energy cooperation policy and strategy. In contrast to other sections of the economy, the energy sector has in many cases larger environmental impacts than most other economic sectors. Due to the heightened awareness of these environmental impacts, investments in energy are increasingly subjected to greater environmental scrutiny. In this context, energy policies increasingly target to reduce emissions and adverse environmental impacts of energy operations and energy usage. One of the avenues pursued is to promote research and development of alternative and renewable energy sources. In recent years several renewable off-grid energy projects have been planned and begun. However, most of these initiatives focus on off-grid renewable energy supply, mainly targeted at small, decentralised units that operate at very high marginal costs and only generate a small amount of the potential energy requirements. 2.3. Renewable energy policy 2.3.1. The Energy White Paper The ”White Paper on Energy Policy for the Republic of South Africa”, published by the Department of Minerals and Energy, December 1998, is the most recent and comprehensive energy policy document for South Africa. One of five energy sector policy objectives is: “Given increased opportunities for energy trade, particularly within the Southern African region, government will pursue energy security by encouraging a diversity of both supply sources and primary energy carriers” (page 12). 38 Some of the medium-term policy priorities are (page 14-15): “Stimulate the development of new and renewable sources of energy” “Adjust electricity market structures to achieve effective forms of competition” “Establish regulations which promote a cost-of-supply approach to electricity pricing for non-domestic consumers” “Investigate an environmental levy on energy sales to fund the development of renewable energy, energy efficiency and sustainable energy activities” The issue on electricity pricing is further elaborated on page 39: “Price signals should result in economically optimal investments in electricity infrastructure and consumption of electrical energy. Government is of the view that this will generally be achieved through the use of cost-based electricity tariffs which include capital replacement costs (long-run marginal costs).” On how quickly this can be achieved, the paper notes: “cost-reflective tariffs will be applied at electricity distributor supply points in due course” (page 40). For non-utility generation, the tariffs shall be approved “on the basis of full avoided costs”. “By including environmental costs into the pricing structure for further development of renewable and environmentally benign generation technologies such as hydro, wind, solar thermal, and waste incineration will also be encouraged”. (page 42). However, “South Africa has to maintain the competitive advantage of low, stable and cost-reflective electricity prices” (page 28), and “recognising that many households are presently unable to afford cost based tariffs, government acknowledges that moderately subsidised tariffs for poor domestic consumers are necessary for equity reasons.” (page 39) On electricity transmission, the White Paper states (page 44): “Government will legislate for transmission lines to provide for non-discriminatory open access to uncommitted capacity, transparency of tariffs, and disclosure of cost and pricing information to the National Electricity Regulator.” 2.3.2. Renewable energy according to the Energy White Paper The advantages of renewable energy are set out in the EWP, particularly for remote areas where grid electricity supply is not feasible. Government believes that in some cases, renewable energy can provide the least cost energy service, particularly when social and environmental costs are included, and will therefore provide focused support for the development, and applications of renewable energy. This narrow view reflects the hesitance of trying out unfamiliar technologies within a changing paradigm of increasing social and environmental linkages and concerns. It is good that the government recognises that renewables can be least cost. It is less clear that the government or electric sector institutions fully understand the relationship between actually including environmental costs in energy decisions, and optimising the benefit cost ratios for energy decisions. It is good news that the government will support production of solar power and non-grid electrification systems, such as the further development of home solar (SHS), solar cookers, solar 39 pump water supply systems, solar systems for schools and clinics, solar heating systems for homes, hybrid electrification systems, and wind power. All of the above will be largely targeted at rural communities. Power from the Cahora Bassa hydroelectric scheme, and other similar options, in southern and central Africa will be tapped, if suitable agreements can be worked out between the participants at government level. Government will promote appropriate standards, guidelines and codes of practice for renewable energy and will establish renewable energy information systems. Government policy on renewable energy is thus concerned with meeting the following challenges: ensuring that economically feasible technologies and applications are implemented; ensuring that an equitable level of national resources is invested in renewable technologies, given their potential and compared to investments in other energy supply options; and addressing constraints on the development of the renewable industry. Government policy is based on an understanding that renewables are energy sources in their own right, are not limited to small-scale and remote applications, and have significant medium and long-term commercial potential. Government will provide focused support for the development, demonstration and implementation of renewable energy sources for both small and large-scale applications. Government will support renewable energy technologies for application in specific markets on the basis of researched priorities. Government will facilitate the production and management of woodlands through a national social forestry programme for the benefit of rural households, where appropriate Government will promote the development and implementation of appropriate standards and guidelines and codes of practice for the correct use of renewable energy technologies Government will establish suitable information systems of renewable energy statistics, where justifiable, and will assist with the dissemination thereof. 2.3.3. The renewable energy strategy of the DME In 1998, on the basis of the long-awaited but not yet published white paper, the DME produced two internal renewable energy strategy papers entitled "Towards an implementation plan" and also "An implementation action plan". The intent of these documents was to further develop and concretise the issues set out in the EWP. The first paper starts out by summarising the availability of renewable resources in South Africa, and setting the requirements into the macro context of the South African socio-economic situation. It gives a list of end-user requirements linked to renewable energy as immediate market areas to be focused on. The list addresses the market areas in terms of institutional and infrastructure support requirements, and also in 40 terms of domestic, agricultural, commercial, and industrial requirements. The items on this list can be grouped into two areas: off-grid energy, with solar playing the biggest role, mainly for underdeveloped rural areas but also for commercial applications such as telecommunications energy efficiency issues, such as passive thermal design of housing The list does not include wind energy or other grid-connected renewable sources, except for co-generation. This is in line with the EWP, which has the same priorities, and reinforces the priorities set out in the EWP. The second paper depicts a prioritisation of issues to be addressed by the DME in form of an eight-point action plan. The eight points are: 1. Establishment of a national energisation agency 2. Accessing the Global Environment Facility and other international resources to expedite renewable energy implementation 3. Implementation of non-grid technologies as a complementary element of the national rural electrification programme 4. Energisation - the provision of rural energy services 5. Passive solar design of houses for thermal efficiency 6. National solar water heating programme 7. A national public education and marketing campaign on renewables 8. Feasibility studies Much attention and detail is given to item number three on this list as it addresses the key objective of the EWP paper in terms of overcoming the inequalities of the past. Item no 8 (feasibility studies) includes wind energy and also specific support for the Darling wind project in the form of facilitating a long-term Power Purchase agreement with Eskom and moral support. Furthermore, the paper recommends the initiation of a process aiming at the development of a national wind energy strategy. Other technologies cited under "feasibility studies" are solar thermal power generation, solar cooking and micro-hydro schemes. 2.3.4. Non-utility generation The EWP encourages the entry of multiple players into the generation market. Initially this policy will be implemented by obliging the national transmission system to publish National Electricity Regulator approved tariffs for the purchase of cogenerated and independently generated electricity on the basis of full avoided costs. The purpose of this policy is to: improve energy and capital efficiencies in the national interest; encourage the development of renewable and environmentally sound electricity generation technologies; and encourage more players to enter the generation industry in order to develop a competitive power market. 41 This policy will enable the economic exploitation of the significant available potential for non-utility generation in South Africa. Research has indicated that a technical potential of as much as 6 000 MW of non-utility generation could be exploited. By including environmental costs into the pricing structure the further development of renewable and environmentally benign generation technologies such as hydro, wind, solar thermal, and waste incineration will also be encouraged. This policy forms part of the integrated resource planning approach to electricity supply. Implementation should thus be overseen by the National Electricity Regulator who will be responsible for finalising the details of the methodology for calculating the full avoided costs of non-utility generation. It is expected that this policy will encourage further energy-efficient generation option exploitation, increase competitive pressures on Eskom and provide the National Electricity Regulator and government with invaluable experience that would be useful should fundamental change towards a market-based electricity supply industry be introduced later. 2.4. The international Framework Convention on Climate Change 2.4.1. South Africa’s position towards climate change South Africa ratified the United Nations Framework Convention on Climate Change in August 1997, just in time to formally participate in the important 3rd Conference of Parties in Kyoto, Japan. In keeping with their communication commitments as a party to the Convention, the SA Government undertook the preparation of an inventory of emissions. In 1990, the base year for emissions reporting, South Africa emitted an estimated (using a top-down method) total of CO2 equivalent an amount of 373,922 Gg/year for the 3 main greenhouse gasses, CO2, CH4 and N2O. This excludes the amount sequestered in woodlands and plantations (20,614Gg) in the same period. Of the emissions the 37.7% is attributed to electricity generation and 89% of the CO2 equivalent is emitted in total from the energy sector see table 1 below, which shows an estimate of emissions based on a bottom up approach: Table: 1990 emissions in South Africa Source Amount Gigagrams Electricity generation 137,333 Heat production 31,669 Manufacturing 25,498 Transport 33,754 Other energy 25,492 Fugitive 36,146 Industrial processes 24,165 Agriculture 41,254 Waste 8,910 % of total in 1990 37.7 8.8 7.0 9.3 7.0 9.9 6.6 11.3 2.4 42 South Africa is by far the largest emitter of GHGs in Africa and is as such considering its leadership amongst African countries amongst the G77 + China negotiating block. However, South Africa’s recent ratification of the Convention has resulted in a rather uncertain start in climate politics manifested in the current scramble for policy direction currently co-ordinated through the multi-sectoral advisory body, the National Committee on Climate Change (NCCC). The Deputy Minister of Environmental Affairs and Tourism, Ms. R. Mabudhafasi delivered the Government’s view on Climate Change Policy in the National Assembly on 6th June 2000. “SA’s ratification of the FCCC signifies government’s commitment to join the global community finding solutions to the escalating greenhouse concentrations in the atmosphere.” The Deputy Minister proceeded to list 3 areas where action would be taken including lighting and heating in homes, energy intensive industries and the export sector. She also pointed to “collective action” between minerals and energy, trade and industry, water affairs and forestry, transport, and agriculture culminating in a “Response Strategy which outline has been approved by Cabinet and is due for finalisation in December 2000.” What is clear from these policy statements is that, despite SA being a non-annex 1 country and therefore not obliged under the convention to meet emissions reductions targets, it realises its exposure to markets where emissions reductions commitments have been made. In operationalising these commitments the fossil energy intensity of these economies will have to be reduced, impacting on oil and coal imports and potentially the embodied energy intensity of imports to committed markets. On both counts SA with its coal energy intensive economy appears to be threatened and wants, prior to sanctions being imposed, to show that it is seriously undertaking an overhaul of its emissions. But then also not too seriously, as SA does not want to sell off the “low-hanging fruit” or cheap mitigation options. Nor does SA want to reduce the “dirty” baselines, prior to the second commitment period beyond 2012, by which time, no doubt, some level of commitment from non-Annex 1 countries would have been negotiated. For the climate-related project developer this approach poses a difficult balancing act. The task is to design sufficiently large projects to be taken seriously, but not to do so much as to be accused of “eating the low-hanging fruit”. It is also important not to shift the baseline lower (in effect shifting the average in such a way as to lower the future certified emissions reductions.) On the other hand, the project developer would also like to galvanise increased investment in response to climate change, initiating domestic action that delivers cleaner services rather than banking on future options. In effect, banking this opportunity would be to sentence countries and their citizens to dirty and costly production methods and unhealthy living conditions in the short term. Alternatively if the ratified Kyoto protocol allows for it, unilateral investments and the banking of credits could occur in non-Annex 1 countries. This type of approach would be consistent with the technology transfer commitments expressed under the UNFCCC articles 4.2 and 4.3. Here, developed country parties commit themselves to providing “such financial resources, including for the transfer of technologies, needed by developing country Parties to meet the agreed full incremental costs of implementing measures that are covered by paragraph 1”. 43 2.4.2. State of the art of the CDM mechanism Very little can be said about what has been decided about the CDM other than what is written in the Kyoto Protocol predominantly under article 12. However, an unprecedented intensity of debate has surrounded this flexibility mechanism since it was given skeletal form in Kyoto. The CDM mechanism allows annex 1 and nonannex 1 countries to combine efforts in a “common but differentiated” effort to reduce emissions. In short, the CDM is unprecedented in that it elevates the issues of climate and sustainable development to the same level. The CDM allows Annex 1 countries to invest in carbon mitigating efforts in the non-annex 1 countries in order to supplement their domestic actions in meeting their commitments. CDM projects are obliged to contribute to sustainable development in reducing emissions. Key unresolved issues are: How much activity should supplement domestic action should be allowed? Should CDM be the only mechanism levied to cover the costs of adaptation? What baseline methodology should be used for assessing emissions reductions and sustainable development? Who should measure quantities of emissions reduced and contributions to sustainable development? What technologies should not qualify? Large dams? Nuclear plants? Clean coal? Oil production/refining efficiencies? Sinks? Will CDM supplement existing Official Development Assistance and Global Environment Facility grants? Will CDM find destinations in the least developed countries? Or will a regional quota be required? If so how will the Private sector respond to this and other rules that they fear will contribute to overly costly transaction costs? Will uni-, bi and multilateral modalities be allowed for CDM? What will be the penalty for meeting emissions reductions obligations under the protocol? What is clear is that grid connected renewables are probably one of the safest options that will satisfy the requirements of CDM. They will reduce emissions and contribute to sustainable development (at least in terms of employment creation and reducing local emissions.) and have baselines which are fairly simple to estimate with accuracy. The CDM has been a beacon of hope for those interested in stemming the shrinking streams of Official Development Assistance (ODA). The debate has shifted from one of collaboration with the south in assisting the north, to one of undue haste required in getting the streams of finance to start flowing to all manner of infrastructure projects that are primarily focussed on development with climate a secondary motivator. Expectations are high on what the CDM will deliver – optimistic estimates put flows of resources between US$24 and US$37 billion over the next 10 years. Whatever happens CDM will take further shape in Lyon in September 2000 and Den Haag November 2000, and beyond that to Rio +10 (2002) by which time, it is hoped, and the EU are lobbying for this, the Kyoto Protocol and with it the CDM, will be ratified. CDM projects, however can be credited retrospectively from the beginning of 2000 on despite the protocol having not being ratified. 44 The Subsidiary Body For Scientific And Technological Advice reported (meeting in Lyon, September 2000) that the Parties were able to reach agreement on the following key themes: technology needs and needs assessments; technology information; enabling environments; capacity-building; and mechanisms for technology transfer. 2.4.3. The potential role of the CDM in the promotion of renewables It is most likely that the international market for carbon will establish the price paid for CO2. If this assumption proves correct, the price will be exposed to the varieties of supply (how many and how big the projects) and demand (the interest of credit buyers and technology transferors and proximity to targets and to the end of commitment periods). However, in establishing what price will be paid for Greenhouse gases in the design of renewable energy projects, there are a few pointers that could assist the project designers: The Dutch Energy Research Foundation (ECN) estimates, based on 79 AIJ projects, that suggests that prices between US$4 and US$10/ton CO2 equivalent are reasonable. The Dutch Government, through their Department of Foreign Affairs, is offering US$10/ton for carbon through both JI and CDM equivalent routes. The World Resources Institute quotes Zhang’s estimates of prices between US$3.50 and US$12.6/ton of carbon, depending on the policy scenario. He then quotes the Dutch purchase tender for Emissions Reduction Units (ERUs) (not Certified Emissions Reductions (CERs)). between EUR 4.54 to 9.08 per ton CO2 (not carbon). UNFCCC reports talk of abatement costs (not market prices) of between US$4 and US$8(per ton CO2) for AIJ afforestation and deforestation projects. A quick calculation using say US$10/ton CO2 would in wind project developed in South Africa (coal powered electricity baseline) results in a subsidy of US$ 0.01131/kWh (at SAR 7 per US$ this is equivalent to SAR 0.08/kWh2). Over the life of the project, this would imply a 20% subsidy of the capital cost of wind turbines. This constitutes a considerable subsidy to a renewables project. (See calculations presented in annex 1) 2.4.4. CDM benefits for renewable IPPs The SA delegation to attend the Lyon 13th Subsidiary Body meeting will be presenting inputs to the debate on vulnerability and adaptation, contained in articles 4.8 and 4.9 of the UNFCCC and 3.14 of the Kyoto Protocol. The introduction of the draft SA position reads “South Africa’s vulnerability is not only confined to the negative impacts of climate change itself, but also to mitigation actions taken by Annex 1 countries. It is clear that in terms of vulnerability, South Africa meets five of the seven criteria set out in Article 4.8, in particular sub-paragraphs (e) and (h).” Under the title Adverse Impacts and Response Measures the text continues as follows: “The initiation of concrete actions aimed at the diversification and expansion of the 2 This is higher than the short run marginal costs of electricity production in South Africa! 45 economies of non-Annex 1 countries highly dependant on fossil fuels by the use of inter alia, the financial mechanism under the Convention and the flexibility mechanisms under the Kyoto Protocol, especially the Clean Development Mechanism.” These mechanisms can be used to facilitate, in particular, the transfer of technology. This can be achieved by (amongst others): Conducting technology needs analyses (through regional or national centres). The national priorities and needs of countries should dictate technology choices. Criteria for the acceptability of technologies should be established by individual countries in order that they meet specific needs and are proven for the particular application.” The South African delegation appears determined to argue to the international community that its use and export of coal not be tampered with. This approach understandably creates a tension between SA and the spirit of the convention akin to that of the oil dependent countries. The extent to which CDM will improve the competitiveness of renewable energy depends upon the price the renewable energy generated electricity is sold at. If for example Eskom purchases the electricity at the avoided cost of mining coal and transporting this to the Mpumalanga power stations, the short-run marginal cost of electricity generation would be in the order of SAR0.02 per kilowatthour. The renewable energy producer could argue that replacement cost of the proposed pebble bed reactors proposed for the western Cape. The costs of production for these prototype plants are in the region of US$0.0243 and 0.0427 per kilowatt hour (Eskom and MIT estimates presented in the World Energy Assessment 1999). Income from sales of electricity is estimated between 10% and 70% of the costs. In both cases a subsidy of 20% is significant. Alternative scenarios could include the sale of the electricity to a private purchaser who is interested in an export market in which renewable energy fuelled production processes carry addition value. Finally, there exists a possibility of sale of electricity to municipal electricity distributors. In this last case the principle would undoubtedly be where the customers would not be penalised by higher prices than that which the municipality would otherwise pay for the renewable energy generated electricity. 2.4.5. Requirements to policy framework and regulatory framework Key to government policy implementation would be to remove barriers to the increased use of renewables and to set achievable goals for the contribution of renewable energy to the national energy mix. It is hoped that these issues will be raised in the country and policy studies currently underway in South Africa. Barrier removal could be in a number of areas, including financial, institutional, human capacity, and technical. The global environment facility would readily provide support to undertake barrier removal projects if government was in accord. The second main policy area is to set goals. The government needs to be convinced that a move towards renewables is consistent with using South Africa’s international competitive energy advantages and does not threaten the SA economy. Rather, the use 46 of solar and wind energy puts the country on a path that utilises another of South Africa’s abundant naturally occurring resource advantages. To convince policy makers that the future of energy will shift towards renewables as a result of international governance in the climate and at a national level, the use of non-tariff barriers as a way of protecting markets and limiting unwanted additions to the carbon emissions inventory. The incentives in the form of GEF support and the potential to describe the projects as qualifying for CDM will all add to a sustainable argument. 2.5. Policy barriers and deficits The post-apartheid economy and correspondingly also the energy white paper are characterised by a comprehensive set of demands from different sides. These can be summarised as follows (as outlined in the energy white paper): 1. 2. 3. 4. 5. Increasing access to affordable energy services Improving energy governance Stimulation of economic development Managing energy-related environmental and health impacts Securing supply through diversity Notably, some of the most important issues relevant to Renewable Energy IPPs are clearly and specifically supported in the EWP: Government will encourage competition within energy markets (EWP page 12) Government will provide focused support for the development, demonstration and implementation of renewable energy sources for both small and large-scale application (EWP page 91) Government will support renewable energy technologies for application in specific markets on the basis of researched priorities (EWP page 91-92) What the EWP does not address, however, are more proactive and practical issues as to how the above goals of implementation of renewable energy power production will be achieved. Because of the emphasis on economic viability in the short-term, the priorities of the renewable energy policy are showing a clear focus on the provision of off-grid energy for rural areas. In addition, Eskom presently has a substantial over capacity which is partly a result of poor planning and partly because of the Asian crisis since 1997 which has resulted in a significant drop in demand and prices for resources (metals and other). Asia, and in particular Japan, is one of the top export region for resources and since the Japanese economy is still stagnating, resource prices and production in South Africa have not yet reached their pre-crisis levels. Because of the energy-intensive nature of the mining industry, this results in a significantly lower energy demand and thus excess capacity. On the other side, Eskom has taken steps to address the electricity planning for the long term. It has embarked on a project investigating a number of technology options 47 for future electricity generation, of which the nuclear technology was favoured. In the light that international trends are clearly phasing out this technology for a number of reasons, it is not clear, whether sufficient foresight and a non-biased decision process have been employed, when evaluating the options under investigation. Generally, the EWP and renewable energy policy in South Africa have the following shortcomings: There is too much technology focus. The real challenges for South Africa, however, are embedded in the management of technology and not the technology itself There is too much focus on investigating the feasibility of options. Many of the technologies are mature and could readily be demonstrated in order to be gain experience and understanding of costs and benefits in the South African context. There is not sufficient focus on renewable energy overall as a long-term energy solution. The EWP sees renewable energy as something the development of which 'must be monitored' Although not being very specific about the topic, the EWP does not seem to include grid-connected renewable energy as a priority technology. In summary, the EWP is very broad and all-inclusive. There is not sufficiently clear commitment towards specific strategies and solutions, as the paper tries to accommodate everything and everyone. It is clear that decisions will have to be made that require more specific policy support A last point worth mentioning is the lack of public debate in South Africa. Internationally, renewable energy implementation, and in particular grid-connected power schemes, has been driven bottom-up by an informed urban population. Except for a small minority interested in renewable energy, the issue is not top of the agenda for a large part of society as it is in many other countries. Together with the facts that South Africa has excessive surplus generating capacity, little environmental awareness, and a great deal of economic problems, bulk renewable energy systems are seen as something that does not address the problems at hand. References: 1. 2. 3. 4. Andrei Ileana. Personal communications 2000. Dutch Energy Research Foundation (ECN). Personal communications 2000. Eskom 1995. Eskom Statistical Yearbook, 1994. Fecher R 1999. Financial protocol for South Africa’s climate change mitigation assessment. Energy & Development Research Centre. University of Cape Town. 5. International Energy Agency 1999. 6. World Energy Assessment 1999. Chapter 8: Advanced Energy Technologies, UNDP, UNEP and World Energy Council, Second Draft Report. October 1999 7. Zhang. Personal communications 2000. 48 Annex 1: Windmill substituting coal power Coal power Net electricty efficiency Heating value Fuel consumption Specific CO2 emission - do - do - % Eskom GJ per ton fuel Eskom kg coal per kWh electricity derived Eskom kg CO2 per GJ Coal Ref: IEA kg CO2 per kg fuel = 0.526 kg C per kg fuel kg CO2 per kWh electricity ratio of produced to available electricity derived Eskom % kg CO2 per kWh electricity 1.03464 Fetcher et al 1999 Price of CO2 Subsidy 34.4 20.09 0.521 96.0 1.93 1.00 0.987 10 1.131 0 10 0.01131 Windmill Capacity Service life Capital cost Operation hours Generation Annual subsidy Total subsidy in percentage of cap. cost 300 20 600000 1752 525600 5943 118867 19.8 kW years USD hours full load per load kWh/year USD/year USD % (no inflation) Transmission losses CO2 reduction at windmill USD per ton USD per kWh electricity 49 3. LEGAL, INSTITUTIONAL AND REGULATORY SET-UP OF THE POWER SECTOR 3.1. Overview The regulatory environment in South Africa for the electricity sector is characterised by a number of loopholes and gaps. Historically, electricity and liquid fuels regulations are separate, although international trends have sparked a debate that this separation may not be warranted any longer. The electricity supply industry is regulated by the National Electricity Regulator (NER), which was established by the Electricity Act No. 41 of 1987. The NER's routine regulatory activities include licensing, tariff approval, handling of disputes and customer complaints, monitoring the quality of supply and service standards and others. Although, the development of regulations being a crucial area, the lack of clear energy legislation has resulted in all stakeholders relying on informal and dynamic relationships for the development of regulations. 3.1.1. Governance structure The governance of the electricity sector is shown in Exhibit 1. The Minister of Minerals and Energy directly heads the Department of Minerals and Energy, whereas an independent board appointed by the same Minister controls the NER. Eskom is even more independent as it is governed by a board and by the Electricity Council, which is appointed by the Minister of Public Enterprises. In effect, the government has very little control over Eskom and relies solely on energy legislation for providing direction and regulation. 50 Exhibit 1: Governance of the DME, Eskom and the NER South African Cabinet Minster of Minerals and Energy Minster of Public Enterprises appoints appoints heads appoints NER Board governs Department of Minerals and Energy Prepares and suggests energy policy and legislation to cabinet for presentation to parliament Electricity Council National Electricity Regulator Develops regulatory frameworks and governs the electricity sector according to the legislation and policies provided Eskom Board governs Eskom Provides electricity within the regulatory frameworks developed by the NER The DME prepares and suggests energy policy and legislation to Cabinet for presentation to parliament. At present, there is not sufficient capacity at the DME to adequately handle the task of translating the policies set out in the EWP into corresponding legislation. For this reason, the DME to a high extent relies on consultants to accomplish this task. However, the process of appointing consultants is complicated and lengthy since there is a number of external stakeholders such as the state tender board involved, which can reject the candidate of choice for a number of reasons. 51 Exhibit 2: Process flow for the development and implementation of energy-related legislation Department of Minerals and Energy Cabinet Prepares legislation in form of bills to cabinet Draft Energy Bill Parliament Presents bills to parliament Energy Bill Votes bills into being Energy Act The NER, through its existing mandate to advise the Minister of Minerals and Energy, can develop regulatory frameworks and governs the electricity sector according to existing legislation. The Minister then may implement the regulations. The existing legislation, however, does not adequately address the issues involved in the development of a free energy market, including renewable energy. Even though the Electricity Act gives the Minister a broad range of possibilities with regard to regulation, there is a strong need for direction in form of new energy legislation for the NER to develop effective regulatory frameworks. Furthermore, the NER in its present form is only five years old and has spent much of its energy building human resource capacity. Many of the present managers and experts have been recruited from Eskom as more or less the only local source of expertise in the field. In addition, the NER had to devote much of its activities towards sorting out internal problems in which it got into crossfire for financial mismanagement. Exhibit 3: Process flow for the development and implementation of energy-related regulation National Electricity Regulator Minister Advises the Minister on Creates Draft Energy Regulation Energy Regulation 52 The National Electricity Regulator (NER) The NER writes about itself: The NER is the regulatory authority over the electricity supply industry (ESI) in South Africa. It is a statutory body, established in terms of the Electricity Act, No. 41 of 1987, as amended by the Electricity Amendment Acts of 1994 and 1995. The NER was established on 1 April 1995 as the successor to the Electricity Control Board. The Minister of Minerals and Energy appoints board members but, once appointed, the NER acts independently and reports to parliament.3. This means that the Minister of Minerals and Energy has no influence on the day-today operations of the NER. Furthermore, it appears that: 1. The reporting structure and frequency to parliament is not clearly defined. 2. The mandate of the NER is not clearly defined in terms of which areas of the ESI it covers. The Electricity Act of 1987 (as amended by subsequent acts4) stipulates that the NER may be asked by the Minister of Minerals and Energy to furnish the Minister with information. Furthermore, the NER has the right to advise the Minister, as stipulated in the act under 4 (4): The regulator may advise the Minister on any matter relating to the electricity supply industry and it may for this purpose carry out such investigations as it or the Minister deems necessary. The above implies that while the Minister has no direct control over the NER, she can to some extent ask the NER to carry out investigations regarding the ESI. However, only the Minister has the powers to produce regulations. The shortcoming of this structure is a potential deadlock as the Minister might wait for the NER and the NER for the Minister, to develop and implement regulations. In other words, there is no clear functional process flow for the development and implementation of electricity regulations. It is also noteworthy that the act does not specifically address the issue of licensing transmission systems, separately from distribution systems. The matter of transmission is of particular importance to the formation of IPPs. 3.1.3. ESKOM governance ESKOM itself states about its governance: "ESKOM is governed by the Electricity Council and a Management Board, established in terms of the ESKOM Act of 1987. The Council determines 3 Source: NER web site 4 Amended by the Electricity Amendment Act 58 of 1989, the Abolition of the National Energy Council Act 95 of 1991, the Abolition of Racially Based Land Measures Act 108 of 1991, the Electricity Amendment Act 46 of 1994, the Electricity Amendment Act 60 of 1995, and the Abolition of Restrictions on the Jurisdiction of Courts Act 88 of 1996 53 policy and objectives and exercises control. The Board manages the affairs of ESKOM in accordance with the policy and objectives determined by the Council. Although ESKOM therefore has a separate supervisory and management board structure, the Council and Board are fulfilling the role of directors and have a collective responsibility to provide corporate governance5 The Minister for Public Enterprises appoints the members of the Council. Appointments are for a maximum of five years or a shorter period as determined by the Minister at the time of appointment. With the exception of the Chief Executive and the Executive Directors of Finance and of Human Resources, all the members of the Council are non-executive and represent a wide range of stakeholders. All Council members are actively involved in, and bring independent judgement to bear on Council deliberations and decisions." The above speaks for itself. It means that the Department of Minerals and Energy has very little control of ESKOM. 3.2. The restructuring of the electricity supply industry The South African government is currently considering implementing great change into the electricity distribution industry (EDI) and the electricity supply industry (ESI). The overall objective of reform in the EDI is to consolidate/rationalise a fragmented industry, while the overall objective of reform initiatives in the ESI is to create a more efficient, effective industry to supply power. In this chapter, we review government plans for reforming the South African power sector. This chapter then describes the implications of these various reforms for the bulk supply of renewable energy. This is done in the context of where – as is the case now – there are very limited initiatives (if any) in place to promote bulk renewable energy generation. The same exercise is done for the context in which various mechanisms are in place to promote bulk renewable energy generation. Taking these potential impacts into account, recommendations in Chapter 8 on how to protect bulk renewable energy generation in new power contexts are presented. 3.2.1. Government’s plans for power sector reform Introduction Government is currently considering implementing reform initiatives in both the Electricity Distribution Industry (EDI) and the Electricity Supply Industry (ESI) of South Africa. Reform of the EDI is being initiated primarily because the industry is fragmented, with many distributors not being financially viable. ESI reform follows international trends whereby competition and greater private sector participation is being called for. These two processes are likely to proceed simultaneously, thought it seems reasonable to assume that ESI reform initiatives will take longer to implement – especially, that is, if all customers are eventually granted choice of power supply. 5 Source: Eskom's web site 54 Rationalisation of the Electricity Distribution Industry South Africa’s electricity distribution industry is currently unable to achieve its primary objectives of meeting the aggressive electrification targets, ensuring world class supply quality, and providing low-cost and equitably-priced electricity to all consumers. As noted in the White Paper on Energy Policy for the Republic of South Africa (1998), this is because of the following: The industry is highly fragmented. Currently more than 120 municipalities have less than 1 000 customers and more than 90 municipalities have revenue of less than R1 million per annum; There are substantial differences in the financial health of municipal distributors. Four municipalities earn 50 per cent of the total surpluses being earned by all municipal distributors and an additional 18 municipalities earn another 25 per cent of the total surpluses. At the other extreme 289 municipalities earn less than 1 per cent of the total surpluses, and the bottom 25 per cent of municipal distributors lose money on their electricity sales. There is a wide disparity in the prices paid by the various customer segments that cannot be fully explained by the costs associated with serving these segments. For example, mining customers pay anywhere from 9 to 17 cents per kWh in Gauteng and anywhere from 23 to 32 cents per kWh in Mpumalanga. Price disparities for other customer segments are as wide. Economies of scale, skill and specialisation are not being captured by many of the small distributors. Average distribution costs (including purchased energy) range from 23.9 cents per kWh for distributors of less than 1 GWh in annual sales to only 13.4 cents per kWh for distributors of more than 1000 GWh in annual sales, a 46 per cent difference in costs. Electrification needs are not evenly distributed across regions with some of the poorer regions having the greatest need. Without explicit or transparent funding mechanisms there is a great risk that in times of tight resources many distributors will not be able to fund their targets. Moreover, as electrification is a national objective, cross-regional subsidisation should be considered as an equitable way to fund the electrification program. While there are many distributors that are not financially viable today, collectively the industry is able to fund both the supply of electricity and electrification over the long-term. However, if the industry is expected to both contribute to funding other municipal services (as it does currently) and to pay for the electrification programme over the long-term, the electricity distribution industry will experience financial bankruptcy without alternative funding and pricing mechanisms, a reduction in the generation and transmission prices (i.e. the wholesale price of electricity), or substantial increases in tariffs. Even if the price municipalities pay for energy is reduced to the price paid for energy by Eskom distribution, the collective position of the industry will not change. The current Eskom distribution surplus will just be transferred to municipalities, without changing the overall cashflow problems for the industry as a whole. The current structure and funding mechanisms characteristic of the distribution industry put it at significant risk. It is already not meeting the objective of providing low-cost and equitably priced electricity to all customers, and financial health continues to rapidly deteriorate. This is evidenced by an increasing number of 55 municipalities who are unable to pay their bulk accounts to Eskom, as well high prices, poor quality of supply in many areas and problems with the delivery of electrification. The South African Government believes that EDI reform should be undertaken in order to: ensure electrification plans are implemented; provide low-cost electricity; facilitate better price equality; improve the financial health of the industry; improve quality of service and supply; foster proper co-ordination of operations and investment capital; and attract and retain competent employees. To address these concerns, Government now plans to consolidate the EDI into a maximum number of financially viable independent regional electricity distributors (REDs). Government’s appointed technical advisors of this particular initiative, PriceWaterhouseCoopers, recently released a working paper (PriceWaterhouseCoopers 2000) detailing views that have emerged following extensive (yet ongoing) analysis and various stakeholder meetings. A selection of these views is listed below. On RED definition, it is suggested that between five and fifteen REDs should be established, with six REDs being the most favourable option. Each RED should contain a major economic centre, and those RED boundaries should be consistent with the new municipal boundaries and the electrical configuration of the network, as well as take cognisance of geographical constraints. On ownership, it has been provisionally suggested that shares should be used to compensate existing distribution undertakings for the value that they contribute to the REDs. On governance and legal status, it is provisionally recommended that each RED be controlled by its own professional Board of Directors, elected by its shareholders. Furthermore, the REDs should be established as companies incorporated in terms of the Companies Act. National government should be responsible for setting and monitoring implementation of policy for the electricity sector as well as ensuring, through regulation, that municipalities perform their functions effectively. On commercial arrangements, REDs should purchase generation and transmission services by means of a regulated Wholesale Pricing System (WEPS). The WEPS would contain separate generation and transmission components, both of which would be regulated. Once the wholesale energy market is established (see below), REDs would be allowed to purchase from this market. The regulatory regime would provide REDs with an incentive to minimise the cost of energy purchased on behalf of their customers, and would limit cross ownership between REDs and generation companies so as to encourage energy purchase to be made on a fully commercial basis. The NER would continue to regulate the price charged for access to the transmission network. Under this arrangement, some large industrial customers would be eligible to choose the company from which they purchase electricity. On regulatory arrangements, the new regulatory regime for the EDI should provide a role for local government (as envisaged in the Municipal Systems Bill) 56 to complement the role of the NER. Local government would be involved in micro regulation of the RED in its area to meet its legal and constitutional obligations, and the NER would be concerned with macro regulation of the whole EDI with a view to meeting national objectives for the industry. The “end-state” regulatory regime for REDs would include: (i) separate regulation of (and licences for) distribution activities, captive market retail activities and contestable market retail activities; (ii) efficiency incentives for the distribution business and the captive market retail business of REDs through regulation of the allowed revenue for each RED; (iii) tight monitoring and performance against quality of supply and quality of service standards. The South African Government recognises that in order to implement the end-state model of independent REDs from the present fragmented EDI, a transitional process is required. The transitional structure, which is likely to be in existence for two years, will consist of Eskom Distribution as well as municipal distributors, and will be a separate company from Eskom Generation and Transmission, including other municipal services. Without substantial increases in tariffs, major reductions in distribution costs, or the curtailing of the electrification programme, it is furthermore recognised that this rationalisation and restructuring process alone will have limited impact on improving the overall financial health of the industry. It is for this reason that the White Paper on Energy Policy states that “the entire industry (generation, transmission and distribution) must move to cost-reflective tariffs with separate, transparent funding for electrification and other municipal services.” Reform of the Electricity Supply Industry For some years now, the Government of South Africa has been considering implementing significant change in the electricity supply industry (ESI). As explained below, proposed changes follow international developments where competition has been introduced into generation sectors, as well as in the retail services component of the distribution industry, and where greater private sector participation in the power sector has been encouraged. To date, very little change has in fact been implemented. Indeed, there is still a generation oligopoly, transmission monopoly and the distribution is highly fragmented. Discussions on how best to design and implement reform measures have, however been numerous. These are outlined below. The White Paper on Energy Policy for the Republic of South Africa (1998) notes that, internationally, benefits have been observed on the introduction of competition. These include: increased opportunities to exploit cheaper and environmentally benign generation options; the potential to increase the level of supply security, at a lower cost, through a regionally integrated and diversified supply base; the potential for efficiency improvements; and the potential for downward pressure on electricity prices. The White Paper notes however that in some countries concerns have been raised about the adverse impacts increased competition has had on equity and environmental goals, as well as the ability of a competitive market to ensure sustained investment and security of supply at low prices in the long term. 57 In consequence of these concerns, the Government of South Africa adopted in 1998 a fairly cautious policy position that it would “support gradual steps towards a competitive electricity market while investigations on the desired course of action [were] completed”. Interestingly, though, the White Paper also notes that “… various developments [in the electricity sector] will have to be considered by government over time, namely: Giving customers the right to choose their electricity supplier; Introducing competition into the industry, especially the generation sector; Permitting open, non-discriminatory access to the transmission system; and Encouraging private sector participation.” The first bullet point above describes a power sector where there is retail competition. The second bullet point calls for wholesale competition, and the fourth could entail privatisation – perhaps of existing assets (strategic partnerships), or perhaps of private participation in new assets. Since the publication of the White Paper there has been considerable debate and analysis on whether and/or how to restructure (or unbundle) Eskom, introduce competition into the generation sector, and encourage greater private sector participation in the power sector in general. It was stated in the White Paper that “any market restructuring is likely to be delayed for a number of years while the distribution sector is restructured and the bulk of the electrification programme is undertaken”. However, it seems now that ESI restructuring may even occur in parallel with these two processes. With a pressing need6 to make further progress in the area of ESI reform, the DME recently commissioned a paper on “A Competitive Electricity Market for South Africa.” The overall argument of this paper was that because of current inefficiencies, the electricity industry should be reformed, and that the new structure should be based on a competitive market system. Furthermore, restructuring should occur prior to substantial privatisation. The paper concludes with the following steps for initial restructuring: The corporatisation of Eskom; The separation of Transmission into a state-owned company and the establishment of a power exchange and a system operator within this framework; The separation of Eskom’s power stations into a sufficiently large number of independent competing generating companies directly owned by the State. In August 2000, the Ministry of Public Enterprises unveiled its Accelerated Agenda for the Restructuring of State-owned Enterprises. Actions by Government vis-à-vis Eskom include the following: Eskom will be corporatised, with Transmission, Distribution and Generation each forming a separate corporate entity; 6 Pressures to make further progress came from various sources including recent statements by the Ministry of Public Enterprises indicating Governments wish to proceed with the restructuring of the four largest state-owned enterprises, one of them being Eskom. Pressures also came from the fact that some progress had been made in the rationalisation of the EDI, as well as a need for follow through/clarification on the various far reaching policy statements contained within the White Paper on Energy Policy (1998). 58 A full evaluation of the different models for restructuring Eskom is currently being undertaken by the Department of Public Enterprises, based on a review of the electricity supply industry undertaken by the Department of Minerals and Energy Different generating companies will be formed to promote internal competition prior to the introduction of private sector participation in generation, in conjunction with new power requirements; Strategic equity partners will be introduced into different Eskom Enterprises business units. The Ministry of Public Enterprises notes the following: The separation of Eskom into separate Generation, Transmission and Distribution companies will result in more transparency and accountability in the electricity supply industry. Different generation companies will ensure that there is competition in generation, which should result in enhanced efficiency and therefore effectiveness in this sector; Government is aware of the social services offered by Eskom in terms of the provision of electricity to the poor in both urban and rural areas. The restructuring plans will ensure that the rollout of electricity to these sections of the population continues. Probable reform path for the Electricity Supply Industry It must be emphasised that few decisions have been made on the appropriate model for ESI reform and indeed that the way forward for ESI reform remains open-ended. However, it seems currently likely that ESI reform will follow the logical steps as illustrated in the generic models illustrated by Figures I, II and III. Industry models Figure 1 below illustrates the Purchasing Agency model whereby Eskom continues to dominate the electricity industry, controlling Generation, Transmission and the unregulated Eskom Enterprises. Essentially, this model is representative of a nearterm situation since Eskom is currently being corporatised, and the distribution industry is soon to be rationalised into a small number of financially viable REDs (Eskom Distribution will be transferred to the EDI Holdings Company and then into the REDs). 59 Eskom Holdings Eskom Generation Internal Pool Eskom Transmission Eskom Enterprises IPP RED 1 RED 2 RED 3 RED 4 RED 5 RED 6 Large customers Customers Figure 1: Purchasing Agency Model Source: Adapted from Hunt & Shuttleworth (1996) Under the Purchasing Agency Model, any new generator entering the market would sell power to Eskom. Government would find it difficult to attract new investments into the industry, as investors would be concerned about the inherent conflict of interest in Eskom, as the owner of Transmission and owner of various generation plants. Open, non-discriminatory access to the system would not be guaranteed. At a minimum, new Independent Power Producers (IPPs) would demand long-term Power Purchase Agreements (PPAs) which could result in consumers being tied to noncompetitive prices for years to come. It is broadly accepted that Purchasing Agency Model cannot last indefinitely. According to the Generation Oligopoly model, Eskom will continue to control Generation and Eskom Enterprises. Eskom Generation units are grouped into different clusters, or operating divisions, under the control of Eskom Holdings. These different operating divisions would however, bid separately to sell power into the pool. Transmission is established as a separate state-owned company. It seems likely that this will occur in the near future. An external, transparent power exchange is also established. 60 Eskom Holdings Generation 1 Generation 2 Generation 3 Eskom Enterprises Power Pool IPP State-owned independent transmission company RED 1 RED 2 RED 3 RED 4 RED 5 RED 6 Large customers Customers Figure II: Generation Oligopoly Model Source: Adapted from Hunt & Shuttleworth (1996) In the Generation Oligopoly Model, there is general concern that Eskom Holdings would be able to exert excessive market power through its subsidiaries. Without regulatory support, investments in large independent generation plants would therefore still be unlikely. According to the Wholesale Competition Model illustrated in Figure III below, Eskom would be left with a highly diluted portfolio of generation assets (in addition to Eskom Enterprises). The remainder of generation would be separated into competitive independent companies. These could be privatised through, for example, black economic empowerment provisions, an initial public offering or a private equity offering. Eskom Holdings Generation 1 Generation 2 Generation 3 Eskom Generation Eskom Enterprises Power Pool Internal State-owned independent transmission company RED 1 RED 2 RED 3 RED 4 RED 5 RED 6 Large customers Customers Figure III: Wholesale Competition Model Source: Adapted from Hunt & Shuttleworth (1996) Retail competition could be introduced at this stage (or perhaps even earlier). This process would entail separating out the natural monopoly ‘wires’ business from retail services at distribution level. It is unlikely that this will occur in the next decade. 61 Reform processes For clarity sakes, the reform processes outlined above can be broken down into ‘unbundling’, ‘corporatisation/commercialisation’, ‘competition’ and ‘privatisation’ initiatives. These are outlined below, and will be utilised in the explanation of possible impacts of power sector reform on bulk-generated renewable energy resources. * Unbundling. In a pure sense, unbundling (or restructuring) electric services is accomplished by breaking out the components of traditional bundled services, assigning existing costs to the various service components, and developing prices based on these costs. As noted, in the short- to medium-term, Eskom will be unbundled into separate Transmission, Distribution and Generation companies (see Figures I, and II above). This will occur as a natural consequence of the EDI rationalisation initiatives, as well as the drive to introduce fair competition into the wholesale power market. In other words, Eskom as a vertically integrated natural monopoly will cease to exist. In preparation for this, financial and operational structures of Eskom Transmission, Eskom Generation and Eskom Distribution have been ringfenced. * Commercialisation and corporatisation. When government decides to commercialise a state-owned enterprise, it essentially relinquishes detailed control, in favour of autonomy for the enterprise and a focus on profitability. Under commercialisation, government maintains ownership of electric utilities but removes subsidies and preferential fiscal policies and requires full recovery of capital, operations, and maintenance costs. Corporatisation entails the formal and legal move from direct government control to a legal corporation with separate management. Eskom will be corporatised this year; with Transmission, Distribution and Generation each forming a separate corporate entity. Thereafter, Eskom will be liable for the payment of taxes and dividends. * Competition. While the “wires” portion of the electricity sector (transmission and distribution services) is still considered a natural monopoly, competition may be introduced into the system for selling power to the grid (wholesale competition) and providing electricity to end-use customers (retail competition). Wholesale competition may take the forms of independent power producers bidding for long term contracts with power purchases, or of the creation of spot or short-term markets for wholesale power. Retail competition can be introduced through different methods. In one, multiple power generators have direct access to the transmission and distribution networks allowing them to compete to supply final customers regardless of who owns the wires. In another, independent retail service providers (which do not own generation facilities) buy power from generators, contract for use of transmission and distribution facilities, and sell the power to final customers (Kozloff, 1998). * It seems likely that South Africa will adopt a multi-pronged approach towards introducing wholesale competition into the South African power sector. These 62 steps are illustrated in the section below. In summary these include: (i) commercialisation and corporatisation of Eskom; (ii) creation of independent competing Eskom Generation companies to promote internal competition as well as non discriminatory access to transmission and distribution networks; (iii) creation of a spot market and the introduction of private sector participation, either through a new IPP licence, strategic equity partners, an initial public offering, and/or a private equity offering. As noted in the White Paper, retail competition (aside from selected large industrial customers being allowed a choice of supplier) is not seen as an option for some time to come. * Privatisation. Privatisation transfers existing power sector assets to private ownership and allows private development of some, or all, new power sector infrastructure. Introducing greater private sector participation into the power sector can involve the privatisation of assets, or it can involve the emergence of private sector involvement in the development of new power sector infrastructure. It is argued that privatisation of Eskom without first creating a competitive market would be detrimental for end-use customers since it would likely mean a guaranteed private monopoly income for Eskom’s new (probably foreign) owners. It would be extremely difficult to force diversity at a later date in order to create competition (Eberhard 1999). The entrance of a foreign strategic equity partner for Eskom would also complicate moves to full competition at a later stage. Given this, it is likely that government will concentrate on moves towards introducing competition prior to any initiatives involving privatisation or greater public sector participation. In all likelihood, though, an IPP will be introduced prior to the establishment of a competitive wholesale market. This will be important in order to ensure adequate installed capacity. The new IPP would likely then sell power to Eskom under the conditions of a long-term power purchase agreement (See Figures I and II above). As noted above, it is government policy to introduce strategic equity partners into different non-regulated Eskom Enterprises business units. Private sector participation will be introduced specifically into the generation and transmission entities, either through strategic equity partners, through initial public offerings or private equity offerings, or as noted above, through granting a licence to an emerging independent power producer. Interestingly, the Minister of Minerals and Energy has expressed concern about privatising components of the power sector. She argues that important public benefits such as programmes promoting black economic empowerment, affirmative action, rural electrification etc. will be threatened, and that this would go against the thrust of national development objectives. 3.2.2. Possible impacts of EDI reform on bulk renewable energy generation Rationalisation of the Electricity Distribution Industry (EDI) will not in itself impact considerably on the fate of bulk renewable energy generation in South Africa. It has, however, been important to note this process primarily because ESI reform initiatives 63 assume a maximum number of financially viable REDs operating in a more competitive environment, and one in which there is ultimately more private sector participation. As will be shown in the section to follow and Chapter 9 on recommendations, REDs will naturally become the main clients of generators producing power from renewable energy sources. Indeed, without the undertaking of this rationalisation process, recommendations put forward in section 9.2.2 would likely be irrelevant. This is because the current financial (and human capacity) status of most distributors of power would not realistically be able to support the framework suggested. 3.2.3. Possible impacts of ESI reform on bulk renewable energy generation International experience indicates that as reform initiatives have been introduced into power sectors, bulk-generated renewable energy has declined (or has not grown in line with the expectations linked to expansion of clean energy generation). This is broadly because very few incentives have been available to independent power producers to undertake bulk renewable energy investments. As the South African power industry lies on the verge of significant reform (see above), it is important for decision-makers to understand what the possible effects power sector reform could have on investment in bulk renewable energy investments. This understanding would then contribute significantly to the learning how these investments could be sustained, and even developed in these new and future contexts. In this section, possible impacts of ESI reforms on the bulk generation of renewable energy are outlined. Impacts are discussed in terms of the categories of reform defined in the section above i.e. unbundling, commercialisation and corporatisation, competition and privatisation. In each section, general international trends are briefly outlined. Thereafter, possible implications for South Africa are identified. In Chapter 9, recommendations on how to ensure investment in bulk renewable energy generation are presented. Unbundling International experience indicates the conditions and tariffs which independent power producers can gain access to the transmission system and use to “wheel” power for sale directly to electricity users fundamentally affects the independent power producers’ choice of technologies in grid-connected applications. Transmission access (including fair cost structures enabling access) has the potential to stimulate development of new renewable power generation. Because renewable resources are location-specific, developers of renewable power generation depend on access to transmission lines to sell power to the grid. Moreover, transmission access gives renewable power producers the ability to sell power to locations where, and at times when, it is more highly valued than by the local utility (Kozloff 1998). Despite legal and physical access to transmission lines, renewable power producers may not have equal access to transmission capacity because of unfavourable terms of contract. Producers of intermittent generation may be charged more per kilowatt-hour to transmit power than their dispatchable competitors. Transmission access charges 64 may be based on a generators maximum rated capacity or what it actually generates during peak periods. Moreover, the site-specific nature of renewables may be a drawback under some transmission pricing schemes. Tariffs may be based on distance or contract paths regardless of actual transmission costs or the flow of electrons (Kozloff 1998). In South Africa, unbundling initiatives could have significant impact on bulk generation of renewable energy. Unbundling would be complete in the model characterised by Figure II presented above. According to the Generation Oligopoly model, Transmission is no longer controlled by Eskom (in other words, the monopoly status enjoyed by Eskom in transmission has been removed) to the extent that ‘fair’ access by independent power producers to the transmission network could now be assumed. This represents a significant step toward reducing the prevailing barriers inhibiting investment in bulk renewable energy generation. As indicated above, transmission access is a necessary but not a sufficient condition for uninhibited investment in bulk renewable energy generation. This is because the terms of contract and tariff structures are also key determinants of whether independent power producers will invest in this area. In Figure II’s Generation Oligopoly model (where as noted unbundling activities are complete), Eskom Holdings may still be able to exert undue market power through its subsidiaries and therefore manipulate tariff levels. If this turns out to be the case, it is unlikely that IPPs focusing on bulk renewable generation will be attracted to the market. Of course, the impact of unbundling on investment in bulk renewable energy generation will depend on the nature of the prevailing regulatory regime (see below. At present there are no regulations supporting investment in this area. As power sector reforms proceed, however, this may change. For example, regulatory interventions which allow for (and insist on) the granting of specialist Power Purchase Agreements, or requirements that the distribution industry distribute a specified percentage of power generated from renewable energy sources could significantly alter the prognosis for investment in this context. Commercialisation and corporatisation International experience indicates that commercialising public utilities has negligible effect on investment in renewables in bulk power markets. Still, the ability to adopt new technologies may be improved. Renewables may be considered more seriously to the extent that improved management, cost accounting, and cost recovery increase the utility’s interest in choosing the least-cost approach to expanding service on a lifecycle basis (Kozloff, 1998). Figure I illustrates the Purchasing Agency Model in which commercialisation and corporatisation initiatives have already been completed. Once fully commercialised and formally corporatised, Eskom Holdings will become increasingly cautious about what projects to invest in. Without appropriate regulatory frameworks in place, it is unlikely that Eskom would choose to invest in a bulk renewable energy generation plant. 65 As Eskom moves towards more cost-reflective tariffs, investment in bulk renewable energy generation is likely to become increasingly achievable by independent power producers. The prevailing regulatory regime would, however, be a key determinant of whether this investment actually occurs. As noted previously, without adequate regulation, it is unlikely that independent power producers would consider investment in new bulk renewable energy generation resource financially feasible. Certainly this would be the case within the context of the models denoted by Figure I and probably Figure II, the basis of which reflect commercialised and corporatised operating environments. Competition International experience indicates that wholesale competition is not likely to favour renewables in bulk power markets. Compared with long-term bilateral power purchase agreements, short-term or spot markets make it more difficult to finance and develop renewable generation options. For one thing, renewable projects bidding into spot markets are harder to finance than generation projects with low capital costs. Lenders are reluctant to provide debt capital for renewable energy merchant plant projects, especially in countries where spot markets have yet to establish a track record. Since lenders require that power projects demonstrate steady, predictable cash flows to meet debt service requirements over several years, the revenue risk created by unpredictable spot markets effectively precludes financing (Blair 1995, Kozloff 1998) Spot markets are particularly unfriendly to the development of “intermittent” renewable resources. Prices may be high for a limited number of hours in a year and not necessarily when these intermittent renewable resources are available. The inability to generate power on demand is a drawback in spot markets, which places a premium on generators that could assure power availability during peak periods. Because these resources cannot be dispatched on demand, the rules governing dispatch and payment in competitive wholesale markets are particularly important in determining their value. In contrast, developers of thermal plants could secure financing because they have greater control over when they sell to the spot market and because their lower debt load gives them less exposure to a prolonged drop in market prices (Kozloff 1998). Retail competition is also likely to affect the ability of renewables to compete in bulk power markets. The incentive to retain and attract customers that is created by retail competition makes electricity suppliers seek opportunities to minimise rates and to differentiate themselves from competitors. In the United States and parts of Europe, some retail suppliers are trying to differentiate themselves by marketing “green” (environmentally friendly) electricity generation. This market niche is smaller in developing countries because environmental consciousness is generally lower and electricity costs tend to look larger in the household or business budgets. In South Africa, meaningful competition is first introduced into the power sector in the Generation Oligopoly model illustrated by Figure II. This model involves the establishment of an independent power exchange with hopefully, independent, trading arrangements. In the Wholesale Competition Model (illustrated in Figure III), Eskom controls a minority share of generation assets, and the remainder rests under the 66 control of independent power producers, strategic equity partners, or shareholders of IPPs and/or private equity offerings. Assuming limited regulatory intervention, these competitive models are not likely to bode well for investments in bulk renewable energy generation. The primary reason for this is that independent power producers would likely be unable to meaningfully compete on the spot market with other generators of power. Independent power producers would not likely be costcompetitive for the reasons stated above (i.e. difficulties associated with raising debt capital and the unpredictability of returns). As will be discussed below, this poor prognosis assumes almost negligible regulatory intervention. Indeed, with a regulatory regime that is supportive of investment in bulk renewable energy generation, this need not be the case. For instance, by regulatory decree, bulk renewable energy generators need not compete on the spot market – these generators could be awarded preferential status, transacting directly with the REDs (see Chapter 9 on recommendations). When, and if retail competition is introduced into the power sector in South Africa, investment in bulk renewable energy generation is even less likely to be sustained. This would be primarily because generators and REDs will be increasingly conscious about retaining customers, and the primary determinant of this is likely to be related to the tariff level (and perhaps service) offered. In order to avoid competitive exposure, REDs would seek to minimise fixed costs, and avoid capital intensive investments. REDs, on the other hand, might choose to market green power as a way of differentiating their product, and in this way demand for bulk generated renewable energy could be sustained. It is unlikely, however, that this demand would be sufficient to justify the entrance of more than a few bulk renewable energy generators. Again, regulatory intervention would be necessary. Privatisation International experience indicates that privatisation initiatives are unlikely by themselves to increase the market share of bulk generated renewable energy generation. Technology preferences for investments in new generation result partly from differences in project financing available to public utilities, private utilities, and independent power developers. When new generation is privatised and unbundled, independent power producers must usually finance projects on the basis of the expected returns from the specific project and the need to recover investment over the loan repayment period. Independent power developers face a higher cost of capital and a shorter repayment period than the vertically integrated utilities. They must recover their investment over the period of their loan repayment. All things being equal, the cost of energy from a capital-intensive renewable project to either a private utility or an independent power producer is generally higher than to a public utility (Kozloff 1998). Because of these financial considerations, independent power producers prefer generation options that have relatively low capital costs per megawatt, a short construction time in order to yield revenue quickly, high efficiency, and the ability to be operated most of the time. Based on recent trends, independent power producers generally appear to favour natural gas generation due to its cost structure and short construction time. Generation options that are not favoured are coal, nuclear, hydro and renewables (Blair 1995, Kozloff 1998). 67 Power purchase agreements can also affect the financing for renewables, depending on the extent to which provisions in these agreements are geared to the characteristics of renewable generation options. Since most independent power projects have been thermal to date, the terms of standard power purchase agreements (PPAs) are often geared to such projects. Payment schedules and other terms in PPAs may create incentives for independent power producers to choose relatively low capital-cost-per megawatt generation technologies over options with comparable life-cycle costs but higher capital costs. PPAs often generate fixed price payments to developers over a limited period of time. Adequate payment schedules are particularly critical for capital-intensive power generation options, a characteristic of geothermal, wind, hydro, solar and thermal options. Independent power producers must attract private debt financing on the strength of the PPAs. They must often recover their capital investments over the fixed price contract period (generally less than the facility’s life span). This is harder to do for IPPs of capital-intensive generation options, putting them at a competitive-disadvantage relative to developers of fuel-cost-intensive options (Kozloff 1998). Renewables face other barriers in obtaining long-term power contracts. Transaction costs incurred to participate in the bidding process may favour certain technologies. Per megawatt, the costs of preparing a bid for a thermal project are less than for a renewable project. Thermal projects can be readily determined and are not particularly site-specific, allowing bids to be prepared more quickly and cheaply. Producers of power from renewable energy resources may find the transaction costs of negotiating PPAs prohibitive. Generation units are only likely to be privatised in South Africa once the structure of the industry has been transformed (i.e. only once competition in generation has be established). However, this does not necessarily mean that greater private sector participation will not occur prior to this. Indeed, it is possible (and likely) that in the next year, a license will be granted to an Independent Power Producer to build new (and needed) power sector infrastructure. Whether a bulk renewable energy producer will be able to meaningfully compete for this license will depend primarily on the prevailing regulatory regime, and cost of capital. As more competition is introduced into the wholesale market, the likelihood of this occurring is much reduced. This is particularly likely to be the case as the natural gas industry in southern Africa develops. Changing regulatory frameworks Power sector dynamics discussed so far include commercialisation and corporatisation initiatives, unbundling (or restructuring), introduction of competition and privatisation. As has been shown the prognosis for sustained investment in bulk renewable energy generation as these various power sector reform initiatives proceed is generally poor. It has been mentioned though that the impact of these initiatives does substantially depend on the nature of the prevailing regulatory regime during these various stages. If regulatory incentives are in place, there is no reason why the future for bulk generated renewable energy should be so bleak. The National Electricity Regulator has recently emerged from a ‘bumpy’ start. As plans for power sector reform take place, it is likely that the NER will become 68 increasingly capacitated to engage more with the power sector. Indeed, it is likely that the NER will play a more hands-on role in the regulation of the power sector in the future. Within this context, it seems fair to assume that the prevailing regulatory regime will evolve, and therefore that regulation in South Africa should also be regarded as a dynamic worth taking note of. 3.3. Stakeholders There is a wide range of stakeholders with interests in the South African energy sector. The stakeholders in the South African energy and power supply sectors can be broadly categorised into the following groups: Government (national, provincial, and local) State-owned companies and municipalities Commercial companies and industry associations Regulatory bodies and related organisations (CEF, NER, etc.) NGOs and research organisations (energy policy, social equality, and environment) Unions Consumers The Southern African Development Community (SADC) represents regional interests. Because of the envisaged regional integration and the trading of energy across borders (gas and electricity), SADC is expected to play an increasingly important role. In addition, a number of commercial consultants provide dedicated services in the area of energy and power supply. In addition, international management consulting companies have recently become increasingly involved in the South African energy sector. 3.3.1. Government Historically, government's interests in the energy sector was largely focused on autonomy and security of supply. Because of the resulting close alignment of interests between government and business during the Apartheid years, there was no clear separation between roles and responsibilities between government and energy supply industry. This was reinforced by the authoritarian regime that prevailed during the 70's and 80's. With the opening up of the country during the 90's, there has been a significant broadening of the interests and stakeholder representation that government facilitates. A range of national government departments exists that in one way or another are involved in the energy sector. These are: The Department of Minerals and Energy (DME) The Department of Public Enterprises The Department for Environmental Affairs and Tourism (DEAT) The Department of Finance 69 Department of Trade and Industry Department of Provincial and Local Government These government departments represent a number of interests including equal access to services by previously disadvantaged individuals and groups, environmental interests, and other issues as set out in the EWP. In addition, provincial and local governments have a stake in the energy supply sector mainly though the ownership of distribution networks and access to end-user markets. 3.3.2. State-owned and companies and municipalities South Africa has a vast heritage of state-owned companies that are in the process of being re-regulated and privatised. The energy supply industry is no exception. Stateowned companies in the energy supply sector include Eskom, SASOL, MOSSGAS, and a range of companies operating under the umbrella of the Central Energy Fund. ESKOM7 is the national electricity supplier of South Africa. Albeit not being a private company, the organisation was restructured in 1999 into a private, non-regulated part called Eskom Enterprises, and a regulated part. A number of municipalities exist that distribute electricity to end-users. Most of these municipalities buy electricity in bulk from ESKOM and take care of the distribution and billing while making a substantial profit by charging a mark-up on the electricity price. These municipalities are represented by the Amalgamated Municipal Electricity Undertakings (AMEU), as well as the South African Local Government Association (SALGA). 3.3.3. Commercial Companies Commercial companies can be broadly categorised into the large multi-national petroleum companies and an emerging new kind of energy service companies backed with international NGO support (for example RAPS). So far, legislation and the regulatory environment in South Africa have not been supportive to grid-connected energy service companies. Thus, this industry does not have any strong representation at any level. The South African Petroleum Industry Association (SAPIA) represents the interests of the South African Petroleum industry in South Africa. Multinational petroleum companies are increasingly becoming involved in the investment in non-petroleum energy services all over the world. The most progressive examples of such companies are Shell and Enron. While Shell's renewable energy strategy is to a large extent based on solar energy, biomass and forestry, Enron has committed itself to investments in the wind energy sector through the purchase of two of the biggest wind energy companies in the world. Coming from a traditional gas-supply background, Enron has become the leading global player in energy trading. Understandably, Enron has so far mainly focused on de-regulated countries and territories. At least partially for this 7 ESKOM was an acronym for Electricity Supply Commission. The acronym is today used as the company name itself. 70 reason Enron has not been very active in South Africa yet, apart from its regional involvement in oil and gas exploration. Shell has committed itself to major investments internationally in the area of renewable energy. In South Africa, the company is involved in a joint venture with ESKOM in the provision of Solar Home Systems. In addition, a new breed of smaller companies has also emerged that is active in the provision of energy services, grid as well as off-grid. Most of these companies focus on the production and of solar energy devices for household end use. Examples of such companies are RAPS and DARLIPP, with the fundamental difference between the two that DARLIPP concentrates on grid-connected wind energy and RAPS on decentralised, off-grid systems of various energy sources. 3.3.4. Regulatory bodies The NER is the regulatory authority over the electricity supply industry (ESI) in South Africa. It is a statutory body; established in terms of the Electricity Act, No. 41 of 1987, as amended by the Electricity Amendment Acts of 1994 and 1995. The NER is effectively only five years old. 3.3.5. NGOs and research organisations Presently a number of NGOs and research organisations represent a wide spectrum of interests ranging from advocating the needs and rights of the poor up to the advocacy of environmental issues. CSIR The former state-aligned research organisation, which underwent substantial restructuring and is now undertaking an effort to re-position itself to undertake research in a more liberalised marketplace. EDRC Based at the University of Cape Town, the Energy and Development Research Centre is the leading energy policy research organisation in southern Africa. ERI Based at UCT, and focuses on largely technical and forecasting/planning issues. IFR The Institute of Future Research is based at the University of Stellenbosch. MEPC Founded in 1994 with the main mission to fill the vacuum in policy development capacity. GEM Group for environmental monitoring, based in Johannesburg, primarily concerned with aligning labour and environmental interests, also involved in research Earthlife Africa Activist group based in Johannesburg EMG Environmental Monitoring Group, based in Cape Town EJNF The Environmental Justice Network Forum is a network of environmentally minded researchers and interested parties 71 SESSA SAWEA The Solar Energy Society of Southern Africa is a non-profit organisation dedicated to promoting and increasing the use of renewable energy. The South African Wind Energy Association is a non-profit organisation established to further the use of wind energy in South Africa. 3.3.6. Unions Historically, the relationship between the unions, companies and the state was heavily politicised. With the beginning of a new era in the 1990's, union leadership has increasingly been co-opted through the formation of bodies such as NEDLAC (National Economic Development and Labour Council). The latest union positions reveal that the struggle is now focusing more on wage issues and job creation than on political power. Nonetheless, the unions are still very critical and cautious towards liberalisation, privatisation, or re-regulation. The Labour Relations Act (LRA) gives workers the right to embark on protest action to promote and protect their social and economic interests, if they follow certain procedures. The largest unions are: COSATU FEDUSA NACTU Of these, the COSATU is the one most actively involved in the debates around restructuring of state-owned enterprises. COSATU has clearly expressed its opposition towards privatisation of state enterprises. COSATU holds the view that the state ownership of enterprises such as ESKOM is the most effective way to ensure service delivery to as many as possible people, thus providing an effective mechanism for cross-subsidisation. COSATU has indicated several times that it will take protest action against the privatisation of ESKOM and other enterprises owned by the state. 3.4. Present legal and regulatory deficits Since the industry is effectively operating with area monopolies, it is virtually impossible for new market entrants to gain access to a customer base, or even building one. This issue is partially addressed as a policy objective in the EWP: Government will encourage competition within energy markets (EWP page 12). However, the EWP neither gives any attention to the need for facilitating the development of markets nor any indication as to how to accomplish the goal of developing the markets. On page 62 the EWP states: "The entry of multiple players into the generation market will be encouraged. Initially this policy will be implemented by obliging the national transmission system to publish National Electricity Regulator approved tariffs for the purchase of co-generated and independently generated electricity on the basis of full avoided costs." At present, "avoided costs" effectively means fuel plus O&M costs, due to the substantial excess capacity. However, energy generation costs are predominately 72 made up of capital costs and only to a lesser extent of fuel costs. This is particularly so in coal-fired generation which make the bulk of South Africa's generating capacity, as well as in nuclear power plants. For this reason, many new market entrants (which are supposedly "encouraged") are effectively blocked from entering the market because they have to recover their investment costs as well as their operating costs. In other words, only a player who happens to already have written off the capital cost of a power plant can theoretically compete in this game. The location and scope of legal and regulatory deficits strongly depends on the route that the restructuring of the industry will take. There are two basic strategies for restructuring. First, a vertical disaggregation of the electric utility industry can take place, which essentially entails breaking up Eskom into separate companies responsible for the generation, transmission and distribution. The transmission network will take over the role of an independent power exchange, effectively facilitating an open market for electricity. The second option is allowing for open access to the existing grid infrastructure for all players, leaving the existing industry intact. It seems clear that while the first option for deregulation is a very ambitious goal in terms of the restructuring tasks, it is also a lesser problem as far as the regulation required is concerned. The second option requires more effective and complex regulation and also a much more stringent enforcement of this regulation in order to work. More specifically, there are five main areas of relevance that are not adequately addressed in the present legal and regulatory frameworks, with varying priorities, as indicated in Exhibit 4. Exhibit 4: Main regulatory areas of relevance to be addressed Vertical disaggregation Open access Regulation of access to electricity markets and customers Major Major Regulation of access to the existing grid infrastructure Minor Major Establishment of electricity wheeling rules and tariffs Minor Major Control of ownership issues by the competition board Major Minor Renewable energy power purchase agreements Major Major (Key: Major/Minor: This is a major/minor issue.) These five areas are briefly addressed in more detail in the sections below. 3.4.1. Regulation of access to electricity markets and customers Legislation needs to be developed that caters for the separation of the operation of the distribution network infrastructure and the provision of electricity service. No such legislation presently exists. In order to make the industry more competitive, at least bulk customers need to be able to decide from which electricity producer they like to 73 purchase their electricity. This can only be accomplished by separating the service of connection from the electricity provision. 3.4.2. Guidelines for access to grid The existing players in the field, i.e. Eskom and the larger municipalities, and to some extent also some large private producers and consumers of electricity, have directly negotiated contracts with each other regarding access to the grid and the purchase of power. Regulation needs to be developed that allows for all market entrants to connect to the electric grid, subject to technical connection criteria such as synchronisation, voltage/frequency regulation, and fluctuations. It should be emphasised that these technical requirements should be developed in a way that takes into account the nature of renewable energy power. 3.4.3. Establishment and enforcement of wheeling rules and tariffs This issue is of particular concern under the "open access" scenario because of the non-separation of ownership interests of established players. Even more important is that the development of electricity wheeling tariffs is the enforcement of such a framework. In case of the vertical disaggregation option, the issue of wheeling is of a lesser concern since it assumes that an independent body will operate the transmission infrastructure, facilitating a market place for electricity. At present, Eskom who owns and operates the transmission grid infrastructure has its own accounting system for electricity transport costing. Under the "open access scenario" this function needs to be taken out of Eskom and placed into a separate department at the NER. 3.4.4. Control of ownership issues by the competition board Under the "vertical disaggregation" scenario, the state competition board must proactively address and monitor the independence of the different players to ensure that all players can enjoy equal market conditions. 3.4.5. Renewable energy Power Purchase Agreements Since renewable energy is still somewhat less competitive in the absence of appropriate incentives, a market for renewable energy is difficult to establish. This can be done in several ways (cf. Chapter 7). One of the most important is to guarantee purchase agreements by all distributors of a limited amount of renewable energy power. 74 References 1. Blair, S 1995. The true cost of renewables. http://www.rapmaine.org.room.htm 2. Clark, A 1999. Demand-side management in restructured electricity industries: An international review. Research report. Energy and Development Research Centre, University of Cape Town. 3. Clark A & Mavhungu, J 2000. Promoting public benefit energy-efficiency investment in new power contexts in South Africa. Research report. Energy and Development Research Centre, University of Cape Town. 4. Ministry of Public Enterprises 2000. Accelerated agenda for the restructuring of state-owned enterprises. Government printers: Pretoria. 5. Department of Minerals and Energy 1998. White paper on energy policy for the Republic of South Africa. Government Printer: Pretoria. 6. Eberhard, A 1999. Competitive jolt good for customers. Business day. 11 November. 7. EU Commission n.d. Towards a single market for electricity from renewable energy sources. Working paper, extracts. http://www.windenergie.de/englisch/euc_w_paper.html 8. Hunt, S & Shuttleworth, G 1996. Competition and choice in electricity. New York: John Wiley and Sons. 9. Kozloff, K 1998. Electricity sector reform in developing countries: Implications for renewable energy. Washington D.C: Renewable Energy Power Project. 10. Miller, A & Serchuk, A n.d Renewable energy in competitive electricity markets. http://repp.org/articles/millser.htm 11. Ministry of Public Enterprises 2000. An accelerated agenda towards the restructuring of state owned enterprises. Government Printer: Pretoria. 12. PriceWaterhouseCoopers, 2000. Electricity distribution industry restructuring project: Working paper 7: Consolidated emerging views. http://www.dme.gov.za 13. Rader, N & Norgaard, B 1996. Efficiency and sustainability in restructured electricity markets: The renewables portfolio standard. The electricity journal. July. 14. Steyn, G 2000a. Draft policy and strategy on electricity supply industry reform for the Republic of South Africa. Draft document prepared for the Department of Minerals and Energy. 15. Steyn, G 2000b. A competitive electricity market for South Africa: The need for change and a strategy for restructuring South Africa’s electricity supply industry. Document prepared for the Department of Minerals and Energy. 16. Swanson, S 1997. The fate of renewables under utility restructuring in the United States. http://www.ttcorp/com/upvg/record/rc197fat.htm 17. World Bank 1999. Fuel for thought: An environmental strategy for the energy sector: Washington DC: World Bank. 75 4. RENEWABLE ENERGY RESOURCES 4.1. Renewable energy technologies suitable for independent power producers 4.1.1. Introduction This chapter provides a brief overview and comparison of renewable energy technologies and the suitability for use in grid connected power plants operated as independent power producers. The term IPP is generally used in referring to a nonutility owned producer of electrical energy who generates and sells its power in competition with other generators. The IPP concept has also associated with it the element of project finance in that the construction of the power plant is financed on a limited or non-recourse basis. The project is therefore financed based on the projected revenue stream of the plant and does not include recourse to other assets of the project’s sponsors (Terblance 2000). As a rough guideline, RET IPPs develop sufficient economy of scale with installed capacity of 8-10MW and up This scale of plant that is considered suitable for establishment of a grid connected IPP is dictated more by the project finance criteria than technology. Smaller size IPP are possible and viable if the project finance route is not required and alternative or recourse financing is provided. The renewable energy power generation technologies that are compared below are those that meet this criterion of scale. The RETs listed below are all mature technologies, which have been successfully and commercially implemented in South Africa or elsewhere. The RETs listed under future potential are technologies which are still under development, but which stand a good chance of being viable in South Africa as a mature technology. 4.1.2. Wind Wind energy is probably the widest spread and fastest growing sector of large-scale (MW range) grid connected renewable energy power plants. The technology is well established and mature. Europe and the USA have led the world in the development of grid connected wind farms. With the growing awareness of the global nature of the energy sector’s environmental impact, particularly on greenhouse gas emissions the developing world has increased its share of the global market. Numerous wind farms have been put up internationally, notably in India, North Africa and Island states in the Caribbean The technology is based on wind turbines varying in size from 0.5kW to 1.5MW+ per unit. These turbines are combined in wind farms with installed capacities ranging from 10 MW to 100 MW and beyond. In the past many wind farms were below 10 MW, but for the future, wind farms should preferably be above 5-10 MW. Due to the intermittent nature of the wind resource a wind farm typically operates on a capacity factor of around 20-30%. This means in practise that a nominal 100 MW wind farm is only producing 20-30 MW of power on an annual average basis. Experience in the countries that have operated wind farms over the last decade or so has shown that despite the intermittent nature of wind, the power production of a wind farm is fairly predictable in terms of the amount and time availability of the power produced. 76 Like most renewable energy resources wind power is very capital intensive with low running costs. The capital cost of installed wind power is in the order of US$1 million /MW and the cost of electricity produced is now approaching US$0.04/kWh and is expected to drop to US$0.03/kWh over the next 2-3 years. Limitations to uptake of wind are the low cost of grid electricity, the need to develop local manufacturing capacity to reduce capital costs, and the lack of Government support or incentives. 4.1.3. Biomass The main sources of biomass that are viable for large-scale power production in the South African context are bagasse from the sugar industry and wood wastes in the wood and paper industries. Both these industries require a significant amount of process heat as well as power for their operations. The availability of a fuel source in the from of process wastes have prompted the sugar, wood and paper industries to generate at least some of their energy needs on site. In general steam is generated for process heat and in some case direct motive power. The availability of high-pressure steam also makes possible the generation of electricity though steam turbines. The amount of electricity generated depends mostly on the pressure at which steam is produced. Higher pressure means more electricity. The use of combined cycle (heat and power) combustion technologies can enable generation efficiencies, which are, double that of conventional steam turbines. Biomass combustion technologies range in size. In the South African context power plants range in size from 5 to 50 MW. In the sugar industry it is common that sugar mills are also exporters of power. In Mauritius some 60% of the national electricity demand is bought from sugar mills during the harvesting season. This dramatically reduces the island’s dependence on imported fossil fuels. 4.1.4. Hydro Pumped storage This application of hydropower utilises low-cost electricity at of peak periods to pump water to a reservoir from which it is released during peak demand periods to generate peak power. The technology is used extensively in South Africa for peak lopping purposes. Eskom operates 1 400MW worth of pumped storage plants and a local Authority (Cape Town) owns and operates an 180MW plant. Although pumped storage plants utilises hydro turbines for power generation the pumping of water during off peak periods is done utilising power from the national generation pool, which is overwhelmingly coal based. In this sense pumped storage cannot be considered a renewable energy technology. Storage This is the most suitable type of hydro power plant for South African conditions. The use of storage capacity (a dam) helps ensure that the plant can run on a continuous 77 basis as water is stored during high flow periods and released during low flow periods to even flow and therefore power production. Due to the negative environmental and social impact of large dams due to the immersion of large tracts of land under storage dams and the displacement of people, hydropower plants are in some instances (e.g. by the European Union) only considered renewable at capacities up to 10-15MW. Capital costs are in the order of US$0.8 – 1million/MW. The cost of electricity produced is in the range of US$0.2/kWh although this can be further reduced to the long operational life (up to 30-40 years) of a small hydro plant Run of river In the light of the highly variable annual flow patterns of most South African rivers and the frequency of droughts, run of the river hydro systems are not likely to be developed in South Africa Suitability for Micro hydro production in South Africa Eskom conducted a study in 1998 to supply non-grid electricity from micro hydro facilities. The cost of this technology was also compared with the cost of grid supply via a Single Wire Earth Return (SWER) system. The cost obtained for the micro hydro option was based on an actual (run of river) site identified in the Eastern Cape, which has a potential capacity of 25kW at a 95% assurance level. The study concluded that, although there may be a number of suitable sites available in South Africa for micro hydro, it would only be economically viable when the demand area is located further than 26km from the existing distribution network. For shorter distances, the SWER line option would be more economical. This study further concluded that the remaining areas beyond the 26km distance are either not technically feasible to sustain a micro hydro scheme or lack the demand. 4.1.5. Solar The dominant solar technologies internationally are photovoltaic systems (PV) and solar water heaters. For purposes of large-scale grid connected power however, solar thermal electric technologies are more suitable. PV is a very well established technology and is increasingly used in grid-connected applications, but at present the technology is not suitable for IPP type applications. Solar thermal electric systems offer considerable potential for large-scale (10MW+) electricity generation. A number of different technologies for solar thermal power generation have been developed. The basis for electricity generation is that of focussing or concentrating solar radiation to achieve high temperatures to drive steam or external combustion cycle generator. Most of the technologies are still immature and require further development to achieve commercialisation. Solar thermal electric plant are either coupled in a hybrid configuration with a fuel such as natural gas or used in combination with advanced energy storage technologies such as molten salts to provide 24-hour production capacity. The main conversion systems are: Parabolic trough Central receiver Dish-Stirling systems 78 Capital costs are in the order of US$1.4million/MW for the current range of parabolic through systems being piloted internationally. 4.2. Comparison of renewable energy technologies for suitability as IPPs The table below lists and compares the available RETs for suitability as grid connected power plants. Coal is included for comparative purposes. Table 1 Comparison of power plant types Type Physical characteristics Coal Flexible with good frequency response Economic characteristics (all descriptions are relative) Medium capital costs, medium to high running costs Hydro (pumped storage) Hydro (+storage) Hydro (run of river) Wind Extremely flexible High capital costs, high marginal costs Flexible High capital costs, low running costs High capital costs, low running costs High capital costs, low running costs Energy crops and biomass residues Flexible High capital costs, low running costs Municipal waste Flexible High capital costs, low running costs. Running regime dictated by need to deal with waste stream Landfill gas Limited flexibility Inflexible intermittent Inflexible intermittent Solar thermal Flexible intermittent dependent on back up fuel or storage High capital costs, medium running costs 79 Typical running regime or role within system “Capacity following” and frequency response provision. Capacity factors from 20-70% Can easily be higher; it is more the demand side than the generation units that determines the total generation Rapid response (in either direction) and peak lopping Base load and capacity following Base load intermittent generator Base load intermittent generator. Capacity factors 25-40% Base load steady output. Capacity factor around 80% (not for bagasse, usually no more than 5 months per year) Base load steady output Capacity factor around 80% Base load. Capacity factor 90% Base load intermittent Based on Hartnell, 2000, p62. From a comparison of the characteristics of the various RETs the following technologies are identified as viable for potential IPPs in the South African context in the period under consideration. Wind Biomass including bagasse, wood and pulp. Hydro Technologies, which could be viable in the longer term, include: Solar thermal Landfill gas Municipal waste incineration 4.3. Renewable energy resource assessment 4.3.1. Background The mere availability of a resource does not mean that that resource can readily be used as a fuel for a commercially operated electricity generator. To utilise the resource several factors need to be considered: the conversion system, quality of the fuel, conversion cost, transport cost as well as the size and location of the demand (CSIR 1999). This section will provide an overview of the renewable energy resources of South Africa, but will focus on those identified in the section above as viable in the short and medium term. A number of resource assessments have been completed for the various renewable energy resources. Notable has been the South African Solar Radiation Handbook, the Wind Atlas of South Africa, and a PhD thesis entitled ’Towards a Renewable Energy Strategy for South Africa’ (G Stassen). Furthermore, the South African Renewable Energy Resource Database that is currently under development by the CSIR, Eskom and the Department of Minerals and Energy. The latter report contains assessments for solar, hydro and biomass resources and is in the process of completing the wind energy resource assessment. The database was developed using a GIS based methodology which enable more sophisticated assessments that with the previous reports. The CSIR report (1999) is based on the analysis of a comprehensive data set, which covers the whole of South Africa. The figure provided below shows the average and total amounts. National level data is useful in identifying potential resource types and localised densities or areas of highest probability. To move from such broad resources assessments to the identification of potential large-scale electricity generation requires a lot more detailed and localised analysis. The CSIR database can be accessed for such focussed and detailed analysis of specific areas. 80 4.3.2. Wind Estimates of wind power potential for South Africa were done by Diab (1995: 3-9) who generally concluded that: Wind power potential is generally good along the entire coast with localised areas, such as the coastal promontories, where potential is very good, i.e., mean annual speeds are above 6 m/s and power exceeds 200 W/m2; Moderate wind power potential areas include the Eastern Highveld Plateau, Bushmanland, the Drakensberg foothills in the Eastern Cape and KwaZuluNatal; and Areas with low wind power potential include the folded mountain belt (vast region of very complex and diverse terrain), the Western and Southern Highveld Plateau, the Bushveld basin, the Lowveld, the Northern Plateau, the Limpopo basin, Kalahari basin, the Cape Middleveld and the KwaZulu-Natal interior. (Stassen, 1996) Figure 1 depicts those locations throughout South Africa experiencing mean annual wind speeds in excess of 4 m/s. A new GIS wind map will soon be available from Department of Mines and Energy. Figure 1: Generalised map of wind power potential in South Africa (Diab, 1995:36) 81 Historically wind energy has had few applications in South Africa, and the country only has a total installed capacity of about 200 kW of wind power made up from small (<5kW) units. Stassen (1996) estimates the potential contribution of wind energy as about 1 717 GWh/annum, or some 1.1% of annual South African energy consumption. This estimation was based on the conversion of the total potential wind resource at a 10% conversion factor. 4.3.3. Biomass Background The use of biomass as a fuel source for sustainable energy systems is growing internationally. Biomass resources are extensively used for energy production in countries such as Mauritius, which are dependent on imported fuels for power production. Electricity generated from bagasse contributes some 60% of Mauritius’ electricity needs during the 9-month harvesting season. Fuel wood is the primary energy source of some 12 million people in both rural and urban areas of South Africa, and some 8 million tonnes of fuel wood are consumed annually. This use of biomass although significant in terms of overall energy balance and rural energy use is not relevant to IPP applications. One of the most important criteria that determine the suitability of a biomass resource for energy generation is transport. If the raw material has to be transported far to bring sufficiently large amounts to a single point for processing, the costs involved may render a project unviable. This is often the case for non-cultivated biomass, which is distributed over a large geographical area or for certain agricultural residues, which is normally available and processed in too small an amount to justify commercial power generation. In the case of sugar mills or wood and paper processing plants, the processing point is situated very close or within the plantation and the amount of biomass residues from processing on site or ‘inside the fence’ is sufficient for powering sizeable power plants. The assessments below will focus therefore on these resources, which are suitable for power production within the present context of processing. The resource availability of other sources of biomass is mentioned more briefly. Stassen (1996) provides a very comprehensive overview of a wide range of biomass resources in South Africa. The data below is mostly drawn from the 1999 CSIR report. In Figure 2 below the total potential biomass energy in South Africa is represented as modelled by the CSIR. The national representation is of little value when considering potential electricity grantors as it includes biomass resources such as grass. It is relevant to note the high energy densities found around the sugar, wood and pulp mills as indicated in the insert. It is at these mills where the potential lies for IPPs. 82 Figure 2: Total biomass energy potential for South Africa (CSIR 1999) Bagasse Bagasse is the residue that remains after sugar cane has been processed in mills for sugar production. The principal sugar cane growing areas are the KwaZulu-Natal coastlands and the Mpumalanga lowveld. In 1998 there were 400 000 ha under cane with an average yield of 52.5 tons/ha. Therefore some 21 million tons of sugar cane was delivered to the various sugar mills, which produced some 7 million tons of bagasse with a net calorific value of 6.8 GJ/ton and a total energy of 47,6 million GJ (Wienesse 1999). With the sugar mills currently generating significant amount of power for own use and even limited export, bagasse offers some of the best potential for IPP in South Africa using renewable or non-renewable resources. Wienese (1999) estimates that the current production of energy of some 30kWh/ton can be increased by up to 120kWh/ton using conventional steam plants running at higher pressures. Using integrated combined cycle combustion technologies the yield per ton bagasse can be increased up to 200kWh/ton. Without further expansion in production but through increased efficiency and new technologies the potential of this resource can be increased from the current 210 GWh to 1 400GWh. 83 Apart from power generation the bagasse is also sold for use in other products. By increasing the efficiency of power production it would not be necessary to use more bagasse that is presently available for power generation if excess bagasse can be sold profitably over the fence. Wood The CSIR (1999) identified the following wood biomass resources: Commercial plantations Indigenous woodlands Alien vegetation Deciduous tree off cuts from pruning of fruit trees Sawmills (primary processing) mostly woodchips, sawdust and bark Pulp mills: boiler ash, sludge, sawdust and black liquor The viability of wood as an energy source suitable for electricity generation lies within the wood, pulp and paper industries. In these industries there is already some heat and power generation taking place and there is potential for upgrading and expansion. The sector consists of two main components: the production of timber and the production of wood pulp for paper and board manufacturing. A GIS-based map showing the availability of wood and pulp resources in South Africa will soon be available from Eskom TSI (Dr L. van Heerden, tel 11-6295526) or from CSIR (Mr J. Muller, tel 12-8413992). Table 2 below give the result of the CSIRs modelling of the wood and pulp industries energy potential based on availability and energy content of fuels. Table 2: Annual Wood and Pulp Energy Potential (CSIR 1999) Type Tonnage (T/Year) Sawmills Pulp mills 1.57 million 1 million Energy potential (GJ/year) 27.5 million 16.3 million Agricultural residues Agricultural residues from the major annual and biennial crops are: Maize husks, stalks and leaves Wheat Sunflowers heads, stalks and leaves Sugarcane leaves and topping (excluding bagasse) Sorgum heads, stalks and leaves These crops constitute more than 98% of annual production in SA (CSIR 1999). The CSIR’s modelling of the energy potential of these crops was based on expected yield per area cultivated and the energy range of the crop residues. The residue amounts per area vary between 0.2 –10 ton/hectare/year with an annual total of 24.4 million tonnes/year. Energy values varied between 2 – 140 GJ/ha/year with sugarcane recording the highest values. Total annual energy production is estimated at 341GJ/year. 84 A GIS-based map showing the magnitude and distribution of the energy potential from agricultural residues in South Africa will soon be available from Eskom TSI (Dr L. van Heerden, tel 11-6295526) or from CSIR (Mr J. Muller, tel 12-8413992). Grass The potential energy from grass reached 84 GJ/ha/year in the most favourable areas along the low-lying areas of KwaZulu Natal, Mpumalanga and the Eastern Cape (CSIR 1999). By comparison in the savannah regions the yield was as low as 0 GJ/ha/year. Manure and Litter The potential exists to utilise the manure and litter from livestock to generate methane gas through anaerobic fermentation in biogas plants. Stassen (1996) estimated the potential energy production from the mayor livestock. Most Cattle farms in South Africa are free range. The poultry and pig farms do have large amounts of manure available on site. It needs to be assessed if the litter and manure from these farms can be used in biogas generators or burned in incinerators on a scale that would warrant classification as an IPP. It is unlikely that sufficient amount of manure would be available at a single point to warrant commercial electricity production. In Table 3 below only the manure and litter available at a single point such as for feedlot cattle of chicken broilers were included Table 3: Potential energy from livestock manure and litter (Stassen 1996) Type Cattle Pigs Poultry Energy Production 14 PJ/annum 1.1PJ/annum 5.1PJ/annum 4.3.4. Hydro South Africa has an average rainfall of 500mm, which is low by world standards. This combined with the seasonal flow of the country’s rivers and frequent droughts or floods limit opportunities for hydropower. The country’s potential for hydropower is concentrated in a few areas along the eastern escarpment where there are 6000 to 8000 potential sites. Stasen (1996) estimates the hydro potential of South Africa as follows: ‘The average annual rainfall of South Africa as a whole is 500mm, compared to a world average of 860mm. The humid subtropical conditions in the east and the dry desert conditions in the west result in an uneven distribution of rain across the country. Surface run-off is the main water source in the country, notwithstanding the fact that on average only about 9% of the total rainfall reaches the rivers. The average annual run-off of South Africa’s rivers is estimated at 53 500 million m3. Because of the variability and evaporation losses, only abut 62% or 33 000 million m3 of the mean annual run-off can be exploited economically with present methods. Only one quarter of South Africa has perennial rivers. These are mainly in the Southern and South Western Cape and on the Eastern escarpment slopes. 85 The estimated maximum theoretical hydro potential of South Africa is about 8 360 MW or 73 230 GWh (300 PJ) per annum. It has been estimated that the maximum theoretical potential for the Eastern Cape alone is some 14 000 GWh per annum. Owing to the high run-off variability from year to year, limited reservoir storage sites, losses by spillage during floods, the uneconomical scale of some sites, etc., a more conservative estimate of the realisable hydro potential would be nearer to 15% of the maximum theoretical potential; that is approximately 11 000 GWh or 40 PJ per annum (Stasen 1996). The figures below provide a graphical representation of the areas with macro and micro hydro potential in South Africa. Figure 3: Suitability macro hydro power in South Africa (CSIR 1999) 86 Figure 4: Suitability for Micro hydro production in South Africa (CSIR 1999) 4.3.5. Summary of resource assessment Table 4: Summary of renewable energy resource potential Resource Wind 1 Bagasse 2 Wood 1 Hydro 3 4 5 6 Total theoretical energy contribution/annum (PJ/year) 6.2 47 44 40 Based on total theoretical potential of total resource Based on total energy value of current harvest Harvestable potential Table 4 provides a summary of renewable energy resource availability. It is evident that South Africa is endowed with abundance in renewable energy resources most notably solar, biomass and wind. Exploitation of these resources for energy generation purposes has the potential to contribute up to 20% of national electricity production by 2020 (SESSA 2000). 87 4.4. Resources with potential for the future 4.4.1. Solar The average daily solar radiation in South Africa varies between 4,5 and 6,5 kWh/m2 (16 and 23 MJ/m2) (Stassen 1996). Figure 5 below (CSIR 1999) provide a graphic representation of the solar radiation as well as cloud cover for the best and worst months of the year. Cloud cover is important for estimating the potential for solar thermal electric power plants, which relies on direct and diffuse radiation for power production. From the figures it is clear that there considerable resource potential both in terms of radiation and unclouded weather in the North West and Northern Cape provinces. Such a resource is well suitable for solar thermal power generation. Figure 5: Annual direct and diffuse solar radiation More detailed maps on solar radiation, cloud cover etc. will soon be available from Eskom TSI (Dr L. van Heerden, tel 11-6295526) or from CSIR (Mr J. Muller, tel 128413992). 88 4.4.2. Wave Energy Wave potential along the Cape coastline is estimated as significant, but no exploitation is taking place to date. A mean annual power level of about 40 kW/m wave crest is typical offshore at the Cape Peninsula. An estimated total average power of 56,800 MW is available along the entire coast however it is doubtful whether any of this potential energy could be realised on a large scale. 4.4.3. Energy from Waste South Africa disposes of almost all of its refuse to landfill sites. The energy content of the total domestic and industrial refuse disposed of in 1990 amounted to 40,5 PJ per annum. The most feasible area for incineration of refuse from large municipalities would be the Reef area of Gauteng where it is calculated that approximately 17 PJ could be produced annually. The net realisable energy available from sewage-derived methane in South Africa would be in the order of 36 MWh (1,13 PJ) per annum for electricity generation and 96 MWh (3,0 PJ) for heating purposes. Options for energy production from municipal waste are in the process of being examined including biogas projects as well as methane gas from landfills. References 1. Hartnell, G 2000 ‘Wind on the system. Grid integration of wind power’ Renewable Energy World, March April 2000. James & James. London 2. Stassen G (1996): Towards a renewable energy strategy for South Africa. PhD thesis. University of Pretoria 3. Diab R (1995): Wind Atlas of South Africa. Department of Minerals and Energy. Pretoria, South Africa 4. CSIR (1999): South African Renewable Energy Resource Database. Council for Scientific and Industrial Research. Pretoria, South Africa 5. Wienesse A. (1999): Co-generation in the South African Sugar Industry. Sugar milling Research Institute, University of Natal, Durban. Durban, South Africa. 6. Terblanche V (2000): Common themes in independent power projects in Southern Africa. Traders, Issue 3 July October 2000. Traders Publications, Johannesburg, South Africa. 89 5. NON UTILITY EXPERIENCES IN SOUTH AFRICA 5.1. Background In the context of this project the term ‘non-utility generation’ refers to non-Eskom electricity generation. Within the South African context electricity generation policy is in the process of being liberalised. Independent Power Producers (IPPs) will have an improved position relative to the national electricity generation giant ESKOM. The implementation of the proposals as set out by the National Energy Regulator (NER) underline this fact making development of IPP projects, and specifically sustainable energy projects, an attractive proposition for new energy players. The proposed restructuring of the Electrical Distribution Industry in South Africa is a direct result of this new policy. The present national Energy Policy of the Department of Minerals and Energy (DME) strongly supports the implementation of sustainable energy projects especially if these are to the benefit of the underprivileged rural population. In this regard too, the constitution of South Africa obligates the Local Authorities to provide electricity services to their (rural) electorate and to do this as cost effectively as possible. It is within the scope of the Local Authorities to look at alternative means of securing its power resources and to pass on any economic benefits to its electorate. Any local power generation possibilities, which are cheaper than conventional methods and are renewable, is an ideal means for the Local Authorities to meet it’s constitutional obligation, pass on economic benefits to it’s electorate and to play a role in improving the local environment. There exists in South Africa a number of electricity generators apart from Eskom which may potentially be structured as IPPs. These generators can be divided into three groups: Existing and licensed generators, Existing but unlicensed generators and Potential generators. The National Electricity Regulator (NER) has licensed most existing generating plants as electricity generators according to the Electricity Act of 1987. The Act specifies that plants that generate more than 5 GWh/annum for resale as well as all municipal generators require a NER license. In 1995 the NER approached all the known cogenerators of electricity and the self-generating municipalities as well as Eskom as part of the licensing process. Private generating capacity was also identified in the process. A license is provided for a generating plant and not for an operator. Eskom therefore has been licensed for each of its power stations. The breakdown of the 50 currently licensed power stations is Eskom 24 plants Municipal 18 plants Private 8 plants Non-utility generation contributes 4.9% (2 114 MW) of South African electricity generation capacity. Eskom provides the remainder (41 027MW). Of interest to this 90 study are the 26 non-Eskom operated licensed plants, other existing plants which have the potential to be developed as IPPs (so called brownfield projects) as well as a number of new or ‘greenfield’ projects. 5.2. Existing non-utility generators There is no formal distinction made in South Africa between renewable and nonrenewable energy powered electricity generators in terms of generation licensing. Generators are listed and grouped according to fuel use such as coal, hydro or gas and utility or non-utility. It is however possible to separate out those generators that use a renewable energy fuel source such as biomass or small-scale hydropower. The NER has licensed 8 renewable energy based non-Eskom operated power plants. Of these, 4 are bagasse burning sugar mills, 3 are municipal owned hydro power plants and one is a privately owned small hydro power station. 5.2.1. Small hydropower Friedenheim hydro Friedenheim hydro can be viewed as the only existing IPP in South Africa. It is privately owned, sells the bulk of the generated electricity through a Power Purchase Agreement (PPA) and is a profitable operation. The plant is operated as a commercially profitable and sustainable business venture. It was financed through equity provided by investors (Friedenheim Irrigation Board - FIB). The project was developed by a consulting engineering firm (MBB), which also has a maintenance and operation contract with the plant owners. The small hydro power plant is situated next to the town of Nelspruit in the Mpumalanga province. It is owned by the members of Friedenheim Irrigation Board and operated by MBB an engineering firm. The plant provides power for water pumping to FIB, but 93% of the power generated is sold to the Nelspruit local authority through a PPA that sets the tariff at 12% below the price at which Nelspruit buys power from Eskom (its bulk electricity provider). The water supply to the turbines is by means of two penstocks feeding from an irrigation channel. The outlet of the turbines is into the Crocodile River. This set-up is suitable for constant and base load power supply, as there is no capacity to store water for peak power generation. After some initial difficulties with the water inlet system and the dedicated power line connecting the plant to the Nelspruit distribution system the plant has proved to require very low levels of maintenance. Maintenance and operation costs are in the order of R 200 000/annum, which is mainly routine maintenance and labour. 91 Overview Name Licensed Capacity Maximu m power produced Net Private energy consumption sent out Load factor MW 3 MW 2 MWh 14 434 % 73.7 Friedenhei m * Used for water pumping by FIB MWh 1 041* The Friedenheim Hydro scheme has proved a profitable and viable investment. Its successful track record has gone along way towards dispelling the myths common in the electricity supply industry that it is not possible to compete with Eskom, especially not with small and renewable energy producers selling energy wholesale. The motivation for the PPA with the Neslpruit Local Authority was based on the cost savings involved in buying electricity at a rate below that of Eskom and to a lesser extent the increased security of supply offered through this diversification in suppliers. 92 Summary - Friedenheim Hydro Friedenheim hydro can be viewed as the only existing IPP in South Africa. It is privately owned, sells the bulk of the generated electricity through a Power Purchase Agreement (PPA) and is a profitable operation. The plant is operated as a commercially profitable and sustainable business venture. It was financed through equity provided by investors (FIB). The project was developed by a consulting engineering firm (MBB), which also has a maintenance and operation contract with the plants owners. The Friendeheim Hydro scheme has proved a profitable and viable investment. Its successful track record has gone along way towards dispelling the myths common in the electricity supply industry that it is not possible to compete with Eskom, especially not with small and renewable energy producers selling energy wholesale. The small hydro power plant is situated next to the town of Nelspruit in the Mpumalanga province. It is owned by the members of Friedenheim Irrigation Board and operated by MBB an engineering firm. The plant provides power for water pumping to the Friedenheim Irrigation Board (FIB), but 93% of the power generated is sold to the Nelspruit local authority through a PPA that sets the tariff at 12% below the price at which Nelspruit buys power from Eskom (its bulk electricity provider). The water supply to the turbines is by means of two penstocks feeding from an irrigation channel. The outlet of the turbines is into the Crocodile river. This set-up is suitable fro constant and base load power supply as there is no capacity to store water for peak power generation. After some initial difficulties with the water inlet system and the dedicated power line connecting the plant to the Nelspruit distribution system the plant has proved to require very low levels of maintenance. Maintenance and operation costs are in the order of R 200 000/annum, which is mainly routine maintenance and labour. Maximum power produced MW 2.4 Nett energy sent out MWh Private consumptio n MWh 1 041* 14 434 Load factor % 73.7 The motivation for the PPA with the Neslpruit Local Authority was based on the cost savings involved in buying electricity at a rate below that of Eskom and to a lesser extent the increased security of supply offered through this diversification in suppliers. 93 Municipal owned hydro power stations Three small municipalities are currently licensed to operate small hydro power stations. These stations date from the 1930’s, and although these plants can be expected to operate for many more years operating efficiencies are decreasing. This is evident from the low load factors, which are at best half that experienced at the more modern Friedenheim plant. This implies that the plants were in full-scale operation for only some 50% of the year. A 1998 overview of the plants is provided in Table 1. Table 1: Municipal small hydro power plants Name Lydenburg Ceres Piet Retief Licensed Capacity Maximu m power produced MW MW 2 1 1 2 1 1 Net energy sent out MWh 6 000 413 2 900 Private consumption Load factor MWh % 0 0 0 34.2 8.6 33.1 Lydenburg The hydro station in Lydenburg, which dates from the 1930’s, has been out of operation since 1998. This was due to the need to repair components of the power plants as well as the connector to the town’s distribution system. The Town council therefore decided to subcontract the operation and maintenance of the plant to the private sector. The intention is that the plant would be leased to a private operator who would do the necessary rehabilitation and sell the electricity to the town. This would in effect make Lydenburg Hydro an IPP. Some five companies responded to the invitation to tender. At the time of writing the result of the tender has not yet been announced. Ceres The Ceres hydro station has a nominal capacity of 1MW. The maximum demand from Ceres varies between a minimum of 6000kVA and 14000kVA. Electricity is generated between a minimum of 50kVA and 900kVA or between 0.35% and 15% of the total usage by Ceres. The amount of electricity generated is determined by the amount of water available in the dam. The generation of the power from the station represents an annual saving of 2.5% on the electricity account at current Eskom tariffs. Piet Retief The Bakenkop hydro power plant was commissioned in 1950 to supply the town of Piet Retief with electricity before it was connected to the national transmission system. After 50 years it is still providing power to the town. The installed capacity is 0.8 MW. The system operates intermittently depending on the availability of water. The annual operational cost is R 290 760. There is no foreseen upgrading or decommissioning of the plant. At present it provides electricity at an average cost of R 0.09/kWh which is about half the rate the town pays to Eskom for its power. The 1998 load factor of 33% will result in revenues of R 210 000, which are some R 90 94 000 less than the operational costs, and the plant is therefore running at a loss. The power station is clearly very maintenance intense. Cape Town Pumped Storage The City of Cape Town owns and operates the 180 MW Steenbras pumped storage power station for peak power production. This is however not a renewable energy generator as the plant uses electricity purchased from the national transmission system (i.e. coal based electricity) to pump the water during off peak times. Other small hydro Eskom inherited four small hydro power plants in the present Eastern Cape Province from the Trankei government when the homeland governments were dissolved and integrated into the South African government in 1994. These hydro power plants, described below in Table 2 are connected to the national transmission network and are providing base load to the Eskom system. A request was submitted to Eskom Generation for information on these plants on 21 July 2000 and a formal reply from Eskom to the project co-ordinator at the DME was sent on 25 August 2000. Table 2: Eskom small hydro plants Name Collywobbles First Falls Second Falls Ncora Gariep Vanderkloff Licensed Capacity Maximu m power produced MW MW 42 6 11 2 42 6 11 2 Net energy sent out MWh 257 544 36 792 67 452 12 264 Private consumption Load factor MWh % 0 0 0 0 70 70 70 70 5.2.2. The sugar industry The sugar industry is the biggest and best-established example of renewable energy fuelled non-utility generators in South Africa. There are 15 sugar mills in South Africa of which five has been licensed as electricity generators by the NER. All the plants however generate steam and power from bagasse. The licensed plants are those who are in a position to export power as listed below in Table 3. The unlicensed plants are therefore not exporting any power. 95 Table 3: Sugar mills licensed by the NER Name TH Amatikulu TH Darnall TH Felixton TH Maidstone* Transvaal Suiker** Licensed Capacity Maximum power produced MW MW Net energy sent out 12 13 32 29 10 7 22 20 MWh 43 775 27 388 79 935 79 582 20 - - Private consumption Load factor MWh % 43 775 27 388 79 935 44 917 51 44.7 41.5 45.4 - - * The Tongaat Hulett Maidstone is a combined bagasse/coal plant **Transvaal Suiker was awarded a generation license in June 1998 and no data is available at present From total bagasse available some 5,5 million GJ of electrical energy can be generated in a typical conventional boiler and turbine alternator configuration as used in the South African sugar industry. This equates to 262 MJ/tc or 73 kWh/tc. Typically this means a boiler operating at 75% efficiency to produce steam at a pressure of 3000 kPa(abs) and a temperature of 400°C which is exhausted in steam turbines at 70% efficiency to a back pressure of 200 kPa(abs) (Winesse 1999). The power generation potential for the sugar industry through improved combustion technologies is listed in Table 4. It is possible to increase electricity production from the present 30kWh/ton to 120kWh using the present steam based technology and to reach up to 460kWh/ton through advanced combined cycle gasification processes. Table 4: Electricity Generation Potential (Wienese 1999) Cycle Technology Electricity generating fuel kWh/ton Steam Steam Steam Combined Combined old old new new new part bagasse (present) total bagasse total bagasse total bagasse total bagasse, tops and trash 30 73 120 200 460 5.2.3. The wood and pulp industries The industry consists of two sectors, the production of timber and the production of wood pulp for paper and board manufacture. A large proportion of the output of softwood mills in South Africa is in the form of kiln-dried timber resulting in a great demand for thermal energy. Almost all of these mills use their wood wastes as boiler fuel for steam generation while some also practice cogeneration (Stassen 1996). Most of the wood mills only utilise the steam generated and still buy their electricity needs from the local distributor usually Eskom. Cochane(1998) report only three of the South African mills generating their own electricity. 96 A reason, why only steam is produced and not power as well, is that kiln heating steam is required round the clock but electricity is only required for the 1012hours/day of the sawmills’ operation. For the sawmills to generate power it must be possible to sell this surplus power when the mill is not operating. According the a recent study (Cochrane 1998) the electricity generation potential through cogeneration technology is about two to three times the mill’s own demand. Steam is produced in the sawmills by the combustion of the wood wastes that result from the timber production process. Saw mill waste makes up about 34% of the tree as harvested (Cochrane 1998). In all three cases, where South African saw mills are producing electricity, the electricity is generated though the use of steam condensing turbines. These turbines were invariably purchased second hand from small municipal power stations. Cochrane (1998) reports that the saw milling industry is well aware of the potential for co-generation power production. This potential is not realised due to the competitive tariffs offered by Eskom and the high cost of installing new power generation equipment. The pulp and paper mills generate some power for their internal needs. This is mostly due to the high need for reliability in electricity supply during production. A dip in power supply can have serious effects on production (Anderson 1994). Power is derived from burning waste wood bark in combination with coal and the distillate from wood chips (black liquor). The energy recovery from black liquor and bark is typically a third of that which is found in similar plants in Scandinavia. There is only one recorded case of a South African mill burning bark for power generation. There is therefore potential for upgrading of these plants to provide more heat and power. The availability of the resource cannot be seen as the constraint rather the financial viability of converting the plants into power exporters and selling electricity into the available market. Table 5 below lists the wood and paper mills in South Africa that process wood for paper production. There are a number of other mills in South Africa that produce paper but these do not process wood as pulp source and therefore doe not have power generating capacity. Table 5: Pulp and paper mills in South Africa Name Mondi Group Sappi Group Number of mills 6 7 A 1994 study (Anderson) found that the generation of power in the paper and pulp industries combined was some 279 MW, while total system demand was some 590MW. The shortfall of 335MW was purchased from Eskom. In only one instance did a mill produce excess power that could be exported. The fact that none of the wood or paper mills are licensed by the NER is an indication that no power is currently exported from these mills compared to the licensed bagasse plants. The mills are opting to buy power from Eskom and to utilise their own generation capacity for increased security of supply is an indication of the perception within the industry 97 of the economic value of own power production. At present bulk electricity prices the mills do not see themselves competing with Eskom. The mills will have to more than double their energy production in order to meet own demand and have power available for export. 5.2.4. Non-renewable generators The NER has currently licensed 17 non-Eskom and non-renewable energy based power generators. Of these 11 are municipal owned coal fired power stations, 5 are municipal owned gas turbines used for peaking power and 2 are private (SASOL) owned coal fired power stations. Table 6 lists and describes all licensed municipal power generators. Of these power stations two (Pretoria West and Kelvin) have applied to the NER to be refurbished as IPPs. The involvement of the Johannesburg and Pretoria Local Authorities with their significant political clout will carry a lot of weight at petitioning government for IPPs to be approved. These initiatives may prise open the door for other IPPs to follow and benefit from. Table 6: Municipal owned power stations Name Licensed Capacity Maximum power produced Net energy sent out Private consumption Load factor MW MW MWh MWh % Coal Athlone Kroonstad Swartkops* Bloemfontein Kelvin A Kelvin B 180 30 240 102 180 420 92 0 15 119 218 0 0 0 0 0 17.9 0 32.2 57.7 63 Orlando Rooiwal 300 300 62 180 0 0 13.6 64.5 Pretoria West Gas turbines Roggebaai Athlone Port Elizabeth Johannesbur g Pretoria Pumped storage Steenbras 180 116 144 286 0 42 322 601 145 1 203 916 73 945 1 016 719 298 100 0 29.3 40 40 40 37 12 0 144 47 0 0 0 0 0.4 0 0 176 78 5 134 0 0.8 24 24 30 0 0 180 179 - 94 264 0 18.4 * Decomissioned in 1998 98 5.3. Renewable energy IPPs under development At the time of writing the NER has received licence applications or pre application project descriptions from three potential renewable energy IPPs. Of these, DARLIPP (wind) and Bethlehem Hydro are at the feasibility phase of development and could be implemented within the next 1-2 years. The other project is Green Energy (wave), which is still in a pre-feasibility phase. Apart from the renewable energy IPPs under development a number of non-renewable energy based power projects have been submitted to the NER for licensing or as preapplication descriptions of potential IPPs. These projects are in various stages of development and include: Proposed Cape Town Natural Gas power plant 1000MW Refurbished Pretoria West Power Station (coal/gas) 180 MW Refurbished Johannesburg Kelvin Power station (coal/gas) 300 MW Eskom Pebble Bed Modular Reactor (nuclear) 100 MW+ Richardsbay (fluidised bed coal plant) 210 MW Solid Waste Technologies (municipal waste) 60 MW It is clear that the proposed renewable energy IPPs are of a smaller scale than the nonrenewable energy power plants. This fact that small IPPs tend to be based on renewable energy technologies (RET) is due to the relatively small economies of scale that can be achieved by RETs. This small scale is also an advantage as it enables a closer correlation between electricity demand and supply by adding smaller steps of generation capacity than would be possible with fossil fuel technologies. The lumpiness of fossil fuel generation is evident from South Africa’s past practice of adding a 3.6GW coal fired power station at a time and Cape Town’s proposed 1000 MW gas fired power station. 5.3.1. Darling Independent Power Producer (DARLIPP) Wind power has a substantial potential in South Africa. Today there are about 300,000 windpumps for livestock and community water pumping, but less than 1 MW of electricity generating wind turbines. Especially on the West Coast, the wind potential seems good. In 1996 a private company the Oelsner Group identified a promising site for a wind farm in Darling, North of Cape Town. The Oelsner Group has then founded a company, Darling IPP (DARLIPP) for the purpose of electricity generation and sale using wind energy technology. Darling IPP has conducted a pre-feasibility study in 1997/1998 for a 5 MW wind farm. Preliminary wind measurements were carried out and results show an excellent wind regime with a potential in access of 7 m/s average wind speed In 1997 the Oelsner group involved the wind turbine manufacturers AN Windenergie GmbH of Germany and Bonus Energy A/S of Denmark to provide input to developing the wind farm in the Darling area. 99 The Moedmaag Hill on the Slangkop Farm outside Darling was originally identified as the site. CSIR (a national technology centre) became involved to undertake the site wind measurements. The Environmental Evaluation Unit (EEU) of University of Cape Town (UCT) was contracted to conduct the Scoping Process required by the Environment Conservation Act, requested as a consequence of the necessary application submitted to Cape Nature Conservation. A lease agreement for land has been entered with the landowner owning part of the hill and the West Coast District Council has been approached in order to obtain the departure or rights to special uses in terms of the Ordinance on Land Use Planning. The 12th of June 2000 the Minister for Minerals and Energy approved the following Ministerial Submission Recommendations: The Minister of Minerals and Energy support[s] the declaration of the Darling Wind Farm as a National Demonstration Project as per... [(a) and (b) below] in a bid to develop strategies for wind energy generation in South Africa. (a) As a National Wind Farm demonstration Project, the Darling Wind Farm will through its implementation of the policies of the White Paper on Energy, test and or inform decisions around replicable new and or novel approaches to recognised energy and environmental problems and will act as a platform for replication by the public. (b) According to DME Guidelines for Energy Policy Projects 1994/95: Demonstration Projects of products, processes and technologies may be supported if the project meets the above criteria and their primary focus is to produce one or more of the following outputs.: Economically viable solution to an identified energy issue; Formulated or implemented national energy policy; Demonstrated operation on site under actual conditions; Reduced barriers to market entry; Publicised results of demonstration. The Minister also supports the request for international assistance from the Global Environmental Facility (GEF) and the Danish Co-operation for Environment and Development (DANCED) in the designing of a National Legal and Regulatory Framework in partnership with the Department of Minerals and Energy. The latter will come up with guidelines on how to assess and process Independent Power Producers (IPPs) and power purchase agreements (PPAs) using the Darling Wind Farm Demonstration Project as a case study. In case of the Darling National Wind Farm, the Department of Minerals and Energy’s definition of Demonstration Project is as follows: “As a National Wind Farm demonstration Project, the Darling Wind Farm will through its implementation of the policies of the White Paper on Energy, test and or inform decisions around replicable new and or novel approaches to recognised energy and environmental problems and will act as a platform for replication by the public. 100 Darling National Wind Farm Demonstration Project: Rationale and objectives: TECHNICAL: The project aims to adapt, develop and apply existing technology to local conditions and needs and to act as a pilot project for Eskom and the public, to resolve technical and structural issues relating to assisting Independent Power Producers (who may be or may be not foreign financed) participate in meeting South Africa’s electricity generation and environmental conservation needs. ENVIRONMENTAL: To contribute to the restoring of the global environment in accordance with recommendations of UNCED (Agenda 21) by identifying barriers for possible replication and provide suggestions on how those barriers could be removed. The project will contribute and activate replication of similar projects and together it will make a real improvement to air quality, reduce carbon dioxide emissions and therefore global warming as well as other gases (sulphur dioxide and nitric oxide) that contribute to acid rain. To be a showcase and example of the Government’s commitment to the Framework Convention on Climate Change through emission - free generation of electricity and working towards an investor- friendly climate in the energy sector. SOCIAL: To promote the benefits and use of wind energy as a commercially viable way of generating electricity by running an Education Centre and contributing to Governments information dissemination efforts around energy matters and environmental impact. It will demonstrate and provide a planning framework for the Government how to approach an equitable balance between priorities for developing (RDP) and environmental conservation. To demonstrate how a South African wind energy industry could contribute to the creation and retention of jobs and skills. To participate in the social up-lifting of the Darling and surrounding areas by bringing jobs to, and sharing wealth (e.g. equity share holding) with, the local community. To include and provide capacity to previously disadvantaged persons (economic empowerment) as equity shareholders and be appointed to the board of directors for decision making and capacity building processes. FINANCIAL & ECONOMIC: It provides an ideal case study and opportunity for South African banking and investment sector e.g. Development Bank of South Africa (DBSA) and a platform for international funders (e.g. Global Environmental Facility (GEF) and the Danish Cooperation for Environment and Development (DANCED) for promotion, facilitating and testing of innovative renewable energy financing options. 101 MARKET: To demonstrate the generation of electricity from wind energy, and its potential to contribute positively to the infrastructure development of South Africa within a successful and sustainable national growth and development strategy. POLICY: Capacity building in the implementation of the Energy White Paper renewable energy in policy, legislation and aim of achieving energy security in electricity supply and environmental restoration through diversity of supply sources. To act as pilot project for legislators to identify and resolve critical issues such as transparency in the generation sector, availability of information, and non-discriminatory open access to uncommitted capacity on the national transmission network. INSTITUTIONAL: The project provides an opportunity for interested parties e.g. NER, DBSA, DEAT, DME, Darling Municipality, DARLIPP etc. to share the risk in the development process which otherwise would not have been possible to be carried alone. The Darling Demonstration Project adheres to the DME Energy Guidelines for demonstration projects and presents an ideal case study as a demonstration project with national spin-offs to the country. As this is a demonstration project and no similar activity has been undertaken in South Africa to learn from, considerable cost (approximately R5 mil project value) and time has been contributed by stakeholders and investors and is going into the development process. This investment in Darling IPP is a so-called Ethical Investment and all investors are participating and taking risks “for the better”. The financial model allows only for a very low return in order to be able to sustain itself. The development process is open, transparent and the outcomes are available to form a basis for others to learn from how to replicate similar activities cost and time efficiently in South Africa.” Following the Minister’s declaration of the Darling Wind Farm as a National Demonstration Project, the Danish Co-operation for Environment and Development (DANCED) and the UNDP/GEF developed project documents for possible assistance to the preparation of the project. According to these plans, the generation of all necessary information will be completed by November 2001, and the establishment of the wind farm will be initiated in May 2002. 102 Summary - Darling Independent Power Producer (DARLIPP) In 1996 a private company the Oelsner Group identified a promising site for a wind farm in Darling, North of Cape Town. The Oelsner Group has then founded a company, Darling IPP (DARLIPP) for the purpose of electricity generation and sale using wind energy technology. Darling IPP has conducted a pre-feasibility study in 1997/1998 for a 5 MW wind farm. Preliminary wind measurements were carried out and results show an excellent wind regime with a potential in access of 7 m/s average wind speed., The Minister of Minerals and Energy support the declaration of the Darling Wind Farm as a National Demonstration Project. The Darling Demonstration Project adheres to the DME Energy Guidelines for demonstration projects and presents an ideal case study as a demonstration project with national spin-offs to the country. As this is a demonstration project and no similar activity has been undertaken in South Africa to learn from, considerable cost (approximately R5 mil project value) and time has been contributed by stakeholders and investors and is going into the development process. This investment in Darling IPP is a so-called Ethical Investment and all investors are participating and taking risks “for the better”. The financial model allows only for a very low return in order to be able to sustain itself. The development process is open, transparent and the outcomes are available to form a basis for others to learn from how to replicate similar activities cost and time efficiently in South Africa. Following the Minister’s declaration of the Darling Wind Farm as a National Demonstration Project, the Danish Co-operation for Environment and Development (DANCED) and the UNDP/GEF developed project documents for possible assistance to the preparation of the project. According to these plans, the generation of all necessary information will be completed by November 2001, and the establishment of the wind farm will be initiated in May 2002. 103 5.3.2. Bethlehem Hydro Project Description In the middle of 1997 a mini hydro project was identified in South Africa by a landowner and a civil engineering consulting firm. What makes this relatively unique is the fact that South Africa does not have many rivers with a constant yearly flow. Generally the rivers are dry in the winter period (May to October) and have a high flow during the summer months (November to April). The Axle River, where the project was identified, however has an average (guaranteed) flow, which is artificially regulated, from the Lesotho Highlands. This water flows via the Axle River over a distance of approximately 300 km to Johannesburg where it is used for drinking water purposes. The South African and Lesotho Governments have entered into an agreement guaranteeing the yearly flow in the river. Furthermore in the past, the generation of electricity was strictly regulated in South Africa and fell solely within the mandate of the national electricity utility Eskom. The new energy policy stance of the post-apartheid government allowing electricity generation by the private sector and the constant water flow in the selected rivers led to the project proposal being formulated The project was subjected to a pre-feasibility study by the project initiators. This prefeasibility study showed that the project was broadly feasible. In terms of size the project was relatively small (approximately US$ 4,5 million). However the sunken costs for a project (detailed feasibility and development costs) are typically independent of its size. Small projects therefore have a relatively high sunken cost percentage in relation to the total investment. This problem, which is universally encountered, prevented the project from going forward. The project initiators therefore approached a Dutch consultant with the request to investigate the possibility of some form of concessionary finance to cover the sunken costs. The project parameters made the project an ideal candidate for the AIJprogramme of the Netherlands Government. The project is in the renewable energy sector, mitigates large amounts of CO2, has a developmental function and is commercially sustainable. SA is also a signatory of the Kyoto Protocol. To make the project an even more attractive object for (international) investors it was decided to include another project Krokodilpoort, which had been identified in 1989 but was never implemented due to financial constraints of the initiators. A further benefit would be that the concessionary finance per ton CO2 mitigated would be further reduced if this project were included. In a rural area of South Africa close to the major town of Bethlehem in the Province of the Free State, a town with a large black rural community, two sites have been identified which are ideally suited for the construction of mini hydro generation plants. The first site is situated at the Saulspoort Dam Wall. The town of Bethlehem uses this reservoir for drinking water. The effective head at this site is about 10 – 12 m. The dam wall offers a unique opportunity to construct a mini hydro plant without having to execute large civil works. The flow in the river is 24 m3/s. However, due to a plan to extract water 35 km upstream for the city of Johannesburg, this flow will be 104 most likely reduced to 12 m3/s in 2012. The installed capacity for this site amounts to 1050 kW. The site is close to the water pumping station of the Bethlehem Council, their existing transformers and other electrical infrastructure, hence major electrical and/or civil works are not to be expected. The latter is of importance as experience has shown that the civil works are major cost factors in hydro projects and can be classed as “killer” aspects for mini hydro schemes if they tend to be extensive. The other site will be along the banks of the Axle River, between 20 and 35 km upstream from Bethlehem. The Department of Water Affairs (DWAF) will be erecting in total 14 weirs in the years 2000 to 2001 in order to reduce the unexpected high erosion in the river since the increased water flow as a result of the delivery of water from Lesotho. In the present scenario it is proposed to construct a 3.5 km pipeline from one of the weirs belonging to DWAF to a point 40 m lower. This head in combination with the 12 m3/s flow allows a capacity of 3700 kW to be installed. The generated electricity from this plant will be evacuated to Bethlehem who will also be the base client for this plant. It should be noted however that the exact location of the River Site has not been established. This will require detailed topographical and hydrographical analyses to be made and these results to be co-ordinated with the weir building activities of DWAF. It is not unlikely that this exercise will lead to a more optimal location and solution to be found. From Clarens, the river source, to Bethlehem, which is a distance of about 40 km, the river, drops in total 80 m. According to the engineers who have been consulted the required head is therefore not a problem. The detailed feasibility will have as one of its main tasks therefore to identify the most optimal site from a cost, technical and construction point of view. At the advice of the engineering consultants the economic modelling in this proposal looks at the most expensive option, i.e. a 3.5 km pipeline resulting in a 40 m drop. The Axle River flows into the Saulspoort dam and is fed from the Lesotho Highlands Water Scheme. As said, the inflow from the Lesotho Highlands Scheme takes place at Clarence (see photo) and the water flow is guaranteed from this scheme on a yearly basis (Ave. 24 m³/s). As is common in S.A., the town of Bethlehem purchases electricity from the national generator Eskom and is dependent on ESKOM’s price structure in determining the tariff structure being passed on to consumers. The average cost price of the electricity purchased by Bethlehem in 1997/1998 amounted to R 0,1462/kWh. This price reflects a combination of base and peak load tariffs. The economic model used an Eskom – 10% tariff. Therefore the buyers will be assured of a 10% reduction in energy costs when purchasing from the hydro stations. Project structure It is proposed to develop the project as a BOO (Build, Own, Operate). A number of project participants have been identified, who will supply technical support, operate the plant and provide financing. In this regard a dedicated IPP has being registered in South Africa. This company named Bethlehem Hydro, will develop, implement and operate the mini-power stations. 105 The shareholders in the company will be the equity partners which have indicated their interest to invest in the project pending due diligence (detailed feasibility). At this stage Cinergy Global Power Ltd (UK), who have a local office in Johannesburg have indicated their interest, as has Electricité de France (EDF) who also has an office in SA. The Dutch Utility NUON has indicated interest in the past. However without a more detailed feasibility study NUON at this stage cannot commit itself yet. The development process has been taken over by the Dutch project management company Planet and a local energy consulting firm e3 Energy & Environmental Management. Bethlehem Hydro has applied for an IPP license from the National Energy Regulator and has also applied for the necessary licence to use the water resources in the river for generation purposes. The Department of Water Affairs conducts the latter licensing procedure. At this stage a number of local businessmen have indicated their interest in the project and in becoming shareholders in the project. Next to equity Bethlehem Hydro will attract (foreign loan) capital and as this project meets the requirements regarding CO2 emission reductions and is in the renewable energy sector, donor funding will be sourced to assist in covering the non-commercial sunken costs such as the development costs. Extensive talks with the Bethlehem Transitional Local Council have indicated a strong interest in the project. The Local Council has indicated that it supports the project and has written a Letter of Intent to purchase the generated capacity conditional to certain requirements 106 Summary – Bethelehem Hydro: Mini Hydro Power project of 9,81 MW. (1.05 MW, 3.7 MW and 5,06 MW). All the plants within an acceptable range of a major rural town. The town(s) will be the major base client(s) for the plant(s). Two plants to be constructed on the Axle River close to the town of Bethlehem. Of these plants one at an existing dam wall with a head of 10 - 12 m, the other at a drop in the Axle River of approximately 40 m. The long-term water resource in the Axle River amounts to some 12 m³/s. Economics: Total cost estimate R 65 million complete. Approx. 8-10 year payback at 13 c/kWh and interest rate of 16%. Present average yearly electricity price for town is 14,6 c/kWh. Estimated rate of return on equity after taxes is +20 % based on pre-feasibility Avoided CO2 emissions approx. 64.000 tons/CO2/year. Cost per ton CO2 mitigated (based on AIJ-finance) is approximately US$8/ ton CO2 (depreciated in 1 year) or US$0.43/ ton CO2 (depreciated over lifetime) Project Status Project identification and pre-feasibility completed. Project development team secured. Intent to purchase obtained from base client. Discussions ongoing with Town Council re. Power Purchase. Detailed feasibility study required. Pending feasibility study outcome, project development to be completed. Project participants identified, IPP Company established. Commitments from stakeholders secured. Concession to generate power applied for from National Government. In principle approval obtained Tentative permit to utilise water resource applied for and received. Financing for feasibility study to be secured. Pending study outcome bulk financing, equity partners and investors to be finalised. 107 5.3.3. Krokodilpoort hydro The Krokodilpoort site is situated in the Mpumalanga Province at a distance of about 25 km from the provincial capital of Nelspruit. Nelspruit is already being serviced by a 2 MW mini hydro at Friendenheim. This plant has been in operation since 1988 and has proved to be a commercial success. The Return on Equity is in excess of 20% and the plant had paid back the investment after 3 years. The Friedenheim is located nearby on the Crocodile River. The Krokodilpoort site is also situated on the Crocodile River and shares a number of project parameters with Friedenheim. Initially in 1989 MBB Consulting Engineers for the Malelane Irrigation Board prepared a pre-feasibility study for the Krokodilpoort site. This pre-feasibility showed that the proposal was highly feasible. However due to financial constraints and political uncertainty at the time, the proposers decided not to take the project further. The site is situated at a weir where a 70-m fall is encountered over a distance of 3 – 3.5 km. This delivers an effective head of 62 m and allows a generating capacity of 5060 kW consisting of four 1265 kW units to be installed. The flow in the river is a stable 10 m3/s average per year. The site is close to two major black towns Kanyamazane and Matsulu. These towns are at present purchasing their power from Eskom and have indicated their willingness to purchase the power from the hydro stations if the price is competitive. The project pre-feasibility has been obtained by assuming a purchase price by these towns of Eskom – 10%. The project shows an Internal Rate of return of 16,6% with a Return on Equity of 17,2%. These figures are based on a very rough escalation of the 1989 figures and are therefore merely an indication. It is proposed to develop the project as a BOO (Build, Own, Operate). 5.3.4. Other Green Energy The NER has been approached by ‘Green Energy’ that is proposing to develop a wave powered power plant with a present maximum capacity of 30 MW in the Western Cape area. The Saldana area is seen as having a favorable wave energy regime for power production. The technology is based on an Israeli concept developed by SDE Energy. The system uses wave follower - hydraulic actuators to generate electricity. A Performance Bond from Israeli Government is awaited Green Energy has entered into negotiations with the West Coast Peninsula Transitional Council as a potential purchaser for its power. Current estimations put the cost of electricity produced at 10.2 SA cents/kWh which is likely to be an attractive price for a bulk purchaser of electricity. Operational costs are estimated at the order of 1.72 SA cents/kWh over a life cycle of 20 years. And the project development time is around 24 months. The developer, Green Energy has identified the following aspects as institutional barriers: Absence of policy details regarding IPPs 108 Uncertainty and delays in the issue of IPP license Appropriate & realistic sharing of existing transmission infrastructure Solid waste recycling and electricity generation Although waste incineration is not a ‘true’ renewable energy technology it can well be grouped under the heading of sustainable energy. The project is of interest as it shares a lot of factors common to IPP development and is illustrative of the type of project that may be developed in SA. The project is being developed by Solid Waste Technologies Gauteng (Pty) Ltd. Proposal objective To develop a solid waste recycling and electrical generating facility by implementing the Thermoselect technology in South Africa. Description Landfill sites are currently used as the primary method of waste disposal in South Africa. Thermoselect is a waste processing facility specifically designed to eliminate landfills and incineration plants. The technology requires no expensive front-end waste pre-sorting and is processed as it is received. The waste is mechanically compacted into a tenth of its original volume under 1,000 tons of pressure and compacted into 1 x 1,5sqm gas type plugs. These plugs are loaded into a highpressure furnace, and converted into carbon. During this time, all liquids are vaporised. The glass and metals in the waste stream are left embedded in the carbon. As the plug moves out of the heated tunnel into the chamber, oxygen is introduced into the furnace. The high temperature destroys all complex organic chemicals and the glass and metals are melted down and separated by a sharp cooling process in the system. The recovered energy-rich gas is used as a fuel to continue the process. The surplus gas is used to generate electricity and sold to local municipalities. Project Proposal Solid Waste Technologies of South Africa together with Interstate Waste Technologies of Pennsylvania - U.S.A. offer the facilities to the Provincial Government. Furthermore the facility will be erected at no cost, and will be under the management of a professional management team at a provincial government allocated site. The plant will be constructed on the land provided over an 18month period with a labour force of approximately 1,000 people. This will result in a lucrative job creation opportunity. Furthermore employment for approximately 200 people will be created for the operating of the facility. For the distribution of the by-products approximately an additional 1,000 people may be employed on average for each by-product e.g. a facility built with four waste streams should create employment opportunities direct and indirectly for 4,000 people. Likewise 10 waste streams will create opportunity for 10,000 people. Economic benefits One million ton per year facility will export 68 MW of electric power for sale to the local authority. 109 Over 300 facilities have already been built in Europe and Asia and have proven the technology to be a success both economically and is an environmental sound solution A one million-ton per year Facility will export 68 MW of electric power for sale to the local utilities, thereby avoiding importing 33,000,000 gallons of foreign oil each year of its operating life. The modular design allows construction of a complete facility in about 18 months as compared to 30 months for a mass bum incinerator. Adding additional modules for waste disposal and electric generation can easily expand the Facility. Requirements The capital to erect and operate the plant will be supplied by the Solid Waste Technologies. In order to facilitate this the project will require the following commitments from the provincial government. All local authorities to deliver all waste to the facilities 7 days per week - 365 days per year. Local authorities to commit to purchase electricity and gas produced by the plant at a lower cost than the current rates of the electricity supplier. Proposed service agreement between Solid Waste Technology Gauteng and Provincial Government A. Facility Design, Construction and operation SWT will finance, build, own and operate a solid waste gasification facility using the Thermoselect technology. The facility will be comprised of 10 Thermoselect processing lines, each with a nameplate capacity of 300 metric tons per day. The facility will be capable of processing 1,000,000 metric tons of waste per year, Electricity surplus to the internal requirements of the facility will be sold to the local electrification utility. B. Solid Waste Technologies Obligations Pay all costs of financing, construction, operation, and maintenance. C. Provincial Government Obligations Provide reasonable documentation, testimonial and other support for permits and approvals required by SWT for the facility. Cooperate with SWT in informing the public regarding the benefits of the facility. Identify a suitable site for the Facility having access to a road or rail network, adequate water supply and electrical supply. The provincial government shall designate the facility as the sole legal site for the disposal of solid waste and shall deliver the agreed quantity of solid waste to the facility Purchase 67 MW of export electric power generated from the Facility for the term of the agreement, 110 5.4. Barriers and other factors influencing IPP development in South Africa 5.4.1. Conflicting messages A major barrier to IPP development in South Africa is the conflicting messages emerging from the Government. On the one hand the Energy White Paper gushes forth about encouraging ‘the development of renewable an environmentally sound electricity generation technologies’ and to ‘encourage more players to enter the generation industry in order to develop a competitive power market’. On the other hand the Electricity Act was written to protect Eskom’s monopoly interests. The NER Board (appointed by the government) has not approved of any additional generation licences after the initial licensing round that followed the NER’s creation. This in effect is restricting the creation of the conditions necessary to increase and encourage competition by for example prohibiting long-term power purchase agreements (see below Section 0). This situation results in a sit back and wait attitude from potential investors and IPP developers. 5.4.2. Tariffs The main factor that is keeping new private generation development at bay is the low cost of Eskom’s electricity. The incremental operational expenditure cost of new generation ranging from hydro to coal and gas is estimated in the range of R 0.140.18/kWh. Compared with Eskom’s current average tariff of R0.16, this leaves little scope for recovering capital costs. Looking at the medium term, especially at when Eskom generation surplus is expected to end (2005-2010) it is inevitable that electricity tariffs will increaseDevelopers of the Johannesburg Kelvin and Pretoria West IPPs estimated the increased tariff at about R 0.25-0.4/kwh by 2010. This paints a completely different picture. A whole range of generation technologies and IPP will be competitive at this range of tariffs. An IPP, which is in the feasibility phase at present, such as Darling, Bethlehem, Pretoria West and others can be brought online in say 2003 – 2005. With a typical lifecycle of 20 years one must now consider the tariff structure that will be relevant in the period 2003 – 2023. Clearly these tariffs will be vastly different from the present set. The exact tariff range volatility is largely dependent on the future structure of the electricity supply industry and the amount of competition in the market. These factors are under consideration by the DME and the NER at present through a number of research projects. Transparency and consultation in the policy development process is essential to establish confidence and attract more investors to the SA generation market. Another consideration is the need to wheel power from the IPP through the transmission network to a customer. Eskom controls the transmission network, which is at liberty to raise a wheeling charge. To circumvent this stranglehold, generators such as Friedenheim have prompted to build their own power lines to link to their customer. This is off course an additional cost to the IPP. The NER that is also 111 responsible for regulating transmission in SA has mentioned that it would see a transmission charge of about R 0.01/kWh appropriate. The transmission charge will need to vary with the transmission distance and other technical criteria. 5.4.3. Project developer profile IPP development is a commercial and profit driven profession. The development of an IPP is a business venture and should therefore be driven from the commercial and business sectors. In South Africa there is at present little interest or involvement of the commercial sector in the development of IPPs. The reason for this is that under present circumstances IPPs are not a viable business venture. The country lacks the appropriate legal and regulatory framework, the electricity sector is in a state of flux due to imminent restructuring and there is no significant bulk demand for power. Trying to develop an IPP under these conditions incurs long and costly project lead times with no immediate returns. It is however exactly these factors and high risks which present opportunities for those organisations and individuals who believe that a market for power and IPP is imminent and those who are in first stand to benefit. Looking at the applications to the NER for generation licences an interesting profile emerges. Four of the applications are from existing power producers, the municipalities and Eskom, two are for renewable energy IPPs, one is from the coal sector and only one is from outside the South African energy sector (Solid Waste Technologies). There are no applications from the biomass (bagasse and wood) sector, which are probably the renewable energy generators in the best position to convert to IPPs. The present entrepreneurial nature of renewable energy IPP development in SA is attracting a specific kind of developer. These developers often lack the specific skills required for energy project development. For both Darling and Bethlehem these are the first project attempted by the developers. These project are also developed at the developers own risk and using own resources. This lack of experience inevitably lengthens the projects development time. It is only by accessing the appropriate IPP development skills and expertise that these projects can be turned into potential flyers. Both projects have however now succeeded in doing this by attracting concessionary financing which will provide the working capital required for business plan development. It is unlikely that until the IPP market in SA is better established and a competitive regulatory framework is secured that the development process will be any easier or faster. Budding IPPs will however benefit immensely from a bit of ‘hand holding’ during the development phase. This support should include at least project development and business skills with some technical and financial backup. 5.4.4. Demand for generation capacity The strongest incentive to bring new generation capacity online is that of a present or foreseen power shortage. IPPs thrive in situations of power shortage. That situation does not exist in South Africa at the moment. In fact South Africa currently has an excess of electricity potential to the order of 8 000 MW. Looking into the future it is 112 expected that South Africa will require new base load power between 2005 and 2010 and peak power possibly earlier. Where there is no shortage of supply or generation capacity in a market the next best bet for an IPP is to produce power at a competitive cost with the current tariffs. With Eskom being one of the cheapest producers of electricity in the world, South African electricity is particularly cheap. Undercutting Eskom by selling electricity into the wholesale market in South Africa (i.e. to Eskom) is near impossible. The way around this is to undercut Eskom at the point of supply to a bulk customer such as a municipality, which buys both cheap off peak as well as expensive peak power from Eskom. The result of this mix is that the average cost at the gate is more than double the rate at which one could sell to Eskom. Average electricity sale price is R 0.16/kWh, (NER 1999). The large number of non Eskom generation plants in South Africa shown that it is quite possible to undercut Eskom in supplying to a specific customer without compromising commercial returns. 5.4.5. Stranded Assets The potential treat that undercutting Eskom poses is that of stranded assets. If more and more capacity is brought online selling power at a rate below that of Eskom eventually demand to Eskom will decrease to such an extent that it will have to reduce its generation levels and even shut down a power station. This fully or partially shut down power station becomes a stranded asset. The plant can still produce power but it cannot compete against the lower cost producers. The investment in the power station is therefore not bringing in any returns. In the case of Eskom where the public utility was financed from public coffers it will result in a loss to the state and the public. Government is therefore loath to support initiatives that carry the potential threat of stranded assets. In reality there is quite a bit of scope for bringing new capacity on line without stranding any Eskom assets. As long as the increment at which new power is added remains small to Eskom total generating capacity the stranding impact is negligible. Adding a 5-10 MW to the system of close to 40 000Mwis unlikely to attract much notice. Eskom can actually benefit from the addition of distributed small scale generation capacity as is provides stability to the large transmission system which connects the clustered coal fired power stations over long distances to its customers. Bulk buyers of electricity, particularly municipalities have learned through the years of being stuck with a singe electricity supplier that having your own generating capacity (allowed under the Electricity Act) puts you in a lot stronger bargaining position with Eskom. More often than not Eskom will supply power at such a tariff that it is not worthwhile for the municipality to run its own power station. Experiences such as with Friedenheim or Bethelehm Hydro have shown that municipalities are willing to move away from sole dependency on Eskom to a more diversified and lower cost mix of supply. 5.4.6. Power purchase agreements Critical to the successful development of an IPP in an electricity market such as South Africa is securing a power purchase agreement. A PPA is a contractual commitment 113 by organisation to buy the power produced by the IPP on certain conditions. The value of a PPA is such that its existence is usually enough to guarantee the development of the project. The ideal PPA is based on the purchase of all the power produced by a power plant over its lifetime. In order to achieve this the selling price of electricity will usually be specified in the PPA as being lower than in this case Eskom’s tariffs and to retain this margin by varying over time. This moves the risk of tariff volatility away from the buyer of the electricity to the IPP. In addition a long term PPA is critical to provide comfort for commercial debt providers. The Electricity Act of 1987 provides for the National Electricity Regulator (NER) to licence all electricity generators above the threshold generation of 5GWh/year. The stance of the NER on PPAs, is stated in the covering letter to the generation licence application. The NER will ‘Advise such applicants that the NER, in the exercise of its mandate to protect the interests of electricity consumers in South Africa, will not approve the entering into of long term power purchase agreements (PPA’s) between generators and distributors.’ This position on PPAs is relevant to large power projects that should be able to compete in the future electricity market. The concern of the NER Board is not to compromise present 'captured' customers, who in future may have a choice of supplier. The NER Board also realises that the practicality of enabling small renewable generation, embedded in distribution networks, would require a different approach. 5.4.7. Financing: Equity The electricity market in the developed world, most notably in Europe, has been segmentation into sustainable or green power and non-sustainable power usually fossil fuelled. This segmentation combined with targets for the renewable energy portion of electricity production had created a generation shortage in the grid connected renewable energy market in the EU. Utilities and IPPs are rushing to provide power into this market. Global warming as one of the drivers behind the rise of sustainable energy has brought a new dimension to the South African energy market. Although there is no local distinction between sustainable and non-sustainable energy, international utilities with green energy targets or quotas are keen to invest in commercially viable sustainable energy projects. The money is there; we just need to get the right projects. 5.4.8. Financing: Debt South Africa has a well functioning and very competitive banking sector. Most of the larger banks have project finance divisions, which specialise in the financing of projects such as IPPs. These banks will be more than willing to provide finance to IPP projects provided security and comfort can be provided for around issues such as: The commercial viability of the project Scale of the project and the loan component Long term PPA or equivalent 114 The payment for the PPA is secured through the appropriate credit rating of the purchaser or other mechanisms Stable regulatory and policy environment Risk is shared with equity holder The terms of the financing will vary with the perceived risks of the project. In South Africa IPPs are seen as ‘entrepreneurial projects’ which carry an according high risk. The financing terms provided will therefore only allow the most secure and most profitable projects to be financed. Projects, which are marginal in terms of returns on investment and debt coverage, will not make the grade. An important criterion is that of project size. The project finance products available from the commercial banking sector are only viable when applied to project with a debt component of around R 30 million and over. Below this level it is not interesting for banks to consider financing. A debt component of R 30 million usually implies a project with total capital cost of around R60 - 100 million (debt equity ratios of 50/50 or 30/70). Taking the rule of thumb of US$1 million/MW this gives a minimum debt financed project size as 9-15 MW. This minimum size may rule out a swath of potential renewable energy IPPs that lie below this level in capacity. 5.4.9. Concessionary and venture finance An alternative to conventional project finance is to ‘subsidise’ the project through concessionary financing. Fortunately there is a growing concessionary and venture financing market available for sustainable energy projects. This can range from Global Environmental Facility (GEF) funds to bilateral climate change programmes such as AIJ/CCM and from development banks such as the DBSA to venture funds such as the Renewable Energy and Efficiency Fund (REEF) and E&Co. Concessionary financing can cover an incremental component of the project GEF) to bring the costs in line with conventional power costs in a market. This mechanism is being used by the Darling IPP project. Alternatively the concessionary financing can cover the development and high risks costs of a project (AIJ/CDM) such as feasibility studies and business plan development. Bethlehem Hydro is utilising this source. Concessionary financing motivated from a climate change perspective usually has the function of removing some of the risk and financing barriers faced by sustainable energy projects as compared to conventional or fossil fuel projects. Development Banks such as the Southern African DBSA or the Dutch Triodos Bank have specific objectives regarding environmental and developmental sustainability governing their activities. These banks are sometimes willing to provide financing where the commercial sector would not be or on better terms. Venture funds such as the USA based E&Co will come into a project as first stage investor in order to take a share of the risks and provide a higher level of comfort for other financiers or second stage investors. 115 To develop a renewable energy IPP in present electricity market in South Africa takes a considerable amount of ingenuity and perseverance to come up with the right structure for a project and to identify those sources of debt and equity. References 1. Cochrane,E.D.D (1998) The use of biomass for electric power generation in the South African and Zimbabwean Saw Milling Industry. EDD Cochrane & Associates Consulting Engineers. Cape Town South Africa 2. NER (1999). 1998 Electricity Supply Statistics for South Africa. National Electricity Regulator. Johannesburg, South Africa 3. Anderson RB (1994) Synthesis report on cogeneration and independent power production in South Africa. Department of Minerals and Energy Affairs. Pretoria, South Africa. 116 6. FINANCIAL AND ECONOMIC EVALUATION OF RENEWABLE ENERGY 6.1. Introduction The ”White Paper on Energy Policy for the Republic of South Africa” (1998) stated the Government’s expectations on electricity pricing (page 39): “Price signals should result in economically optimal investments in electricity infrastructure and consumption of electrical energy. Government is of the view that this will generally be achieved through the use of cost-based electricity tariffs which include capital replacement costs (long-run marginal costs).” It was further emphasised (page 40) that “cost-reflective tariffs will be applied at electricity distributor supply points in due course”. On this background, the aim of the present chapter is to determine the Long Run Marginal Cost (LRMC) for traditional coal-fired generation and compare this with the LRMC of renewable energy independent power producers (REIPPs). A renewable energy generator could argue that the avoided cost be determined by the cost of the pebble bed nuclear reactors proposed for the Western Cape. However, as more than 90% of the existing capacity is coal-fired, this technology is still the trendsetting technology, and the study has therefore chosen coal-fired generation to be the alternative to renewable energy. The marginal cost is not the embedded cost of current generation resources, nor is it the average or peak cost of electricity. It is the anticipated cost of a new power plant in future years. The last few years there has been a slow growth in electricity demand (below previous predictions), which has resulted in excess capacity. The present peak load is 27,800 MW while the available capacity is 40,000 MW8. At the same time the South African Rand (ZAR) has devalued considerably. Together, this has resulted in an unclear picture of the capital costs measured in ZAR. For this reason, the present study has found that international data on investment costs provide a more realistic estimate of the LRMC than historical data from South Africa. 6.2. Financial aspects The annual inflation in South Africa has for some years been 7- 7½ % but is now declining. According to the Financial Times’ Annual country report (FT October 6 2000) the inflation (annual % change in CPI) was 5.2 % in 1999 and is forecasted to become 6.2 % in 2000. The calculations in the present report have been based on a constant inflation rate of 7% per year. Interest rates in South Africa are high. Interest rates for large, long term, bankable projects with firm power purchase agreements are typically between 14.5% and 16% 8 Eskom, Annual Report 1999 117 per year, equivalent to a real interest rate of about 8-10%. Nominal interest rates for other energy projects can go as high as 30% For comparison it should be mentioned that the US and most EU countries have real interest rates for long term financing of about 3-5% or half of the SA figures. This situation has a negative impact on the financing cost, in particular for projects for with high initial costs, such as many renewable energy technologies. The high interest rates in South Africa are not always reflected in how the capital cost or return on capital is calculated. In Eskom’s latest Annual Report (1999) the real (inflation adjusted) return on total assets is as low as 0.90%. This is far below the SA market rates. From 1990 to 1999 Eskom has had return on total assets between 7 and 12% real. In 1998 it was 9.69% and in 1999 7.37% (Eskom’s Annual Report 1999). In this report, a nominal interest rate of 16%, equivalent to a real interest rate of 8.4% per year, has been applied. 6.3. Real cost of coal-fired power generation In South Africa electricity generation has traditionally been based on coal. Presently about 90% of all generated electricity is from coal-fired power plants. The remainder comes mainly from nuclear and hydro. The present study looks into the issue of utilising other sources for electricity generation. The long run marginal costs (LMRC) shall be based on the costs of new power plants. For this reason, international data on investment costs provide a more realistic estimate of the LRMC than historical data from South Africa. 6.3.1. Direct costs Investment costs In the 1980’es Eskom was building for a 10% annual growth in electricity demand. The down-turn of the economy has therefore resulted in a considerable surplus capacity. During the time when most of Eskom’s current capacity was established Eskom made use of forward cover to protect against exchange rate changes. This policy paid off well, because the Rand has devalued from about R2 to a pound sterling to R10 to a pound since the power station construction peaked in the early 1980’s. Today, Eskom therefore has no need to establish new coal-fired plants, and the capital costs of the existing capacity does not reflect the real cost of establishing new plants. On this background, the estimation of capital cost in the present analysis has been based on a survey conducted by the International Energy Agency (EIA). IEA conducts surveys of generation cost from time to time. The most updated report is 118 from 1998 and is based on data from 1996. The survey provides a picture of construction cost directly and indirectly, O&M cost and fuel cost. All costs are in USD. To compensate for price increases from 1996 to 2000, 10% has been added. The investment costs include base construction cost, contingency, interest during construction and major refurbishment, if predicted. . The investment cost of 1 kW of coal-fired generation capacity varies between the most costly countries Japan 2800 USD and Portugal 2200 USD to the lower end with costs of about half. The table below shows data for the cheapest segment of the surveyed countries. 1000 USD per MWe price level 2000 = 1996 +10% Finland Canada USA Turkey India without desulphurisation China Base construction cost including contingency 1022 967 1192 1152 1059 1043 Interest during construction Total costs 60 103 113 98 43 140 1082 1070 1305 1250 1102 1183 In view of the above it is found that a likely level of investment cost for a new coalfired power plant in South Africa would be in the range between 800 USD/kW (5520 ZAR/kW) and 1200 USD/kW (8280 ZAR/kW). This depends on whether installation of desulphurisation and NOx reduction equipment is included. The global tendency is moving towards cleaner technologies. It is hence likely that in the future desulphurisation and NOx reduction equipment will be installed in new power plants in South Africa. The cost of these facilities should hence be included in the LRMC. The 800 USD in investment cost result in an average capital cost per kWh of 8.6 ZARcents and for 1200 USD of 12.9 ZARcents per kWh. The assumptions are a nominal rate of interest of 16% and depreciation over 25 years. Production per kWe capacity is 6000 kWh per year. For a new plant the production may be higher, approx. 7000 kWh per year (baseload). However, during the service life of a power plant, it is usually de-rated from base-load to medium-load and finally to peak-load. The assumption of 6000 kWh/year is the average production during the entire service life. 119 Fuel costs South Africa has most likely the lowest fuel cost in the world. The abundance of coal combined with easy access contributes to this. Eskom utilises cheap secondary quality of coal. First quality is exported at much higher prices. The 1999 average cost of coal consumed by Eskom was 42.8 ZAR per ton. Each ton has an energy value of 20.09 GJ9. With an average overall thermal efficiency of 34.4%, this makes a fuel cost of 2.23 ZARcents per kWh electricity. This is far below many other countries. The country in the IEA survey with the lowest fuel cost is USA. It has a fuel cost of 0.9 UScents per kWh = 6.2 ZARcents per kWh. Canada and Finland have 1.5 UScents = 10.3 ZARcents. South African coal is gradually becoming scarcer, and increasing environmental costs are likely to be imposed on the mining and handling of coal. For these reasons the present study assumes that the LRMC of coal is 15% higher than the present cost, i.e. 2.6 ZARcents per kWh electricity. O&M cost The IEA survey shows that great variation exists with regards to O&M costs. In table 6.2 below the figures for some of the countries are shown. The figures have been converted to year 2000 and ZAR for easy comparison. Table 6.2. O&M cost per kWh in ZAR cent O & M costs in ZAR cents per kWh Canada 3.1 c Denmark 5.1 c Turkey 6.8 c US 3.8 c Brazil 2.5 c Source IEA: Projected cost of generation of electricity, 1998 table 15. Amounts converted to year 2000 by adding 10% and converted to ZAR on the basis of an exchange rate of 1 USD= 6.9 ZAR On the basis of the above table and assuming that South Africa is likely to be in the cheaper segment, a figure of 2.8 cents per kWh, which is the average of the two cheapest countries in the survey, is found reasonable for South Africa. Total generation costs On the basis of the figures presented above the direct generation costs can be estimated. The component and cost picture is showed in table 6.3 below. 9 Eskom Annual Report, 1999. 120 Table 6.3 Total direct generation cost in ZARcents per kWh LMRC of coal-fired electricity generation in South Africa Capital cost O&M Fuel Total cost Without desulphurisation and NOx equipment 8.6 2.8 2.6 14.0 With desulphurisation and NOx reduction equipment 12.9 3.8 2.6 19.3 The cost of the nuclear reactors proposed for the Western Cape are in the region of US$ 0.0243 to 0.0427 per kWh corresponding to 17 - 29 ZARcents (Eskom and MIT estimates presented in the World Energy Assessment, 1999). According to the latest annual report from Eskom (1999), Eskom’s financial performance in 1999 was as follows: A. Total external sales B. External revenue C. Internal revenue D. Total Revenue E. Operating expenditures F. Interest income G. Interest expenditure H. Net profit I. Average total cost of electricity based on external sales; (B – H) / A 173113 GWh 21523 Rm 43 Rm 21568 Rm - 17027 Rm 1261 Rm - 3634 Rm 2168 Rm 0.112 c/kWh According to the 1998 Electricity Supply Statistics of NER Eskom’s average total costs of 11 cents/kWh can be accounted for as follows: 7 cents for generation, 1 cent for transmission and 4 cents for distribution. It has already been explained why the LRMC is higher than the present costs. Indeed, it would be quite questionable were it not higher than present costs. The short run marginal cost (SRMC) is quite different, as it only covers fuel cost and O&M costs. With fuel costs at 2.5 cents and O&M of 2.8 cents, a total of 5-6 cents seems likely as SRMC. However, due to the nature of Eskom’s long-term coal contracts with collieries (owned by private mining companies), the SRMC of the coal is about 20% of the average cost of coal, resulting in an even lower SRMC. Eskom pays on a cost plus profit basis for coal hence Eskom’s price is similar to an 80% fixed (take or pay) and a 20% variable cost. The profit element is low as Eskom made capital for colliery development available when building the power station. As peaking capacity Eskom has about 1400 MW pumped storage plant in service. With a cycle efficiency of 70%, the SRMC cost of peaking power is 1.4 times the SRMC of coal fired generation. 121 In a period with considerable excess generating capacity it can be argued that the real cost of electricity is equal to the SRMC, as there is no immediate need to invest in new capacity. Transmission costs and losses From international experience it is assumed that servicing the loans and the operation and maintenance of the transmission system amounts to 1 ZARcents/kWh. According to Eskom’s Annual Report 1999 the energy balance in 1999 was as follows: Total input to transmission: 184968 GWh Total sold: 173423 GWh Losses: 11545 GWh The total energy losses therefore amount to 6.2%. It is assumed that the energy losses from the transmission system itself (defined as all grid components above 132 kV) are 3 %, corresponding to 0.5 ZARcents/kWh. From the above considerations it is assumed that the total transmission costs (capital costs, O&M and losses) amount to approximately 1.5 ZARcents/kWh. The remaining losses are the losses from the distribution systems (defined as all grid components below 132 kV) plus some theft, i.e. 6% - 3% = 3%. According to the 1998 Electricity Supply Statistics of the NER Eskom’s total average costs for distribution are 4 cents/kWh (without losses). This cost is high due to the low energy usage of newly electrified customers. At present Eskom connects 300,000 new domestic customers per year (1000 per day). Other costs Previously Eskom has not paid corporate tax and dividends. In the future Eskom will be corporatised and will then pay tax and dividends. Municipal generators will still not pay tax or dividends. An electrification levy is presently been prepared, probably around 1 cent/kWh. The electrification cost of about 1 c/kWh is presently contained in the 4 c/kWh distribution cost. When the levy is to be paid, electrification will be funded from the levy. Hence it is not intended to be an extra cost, but will make the cost of electrification transparent 6.3.2. Electricity tariffs It has been Eskom’s practice to develop a price that earns an inflation-adjusted return of about 3.5 % on assets used. This has been considered sufficient to finance replacement (after 35 years). 122 Eskom currently applies a cost differential of 1 to 3 % depending on the distance from the centre of power generation when in fact the costs differ much more (NER, May 2000). The proposed WEPS gives figures for transmission network related charges. These include an annual charge for transmission capacity and an energy loss rate to account for real electrical energy losses. The proposed transmission capacity charge could have significant implication for independent power producers. In the areas far removed from the main coal-based electricity generation areas of the country, the proposed capacity charge (R/KW p.a.) are negative. This implies that a generator may be paid a rate per installed kW per annum. This arises because the generator in question is beneficial to the transmission system by reducing the requirement for investment in transmission capacity (NER, May 2000). The capacity charge provides long term siting signals to transmission customers. The highest proposed negative capacity charge is for the Port Rex power station of –R79.36 per kW per annum. For a 1 MW generator producing 3 GWh of electricity per year this would effectively represent a reduction of 2.6 c/kWh on the price required for viability. There is no tariff policy for IPPs and none is being planned. The new Regional Electricity Distributors (REDs) will likely operate with 3 different licenses: Network licenses Retail licenses, captured customers Retail licenses, residential customers The present tariff for a municipal distribution company far from the centre of generation (e.g. Darling, Western Cape) is 18-19 c/kWh. 6.3.3. Subsidies and cross-subsidies In many countries elements of cross-subsidisation exist. To supply more remote areas is often more costly than is reflected in the selling price. An often quoted Eskom statement is that the average true cost of supply to low consumption consumers (50250 kWh/year) is about 75 cents/kWh, much higher than the average charge of 26 cents/kWh. Eskom is not allowed to sell energy below the short run marginal cost, as it would not be in the interest of the general body of South African electricity consumers. Commodity linked pricing deals could however temporarily under recover the full marginal cost during low cycles. The degree of under and over recovery is monitored. Nuclear energy in South Africa is being subsidised. According to the Clive van Horen report from 1996 (“Counting the social costs”), the nuclear energy received a fiscal subsidy of about 8 cents per kWh of electricity generated by the Koeberg power plant. The PBMR research has been ongoing since 1993. The research costs have largely been borne by Eskom internally (the IDC holds a 25 % equity share in the project). British Nuclear Fuel (BNFL) has also recently taken a share in the project. S. Daly and F. Moti estimate that the research expenditure to date on this project has been of 123 the order of R120 million (Business report, 12 April 2000, “Eskom gets the nod for Pebble Bed”). Estimates for this figure go as high as R350 million with a further R150million having been budgeted over the next few years. It is interesting to note that the PBMR project is no longer included as a strategic research project but is considered to have entered the implementation phase of the project. The fiscal subsidy to the Nuclear Energy Corporation of South Africa (NECSA) now represents 44% of the budget of the DME. This amounted to R12million in 1999. 1% of the DME budget goes to the council for nuclear safety. By contrast, the subsidy from the fiscus to the MLIS program of the former AEC amounted to R40 million between 1995 and 1998. NECSA is still involved in the PBMR only in research into the fuel fabrication process. 6.4. Externalities For non-utility electricity generation the ”White Paper on Energy Policy for the Republic of South Africa” (1998) stated (page 42) that the tariffs shall be approved “on the basis of full avoided costs”. “By including environmental costs into the pricing structure for further development of renewable and environmentally benign generation technologies such as hydro, wind, solar thermal, and waste incineration will also be encouraged”. Possible social and environmental benefits from distributed energy may be internalised in the economy of the power sector. This is either done through an energy tax on the less wanted fuels and fuel cycles or through power purchase agreements favouring more desirable fuel cycles - or it may be recompensed through tax funded subsidy schemes of various kinds. Which type of internalisation preferred is first of all a political issue. Some major concerns would be: market perfection: in order to make the market respond to the policies outlined the power prices should reflect the “true” costs including external costs, or the distributed generators should be proposed conditions to compensate for the relative benefits. distribution of the costs within the society. If all costs were internalised in electricity prices the financial burden would be distributed according to the distribution of power consumption. This would affect first of all energy intensive industries and thereby their competitiveness could be adversely affected if no complementary actions be taken. long run market response to the pricing signals: One of the advantages of internalising externalities through connection and buy back conditions might be that they have no direct impact on the state finances as is the case for tax rebate and subsidy schemes. Therefore, buy back rates could be less sensitive to the changes in political priorities although even tariffs are not insensitive to political changes or changes in the power development plans as has been seen in for example USA. 124 6.4.1. Direct accountable externalities Hohmeyer of Germany conducted a major study of the externalities in 1988. The result was that the externalities were almost of the same magnitude as the generation cost of electricity. Van Horen published a comprehensive survey of the impacts from coal mining in South Africa in 199610. The externalities covered: Injury and deaths in connection with mining the coal Health risks from coal dust Emission of sulphur and NOx Impact on other aspects of human body and productive activities The sulphur is contaminating the fields and hence results in reduced agricultural yield Pollution of water from mining activities The fatality rate has been estimated at 0.31 persons per million tons mined and the number of injured at 1.68 injured for one million tons. The electricity sector is a major consumer of water. The present price paid for water by the sector does not reflect the actual cost, and in particular not the long run marginal cost. Water is a scarce resource in South Africa. The aspect of low level pollution in townships due to poor quality coal being used for cooking and heating should also be included in an externality evaluation. This is particularly a problem in winter months (houses poorly insulated due to short but severe winters). The official ‘wisdom’ is to keep electricity costs affordable to those communities and burning the coal in power stations, but this has still not resulted in a switch from coal to electric heating and cooking. Different schools exist with regard how to handle the issue of externalities. It could either be made on the basis of a damage function, or the basis of the surrounding people’s willingness to pay for avoiding the damages or nuisance. The gap between theory and how people perceive the risk and benefits often complicates the method of willingness to pay. Such measures will add to the cost of coal-based power generation. Of the above-mentioned externalities the following could be included (all amounts in ZARcents): Cost of desulphurisation and NOx reduction Cost of death and injured Lost production costs Water Health, morbidity and mortality from emissions Total 10 5-6 cents per kWh 0.02 cent 0.001 cent 0.13 cent 0.543 cents 5-6 cents per kWh Clive van Horen: Counting the social costs. Electricity and externalities in South Africa, 1996 125 6.4.2. Indirect and global externalities The global perspective - CO2. As a part of the Koyoto protocol several countries have agreed to limit CO2 emissions. South Africa has also signed the protocol. In order to demonstrate the willingness to reduce CO2 emissions several countries have put a levy on CO2. In Denmark it is about 25 USD per ton while a more international figure is approximately 10 USD per ton. Such a levy has two effects: First it contributes to create an awareness of global problems with CO2 emissions, and secondly, it improves the economic framework for energy sources, which do not produce CO2, like hydro power and wind turbines. Generation of 1 kWh produces approximately 1 kg of CO2. With a levy of levy of 10 USD per ton it corresponds to 1 UScents per kWh or 7 ZARcents (cf. paragraph 2.4). A more recent study for the WWF (1999) reports on “Macro economic reforms and sustainable development in Southern Africa”. Report No. 5, “Electricity production”, summarises the external costs of electricity generation as in the table below. The methodology followed was to assess the damage costs of externalities together with the associated impact pathway. The impact pathway relates changes in environmental quality to the direct emission or resource impact. This study also included the positive externalities of electrification. The strategy followed here was to relate external costs to household fuel use and then determine the impact of electrification on the change in those fuel use patterns. Subsidies to the nuclear industry were not included in the WWF study subject to further discussion with government and analysts regarding the allocation of the current subsidy to NECSA (Nuclear Energy Council of South Africa formerly the Atomic Energy Corporation). The subsidy to the nuclear industry has been reduced from the order of 70% of the DME budget in the 80s to 45% of the current minerals and energy budget. Eskom’s research on the PBMRs is funded internally. 126 Activity Estimated externality (c/kWh) Low Medium High Coal fuel cycle excluding GHGs 0.70 0.98 1.24 Coal GHG damage estimate 2.53 11.06 16.58 Total Coal fuel cycle 3.23 12.04 17.82 Nuclear: fiscal subsidy 4.74 5.01 16.14 Weighted average external cost (Van Horen) 3.28 11.59 17.72 WWF study coal without electrification 0.55 0.80 0.93 Electrification benefit -0.02 -0.13 -0.31 Climate change estimate 1.32 4.00 9.35 Total WWF Coal externality 1.88 4.67 10.02 Sources: WWF (1999) “Macro economic reforms and sustainable development in Southern Africa”, Table 2.11, and Van Horen (1996) table 5.10. All values in 2000 c/kWh converted from 1997 and 1994 values respectively using annual CPI increases. 6.4.3. Total production costs of coal based energy In the paragraph above is described and quantified the costs of externalities related to electricity generation in coal-fired plants. It is evident that an environmentally friendly policy would incorporate this cost and not only aim at reaching the lowest production costs. It appears from the above that many of the negative health impact have no significant impact on the production costs. Even if the cost being adjusted upwards with inflation and higher income. Whereas the impact and cost of mitigating the sulphurisation might add a considerable amounts to the existing generation costs. On top of that the issue of global warming from CO2 emissions could be given attention. A further 7 cents levy is of a considerable size compared to the present production costs. 6.4.4. Total production costs without subsidies and with externalities. The previous paragraph has described and quantified the direct generation costs, the externalities on the local environment and the global externalities. By not making the polluter responsible, the society is indirectly supporting the low cost of electricity by giving a hidden subsidy. This is parallel to a real subsidy and should be viewed in the same way. To cover the cost of externalities it requires a levy on electricity of about 5-6 cents to cover for the direct local externalities, while a responsibility towards the global 127 problem would add additional 7 cents on top of that. Resulting in an electricity LRMC of about 26 cents per kWh in a global perspective and 19 cents in a local perspective. 6.5. Real costs of REIPPs Below follows a cost comparison of different kinds of electricity generation. The figures are based on production costs of minor entities in an attempt to reflect the cost of an IPP. The evaluation has been made on common grounds with regard to financing etc. The analysis has set the tariffs in Rand per kWh as the parameters to minimum tariffs for achieving Financial Rate of Return on equity of 12%. The common assumptions for a fair evaluation are: Economic analysis covers a 20 years period Debt financing of 70% of the investment 30% funded as equity Interests rate of 16% ( see below) Payback period of loan of 15 years Inflation in South Africa = 6-7% p.a. declining to 5½-6% Tariffs to be adjusted by 5% p.a. of the average consumer tariff paid Exemption from corporate taxes during the first 12 years Main output parameters are: Tariff to be paid to achieve a Rate on return on equity of 12%. Financial Internal Rate of Return FIRR (overall) Return on equity There are signs that the macro economic situation in South Africa is about to improve. Important parameters such as growth has increased from about 1% per year to over 3% and inflation is declining from a level of 6½-to 7% per year to 5- 5½%. There are indications that the devaluation of the Rand will be much less than during the last years. There are signs that the high interest rates are going to be reduced11. 6.5.1. Mini hydro systems Several options for small hydro power stations exist. Installation of small hydro plant can in many cases supply the local community at a low cost. It is important that rivers have a year-round flow of water. Some rivers have even a good downward slope so construction of dams can be avoided. 11 Economist Intelligent Unit ( EIU) Country Report, June 2000 128 The present study has investigated the Bethlehem project where small hydro-turbines of a total capacity of 9.81 MW are going to be installed. See Chapter 5 for further details. Project: Bethlehem Capacity Investment cost per kW Initial investment Energy produced per year O&M costs per year Tariff Overall FIRR 9.81 MW 6630 ZAR 65 million ZAR 60155 MWh 600,000 ZAR 0.16 ZAR/kWh 15.9% Conclusion: It appears as an environmentally friendly solution at low cost. 6.5.2. Industrial bagasse The consultant has selected information from similar projects in Thailand. There are also projects in South Africa, but one of the major ones are supplying Durban Metro with electricity and for business reasons has decided not to disclose information. Information and data from Thailand: Capacity 39 MW Investment cost per kW 6900 ZAR Initial investment 269 million ZAR Electricity efficiency 27% Fraction of fuel converted to 41.7% process steam Electricity produced per year 140400 MWh Average load factor 41% O&M costs 5% of investment per year Fuel costs 28 ZAR/ton = 3.5 ZAR/GJ Required electricity tariff 0.36 ZAR/kWh Overall FIRR 13.7% The reference for the above calculation is a new bagasse-fired boiler, generating the same amount of process steam. Investment cost 690 ZAR per kW(th), thermal efficiency 75%, and O&M equal to 5% of investment cost per year. It should be noted that the estimated cost of bagasse (the avoided disposal cost) probably is too high. It is based on experiences from Thailand. For South Africa the cost of 3.5 ZAR/GJ should be compared with the cost of coal. In 1999 Eskom was paying an average price of 2.1 ZAR/GJ, so it may be cheaper for a sugar industry to use coal rather than bagasse as fuel. 129 For South Africa, the maximum cost of generation for the bagasse generator in Maidstone (cf. paragraph 5.2.1.4) can be deduced by considering the Megaflex tariff structure (shown in the table below) applicable to the distributor purchasing the electricity. Peak Standard Off-Peak High demand tariff (c/kWh) (April - September) 25.16 14.12 8.09 Low demand (c/kWh) (October - March) 19.87 11.11 6.39 The 1999 sales data (in the table below) by the bagasse generator are used and it is assumed that the sale and production of electricity is evenly distributed over the 8 month harvest season from April to the end of November. Then the weighted average upper limit to the cost (assuming that the generation plant runs at a profit) for viable production and sale is 12.44 c/kWh. The electricity is, in fact, purchased at a price slightly below the Megaflex tariff. It should be emphasised that this figure is largely an artefact of the development of the sugar mill and the surrounding village some 40 years ago. Furthermore, there is effectively no fuel cost. A better reflection of LRMC could be obtained by using the international capex and technical figures and local fuel costs. This generator will start operating in cogeneration mode in 2000. The given price details, which represent the previous island (non-grid connected) mode of generation, will still be applicable. Electricity category (Time of Use) Electricity purchased kWh Peak Energy Standard Energy Off-Peak Energy Total Energy 2 445 360 5 945 420 7 003 460 15 394 240 A key issue for biomass cogeneration is risk minimisation, in particular fuel supply related risk. Fuel supply is affected by seasonal conditions (this is particular the case for bagasse), by structural changes and global trends affecting the agro- and forest industries. Based on information on existing and potential crops in the region, the probabilities of possible incidents shall be thoroughly assessed. 6.5.3. Wind power The Darling Demonstration Wind Farm project is described in Chapter 5. Other parties have carried out the financial evaluation of the Darling wind farm: The private consultant, Hugh Ashby, elaborated a financial evaluation in January 1999. Eskom published a report on the issue: L.Y. Kok: Darling demonstration wind farm proposal. Presentation to Eskom management board. June 1999. These two evaluations only differ on minor details. The figures below are quoted from the Eskom report: 130 Capacity Investment cost per kW Initial investment Energy produced per year Load factor O&M costs 1.5 % Tariff Overall FIRR 5 MW 5300 ZAR 26. million ZAR 13500 MWh 30% 395,000 ZAR 0.33 ZAR/kWh 17.0% The calculated generation cost of 0.33 ZAR/kWh appears high compared with international experiences, cf. the figure below: 1.20 ZAR/kWh 1.00 0.80 0.60 0.40 0.20 0.00 1980 1985 1990 1995 2000 Estimated real costs of wind generated electricity. Based on 20 years depreciation, 5% interest rate and siting in roughness class 1 (average wind speed 4.4 metres/sec at 10 metre height). Price level: 1999 (exchange rate 1 ZAR = 1.20 DKK). Reference: “Wind Power in Denmark”, Danish Energy Agency, 1999. One reason for the higher cost of wind generated electricity in South Africa than in Denmark is the higher interest rate. For illustration, if the real interest is lowered from the 8.4 % per year, as used in the present report, to the 5 % per year, which was used for Danish figures shown in the table, the cost of generating electricity would decrease by almost 5 Randcents per kWh. There are two explanations for the rapid decrease in generation costs shown in the figure above: 1) Technology development of a fairly young technology, and 2) increasing turbine capacities. Both developments are illustrated on the next figure: 131 ZAR/kWh/year 2.50 2.25 225 kW 500 kW 600 kW 2.00 1.75 1990 '750 kW 1992 1994 1996 1998 2000 Development of specific investment costs defined as ex-works turbine price divided by annual generation in roughness class 1 (average wind speed 4.4 metres/sec at 10 metre height). Price level: 1999 (exchange rate 1 ZAR = 1.20 DKK). Reference: “Wind Power in Denmark”, Danish Energy Agency, 1999. Please note that the figure does not contain information on windmills larger than 750 kW. The latest generation of wind farms that has been commissioned in Denmark is using 2 MW turbines. 6.6. Comparison of costs The financial evaluations of the previous sections (6.3 and 6.5) are compared in the figure below: 132 Generation costs in ZARcents/kWh 40.0 30.0 20.0 10.0 Capital cost O&M Fuel Environ CO2 Total costs h N uc l ea rH ig rL ow ea N uc l Ba ga s se d W in H C oa l yd ro 0.0 Losses Total generation costs of various technologies. For each technology the column shows the total costs to the right. For some, the cost components are shown to the left. 6.7. Power purchase regulation for distributed generators Since the late 1970’es a large range of countries around the world have developed specific regulation regarding interconnection and pricing of power from small and distributed generators. The main purpose has been to promote independent and distributed generators by determining rates and conditions related to connection and power exchange by protecting the interests of distributed generators as the weaker part in the business of selling power to a monopoly. 133 Most regulations for power purchase from distributed generators explicitly refer to the principle of avoided costs as the basis for rate setting. This principle states that the rates provided by the power utility should reflect all the costs and benefits which the power utility observes when purchasing power from a distributed generator. However, a consistent application of the avoided costs principle is very complicated and requires a large amount of information about the generation, transmission distribution and consumption characteristics of the entire power utility. Some concerns of major importance to the resulting rates are: is the capacity value of distributed generators evaluated on an individual level, or is any account taken to the collective guaranteed capacity they might provide, even if they are individually less reliable? are the local benefits of the generators in terms of avoided energy losses and saved transmission and distribution costs taken into account? While new efficient renewable energy technologies are seen as promising future alternatives to conventional power generation, they have not been - and still mostly are not - competitive in an unregulated market. Consequently policies have been set to secure fair prices of electricity generated and to support the technologies through various kinds of government financial support. When it comes to the determination of fair prices, it has almost invariably been the case that conflicts have arisen between power utilities on the one hand and distributed power producers on the other, with the government agencies somewhere in between. The distributed generators on their side claim that the power they provide represents a value in terms of avoided costs to the power system, which they should be accounted for. First of all the power replaces power otherwise being produced at a centrally dispatched plant thereby reducing the fuel costs and operation and maintenance costs of this plant. Secondly, the distributed generator provides capacity to the system that reduces the need for future investment in power production and transmission capacity. The power utilities on their side tend to look upon distributed generators as a very uncertain business for a variety of reasons. It fundamentally competes with them in what many still wish or perceive as their domain. Often their objections take the form of technical arguments such as: the impacts on the local electricity grid are less predictable, which incurs a risk of excessive costs in power quality equipment unlike conventional power generation the reliability of the technologies is far less well known to the power utilities the future availability of the generators depends on a variety of factors like the financial viability of the owner, the prospects of the industrial business (in case of industrial co-generation), future availability of the fuels used etc. factors which are unfamiliar to the power utilities. Taken these risks into consideration most power utilities value the power output far less than the producers using a normal avoided costs calculation. In fact, many utilities would prefer not to depend on distributed power generation at all. 134 The impacts of distributed generators connected to the electricity system. Avoided energy costs Whenever a distributed generator produces power to the grid this power would replace electricity production at a centrally dispatched power plant and thus lead to reduced energy and operation/maintenance costs (normally referred to as energy costs) at that site. Avoided generation capacity costs In a situation when the power demand is growing or when the reserve capacity is not sufficient - or even when outdated power production capacity must be replaced by new capacity - a distributed generator may offset a need for investment in new production capacity. The calculation of the possible fraction of marginal capacity costs being avoided from a distributed generator is probably the most difficult and questionable process of establishing a coherent and consistent pricing system. The discount widely depends not only on a variety of parameters regarding the delivery of power but also on the context in which the distributed generator is being seen. Starting with the latter, traditionally a distributed generator is being seen as one single individual generator relative to the dispatched power system. From that viewpoint any lack of guaranteed delivery of power would result in the requirement for back up capacity, and the capacity value of the generator would be reduced accordingly. But to a certain extent it could be fair to regard distributed generators not as individual generators but as a total of generators providing more or less back up for each other. This might be the case for the diurnal and annual variations in output from each generator as well as for the long run commissioning and de-commissioning of distributed generators. Capacity provided beyond the guaranteed capacity may have some value due to the reduced loss of load probability, but the value would in general be much less than that of the guaranteed capacity. As an example simulations of the Dutch power system has shown that wind turbines represent a total value of 14-16% of installed capacity although they have no guaranteed availability at any particular moment. In a situation when power demand increases beyond the forecasts distributed generators may provide a short run value because of the shorter lead-time (period from contract signing to plant commissioning) by which it may alleviate any shortterm lack of capacity. When a group of distributed generators are considered as one generation unit the avoided costs evaluation may come out very different both when it comes to long run guaranteed capacity delivery and when it comes to guaranteed diurnal and annual capacity provision. The US Power Utility Regulatory Policies Act (PURPA) passed in 1978 is among the first government regulations establishing detailed rules for connection and power 135 delivery from distributed generators to a power utility. This regulation has been trend setting for similar regulations in many other countries. PURPA has some interesting features, when it comes to grouping of distributed generators: Avoided capacity costs should take into account the individual and aggregate availability of the qualified facility. This implies for small facilities less than 100 kW that if they can provide evidence that on an aggregate level an effective amount of capacity is provided even if the output of each individual generator is stochastic, they should be recovered accordingly. Generators larger than 100 kW are allowed to enter into operating agreements by which they may be able to increase the assured availability of capacity to the utility by co-ordinating scheduled maintenance and providing mutual back-up service. Connection costs There is an immediate capital cost of the between the generation plant and the electricity system as it existed prior to the connection of the plant. This includes among others meter, security system and power line. Fault level The distributed generator could affect the level of power supply faults in the local area due to fluctuations in power quality. This might incur extra investment costs in control equipment like power breakers in the local system. These costs could also be accounted for as part of the connection costs calculation. System reinforcement The distributed generator will affect the upstream load of the system. This could impose a cost as well as avoided costs to the distribution system - and in principle also to the transmission system. Use-of-system-costs If distributed power is being transmitted through the electricity transmission system to be sold directly to a remote consumer (wheeling) rather than to the power utility it is most often seen that a use-of-system charge is being imposed. Energy losses The new generator will change the flow of electricity in the grid thereby affecting the energy losses. In case the generator is situated closely to the demand absorbing the generated power energy losses would be reduced. On the other hand, if a large generator is situated at a remote location the distance to the corresponding demand could be long and increased losses could be the result. Distribution and/or transmission constraints If the generator is situated in a zone with a much higher power demand than generation capacity and with limited transmission capacity (import constraint) this zone might face constraints in purchasing the electricity at the lowest price due to the transmission constraints. In this case, the increased local capacity resulting from the new generator would reduce the constraint. 136 On the other hand, when the generator is situated in a zone with much excess generation capacity and limited transmission capacity (import constraint) the new generator would increase the electricity export constraint. 6.8. Employment aspects The issue of employment is found important in many countries. Although no calculations have been made specific to South Africa, the following table summarises studies done elsewhere and shows the potential job creation benefits of a renewable energy strategy, when compared to either coal or nuclear power stations. Information Source Resource Coal fired power plant Photovoltaics Solar thermal electricity Wind-generated electricity Biomass-derived electricity Hydro-derived electricity Danish Studya New York Stateb AWEAc World Watch Instituted [man-years, same amount of energy] [jobs per mil. US$ invest.] [jobs per mil. US$ invest.] [jobs per TWh] 6,200 13.1 7.4 13 116 14,200 10.0 14 248 542 17.0-22.6 4.0 8 a Source: l. Munksgaard, J Rahbæk Pedersen. T. Jensen Societal benefits of wind turbines, part 3 Employment and balance of payment. (in Danish, AKF 1995) b Source: 1994 New York State Energy Plan, Volume III: Supply Assessments, Table 57, p. 612. c Source: American Wind Energy Association (AWEA) (1995) d Source: Scheer (1993), p. 110. The Danish comparison has been conducted on a macro economic model for Denmark. The model includes the induced effects on investment and employment of sub-suppliers. The comparison has been made on capacity to supply the same quantity of energy (MWh). A comparison was made between a 420 MW coal–fired power plant and 1000 MW of wind turbines with a gas fired power plant of 220 MW for back up. The result showed that for the wind-turbines project the number of man-years was 14200 and for the coal fired 6200 man-years. The number of employed people in the wind project is about 12,000 man-years during construction while the subsequent maintenance only requires 110 man per year. For the coal fired power plant the corresponding figures are 4100 during construction and 105 man per year during the subsequently maintenance. The figures reflect the northern European production methods with limited labour input. For South Africa the employment figures might be the double. The employment corresponds to about 13 man-years for each MW installed for wind turbines and 6 for coal-fired plants. In countries with more labour employed in production than in northern Europe both figures will be higher. The assumption for the above employment analysis should be made clear. In Denmark the import content of investment in both wind-turbines and coal plant is 137 35%. While operating costs of coal plant requires import of coal. The South African situation is quite different, with wind person years perhaps being reduced (as more of the technology would be imported). On the other hand coal person years would increase significantly because the coal is mined locally. As rule of thumb the investment cost distribution for a wind farm is as follows: Complete wind turbine excluding the tower Towers Site preparation, foundation, road works, grid connection 45-50 % 15-20% 35% This implies that, if the tower is imported, 35% of the investment will be delivered from SA sources. If the tower were manufactured in SA, the local content would be 50-55%. If more than 80-100 MW of wind turbines will be installed per year, it may be feasible to produce otherwise imported parts in SA, e.g. blades, gear, generator, auxiliary equipment, under license agreements with the various suppliers of the equipment. It may thus be possible to gradually increase the local content to well above the 50-55%. The option for further employment therefore requires a policy of expanding the wind energy sector. In this connection, it is worthwhile to mention that potential SA manufacturers of wind turbine parts would have a larger potential market than SA itself, probably the entire region of Southern Africa. 138 7. REVIEW OF INTERNATIONAL RENEWABLE ENERGY POLICIES 7.1. Introduction Where renewable energy use has thrived around the world, favourable energy policies have in part been responsible for this growth. These policies make investments in renewable energy capacity attractive to power producers through either subsidies or requirements for renewable energy power generation. The justification for introducing policies favouring renewable energy (RE) can be defined at two levels. First of all, an equal level playing field has to be established. Secondly, RE may be given a special status, including more incentives than other energy sources. This chapter describes the main incentives that have been tried, followed by more detailed information from selected countries. 7.2. Incentives It is not only important that renewable energy use be increased, but also that this growth is sustainable. Large subsidies can foster tremendous use of renewable energy, but since most subsidies are not sustainable, it is important for the technologies to become cost-competitive for sustainable and commercial markets to be developed. If the goal is to maximise renewable energy generation, then a fixed incentive or setaside should apply to all technologies. This minimises the incentive payments for maximum use of renewable energy, and it allows for future cost reduction of technologies which are currently too expensive to be deployed. This would encourage biomass power, but solar PV, solar thermal electric or wind would not be deployed until cost-competitiveness was reached through decreasing technology costs or discovery of excellent resources. Because this goal is not technology-specific, it allows for a new renewable energy technology to come on board and does not force the use of expensive technologies or inadequate resources. If the goal instead is to deploy and begin commercialisation of certain technologies, then individual incentives or set-asides can be set for each technology. As an example, small incentives could be used to promote biomass power, with much larger incentives for more costly yet still promising technologies such as PV. This is a more costly and comprehensive program and this should be carefully assessed, because the amount of funding needed to make PV cost-effective for utilities is quite high on a per MW basis in comparison to biomass. One incentive (likely to be a financial incentive) will likely be the primary driver for renewable energy development. Supporting incentives will be needed to fill the remaining gaps in overcoming barriers the development of renewables. For instance a primary incentive which focuses on overcoming the cost-effectiveness barrier may still need financing mechanisms to overcome the high capital investment barrier. 139 There are many methods for governments to promote renewable energy. A summary is presented in the table below. Tool Production incentives Advantages Easy to implement, Easy for developers, Encourages renewable energy production. Disadvantages Does not directly address high first cost barrier. Can be abused if incentive too high. Investment incentives Overcomes high first cost barrier Encourages investment, not production Renewable Set-Asides Allows control over amount of renewable capacity added, Competitive bidding encourages cost reductions Power Purchase Agreements Long-term, standard agreements help developers and facilitate investment Environmental Taxation Correct energy prices including costs of environmental impacts provides a more level playing field for renewables Can be very bureaucratic. Bids may be controlled by one entity. May lead to lumpiness in installations. Difficult to achieve when the electricity supply industry is in the process of restructuring Taxes are often politically unfavourable Externality Adders Allows for full-cost Implementation does not accounting in power planning always follow planning Research, Development and Demonstration Builds long-term foundation for technological and industrial development Government Assisted Business Development Builds market infrastructure Green Marketing Allows choice in power purchases Difficult to pick a technological winner to invest RD&D in May be under-subscribed Of these, the methods that have been most successful in promoting renewable energy development are investment incentives, production incentives, and set-asides. Some options, such as environmental taxation, RD&D and green marketing, have been helpful, but have not had the same impact. Other options, such as establishment of standard power purchase agreements, may be a necessary condition for renewable energy promotion, but they may not be sufficient. 140 7.2.1. Production Incentives A production incentive provides a financial incentive for the generation of electricity from renewable energy. In the case of the US, the production incentive replaced the investment incentive because of abuses with investment subsidies. Investment subsidies encourage the installation of renewable energy capacity. But if the power plants are sited in areas where resource is not good, if proper O&M is not carried out, or if bad designs are installed, then the result could be a large amount of installed capacity but little electricity generated. The production incentive is a tried-and-true mechanism for promotion. Some of the problems with this approach include the disincentive for cost-competitiveness, as seen in Germany’s wind power incentive, which gives a fixed high buyback rate. These very high subsidies do not encourage developers or manufacturers to reduce costs. One way to finesse this is to design a diminishing incentive over time. Another way to limit excessive profits is to give an incremental subsidy over conventional energy costs, such as was done in the US in the 1990’s when $0.015/kWh was paid to renewable energy power producers. In a South African case study (the Darling Wind Farm), this incremental subsidy would be of the order of 16c/kWh (= 35-19) to encourage investment. If a production incentive is used, it is recommended that: 1. The level of a production incentive be carefully designed to encourage costcompetitiveness and efficiency in power production. This could be a function of technology, location and time of generation. The electricity regulator would have to set this in a way that encourages least economic cost electricity generation. The full avoided economic cost of generation would be the ideal level be for this production incentive. As a starting point or in the absence of quantified external costs, purchase by the generator of negative units at the wholesale electricity price could be considered. The purchase of negative units at the applicable wholesale tariff would effectively mean sale by the generator of the units at the same price as the wholesale tariff (including whatever time of use or other structure the tariff might have). There would be no premium to the RE generator per unit nor any profit to the distributor reselling the units. In this way there is no difference between the price paid to the generator and the price at which the distributor sells the electricity. The distributor would have to be obligated or given some other incentive (like green pricing) to buy this energy. 2. The program be periodically monitored and evaluated to readjust the incentive level in order to encourage renewable energy generation and discourage abuse of the incentive; 3. The incentive rules and regulations are clearly stated so that developers and investors can easily develop projects and acquire financing. The production incentive also does not necessarily offset the large capital investments and correspondingly high initial risks of renewable energy development. In order to deal with these problems, supporting incentive measures, such as long-term, standard power purchase agreements and special financing mechanisms may be necessary. These are discussed in the next section. 141 7.2.2. Investments subsidies Investment subsidies and tax credits have proven to be easily abused and have been replaced with other types of incentives in some countries. Therefore investment subsidies generally should not be used as a primary driver for renewable energy development. Investment subsidies are notable for overcoming one of the main barriers of renewable energy: high capital investment costs. However, financing mechanisms (access to credit, revolving credit funds, soft loans, etc.) can also overcome this barrier and are less conducive to abuse. Investment subsidies may still be very useful in promoting small-scale technologies to residential and small commercial or industrial enterprises, which have little access to good financing. If they are to be used, very careful oversight is necessary to guard against abuse. 7.2.3. Set-asides A set-aside is a block of energy supply, e.g. 50 or 200 MW, that is earmarked for renewable energy capacity. A transparent solicitation procedure can be used to select the most competitive projects or standard offers can be set with energy suppliers meeting capacity on a first-come, first-serve basis. Such a demonstration programme on a limited scale can be done without neither setting unwarranted precedents nor changing the current cost of electricity. If 200 MW are 20% more expensive (per MW) than the remaining 40,000 MW in a system, the influence on the cost of electricity would be 0.1%. The establishment of full-scale demonstration projects will fulfil several objectives: It will significantly help resolve concerns by energy sector stakeholders It will support the progress of actions 1-3 by practical learning processes It will bring international technology and experience to the country It will create show-cases for the citizens on how clean air, clean water, and sustainable energy systems can be obtained The winning projects will receive financial support; e.g. a subsidy per kWh or a guaranteed fixed electricity tariff, to ensure attractive paybacks. Example: A subsidy of R. 0.05 per kWh in 10 years given to 200 MW (operating 4000 hours/year) would cost R 400 million in total subsidy. To prepare a bid for power capacity requires that the project be fully developed to the stage of banking and contracting with potential electricity buyers. This preparation can be very costly. Therefore it is very important that the bidding conditions are clear and reliable, so that the bidders can trust that their bids will be treated fairly, and that the conditions offered are stable and viable. The bidding process should therefore go through a pre-qualification stage before real bids are invited. During the prequalification process the bidders will outline their project, justify the fuel resources available and prove the financial viability of the investor. Many project developers are foreseen to face lack of available expertise for solving the unfamiliar technical problems related to the project preparation. It is therefore recommended to establish a team of experts to assist the bidders with information and 142 counsel to help increase the quality of the tenders. The team should be established as a special unit within the responsible ministry. The services offered to project developers may be either direct technical assistance or financial assistance to employ a consultant to carry out a pre-feasibility study (e.g. max. R 150,000 per project). The technical assistance should comprise: Resource availability analysis, e.g. availability of bagasse as a reliable fuel. Legal and regulatory issues Commercial issues (PPA’s, fuel contracts) Financial issues (as some developers (power companies, multinationals) have ready access to cheap finance, whereas typical RE owners (e.g. a sugar factory or a wood industry) only can obtain much more expensive finance, the special unit could provide guidelines for project financing, including financial risk assessment). Sector experience Technical issues (e.g. available cogeneration technologies, contacts to equipment suppliers, complementary fuels) To ensure sufficient diversity of the programme, the projects may be grouped in separate categories, so that no one technology will eclipse others. The programme may for example distinguish between the following technologies: Bagasse CHP’s. CHP’s in the wood and pulp industry. Wind farms. Mini hydro. Micro-hydro. Solar thermal power generation. Some of the identified problems with current set-asides are: the UK NFFO has led to bureaucratic and expensive bidding processes with a “lumpiness” in installations12; the Renewables Portfolio Standard (RPS) under consideration in the US puts all renewable energy technologies together, discouraging development of the less mature technologies. However, the benefits of this mechanism may be worth the implementation trouble. The key advantage of using a competitive set-aside is that it encourages costcompetitiveness of renewable energy technologies. This is important because in addition to reducing the cost to the utility and end-user, it also demonstrates to the government policy-makers and the public that renewable energy technologies can become cost-effective. Another important advantage is that the government can easily determine and control the installed capacity of renewable energy generation. The RPS, which is under consideration in the US, will help to eliminate this lumpiness as well as provide economic efficiency through credit trading. However, the RPS in the US currently sets a minimum percentage of electricity to be generated 12 By lumpiness, we refer to the large amount of installations which follow a NFFO tranche and the lack of installations between the tranches. 143 by all renewables, and thus might only promote the least cost renewable energy technologies, e.g., wind turbines more than PV. An alternative strategy might break down the requirement or bidding into technologies, such as in the UK. This would allow for a minimum percentage of electricity to be generated by wind, solar, biomass, waste, etc. The RPS has generated some interesting debate, which can be found at: http://www.ucsusa.org/energy/brf.rps.html http://www.igc.apc.org/awea/pol/ngsaresp.html http://www.renewable.org/ This site lists a series of initiatives and arguments by the Gas Association against renewable energy One variation on the set-aside concept would be a standard offer for integrated resource bidding options which used both renewable energy and energy efficiency technologies13. This is similar to the integrated resource planning approach that minimises the cost of meeting energy services, but is designed for implementation. Standard offers have been implemented in the US, allowing a fixed amount of power capacity to be met by any party on a “first-come, first-served” basis. This is not a competitive bid: the advantage of cost-competitiveness is lost and the disadvantage of bureaucratic and expensive bids is eliminated. 7.2.4. Green marketing. Green pricing programs allow specified types of generators, determined by size and type of energy used, to obtain a higher payment than generally obtainable. The extra costs to the utility are being recovered through a special sales tariff for green electricity, which is being offered to customers wanting to support renewable energy through their energy bill. Green marketing appears to be effective in some countries and is becoming increasingly popular. However, it perpetuates the idea that renewable energy is expensive and needs support. It does not aim to decrease the cost of renewable energy, but may coincidentally have this effect in real terms in the long run. The motivation for setting ‘green tariffs’ is based on the assumption that there are certain electricity customers who would be willing to pay a premium for electricity produced in a way which is deemed as environmentally sustainable. This financial incentive should be provided for the generation of green energy. An alternative to a green tariff is that of increasing the taxed component of non-sustainable energy, thus raising electricity tariffs to the point where green generated energy becomes cost effective. This offers a unique opportunity to IPP developers in that the income stream from a sustainable energy plant can by virtue of the higher tariffs exceed that of other generation options and offers the potential to increase the profitability of the project. If the capital and operational costs of two different IPP plants are equal but that one option can sell its electricity at a higher tariff by generating it in a sustainable manner Adam Hinge, “Integrated Resource Bidding as a Tool for Introducing Sustainable Energy Investments amidst Power Sector Restructuring”, prepared for IIEC, May 1998. 13 144 the green option will be the preferred one. It was indeed this mechanism which was used as incentive for the development of much of Europe’s renewable energy IPPs. It must be kept in mind that green tariffs are not a prerequisite for renewable energy IPPs. Whilst higher tariffs will not be refused by any IPP, some of the IPPS under development (such as Fridenheim or Bethlehem) have developed their business plans based on current electricity tariffs and do not require additional subsidies in order to become competitive. In order to market green energy, a number of criteria must first be satisfied. The electricity generation sector must be open to competition The transmission system must be accessible to all suppliers Electricity distributors must not be locked into a supply contract with a single generator Customers must have a choice of suppliers A certification system for electricity must be in place to ensure that electricity sold as green is indeed generated sustainable The last point is very important in terms of the structure of the electricity market. The actual mechanism used to promote green energy will have a deep impact on the markets structure and development. The different options followed in Europe and the different effects resulting has shown that there is currently no ideal model, which will lead to increased uptake of sustainable energy without skewing the market in an inefficient manner. The conditions described above are those, which would be found in a liberated electricity market with at least generation and distribution competition. 7.2.5. Power purchase agreements. Clearly, one of the most important mechanisms for grid-connected renewables is the establishment of standard, reliable, long-term power purchase agreements. This is a key component for the success of renewable energy on the grid. It must be clear to the private sector and their financiers that they can hook up their power plant to the grid and receive a certain payment for energy over a set period of time. In a period, where the electricity supply industry and/or the electricity distribution industry is being restructured, it may be very difficult, if not impossible, to obtain long term contracts. 7.2.6. Loan guarantees. The high investment costs of renewables are a significant barrier and the finance sector needs to be examined to see if special finance mechanisms are needed. This will be especially necessary if investment subsidies are not used. With the recent economic crisis, preferential finance for power plants and preferential loans or tax breaks for renewable energy businesses may be necessary to encourage the private sector. Along these same lines, loan guarantees can help to reduce financing risks and thus lower costs. 145 7.3. International Initiatives The International Finance Corporation, the World Bank, the Global Environmental Facility and others have kicked off two global investment and market transformation initiatives know as the Solar Development Corporation and the Photovoltaics Market Transformation Initiative Respectively. The Solar Development Corporation is intended to offer advisory and financial services to speed up the use of solar PV systems. The Corporation will be capitalised at $50 million with the IFC contributing about $6 million. The SDC will support many aspects of the solar PV industry including local assembly, system integration, and energy service companies as well as traditional distribution and retail operations. It will as well invest in financial intermediaries such as banks, leasing companies, and non-traditional (e.g. non-bank) intermediaries such as NGOs. There will be another arm to the SDC, the business advisory service arm, which will fund advisory services and general PV awareness and capacity building services. More can be found at http://www.worldbank.org/pics/ifcspi/1ws09137.txt The Photovoltaics Market Transformation Initiative is targeted at three countries, Kenya, India, and Morocco. It will make investments in 15 to 20 sales, service or system integration companies. The PVMTI is supported by $30 million in concessional GEF funds. IFC says the PVMTI is intended to address PV market barriers by supplying “appropriate” financing and stimulating business activity. “Appropriate” means below market terms, e.g. lower interest or longer maturities than are locally available. The IFC will broadly distribute a solicitation for project proposals. Successful proposals will get between $500,000 to $5 million. More can be found at http://www.worldbank.org/pics/ifcspi/1w502223.txt Launched in February 2000, the Renewable Energy and Energy Efficiency Fund for Emerging Markets, Ltd. (REEF) is the first global fund organised to tap the considerable opportunities to invest in emerging markets renewable energy and efficiency. REEF actively seeks to make minority equity and quasi-equity investments in profitable, commercially viable private companies and projects in various sectors. The sectors include electricity generation, primarily fuelled by renewable energy sources, energy efficiency and conservation, and renewable energy/efficiency product manufacturing and financing. The International Finance Corporation joined with several other private and public sector groups to invest in the REEF. The fund will invest up to US$100 million in these projects and is intended to stimulate investment in environmentally friendly energy technologies in the developing world. The fund will target the ample opportunities for investment in grid-connected renewable energy technologies such as small-scale hydroelectric plants, geothermal power plants, biomass-fuelled power plants or cogeneration units, and wind farms. It will also invest in off-grid renewable energy projects and energy efficiency projects. The fund's investments will be limited to projects with total capital costs below $100 million, and will also include a deliberate focus on smaller projects, using GEF co-financing where appropriate. 146 7.4. Country Experiences with Grid-Connected Renewable Energy Policies Unless specifically noted otherwise, the information contained in this section has been taken from R. Redlinger (1998), 'Review of International Renewable Energy Policies', UNEP Collaborating Centre on Energy and Environment. The renewable energy promotion mechanisms described in the previous section are rarely implemented in isolation. Rather, countries typically follow a multi-pronged approach incorporating various mechanisms. In some cases, this is a result of a clearly developed strategy and recognition that any one mechanism may not be sufficient to achieve the desired implementation rates. In other cases, the use of multiple mechanisms is simply a result of poor policy co-ordination and a piecemeal approach. Significant insight can therefore be gained by examining countries’ comprehensive policies for renewable energy promotion and analysing their successes and failures. 7.4.1. Denmark Denmark is the world’s largest wind turbine manufacturer as a result of stable wind energy promotion policies and strategies. Incentives for wind energy can be categorised according to ownership: wind energy co-operatives, private, and utility. Co-operatives and private owners enjoy the following incentives: (1) guaranteed power purchase contracts with utilities in which utilities pay generators 85% of the local retail price of electricity, amounting to approximately 0.33 DKK/kWh; (2) refund of 0.17 DKK/kWh energy tax; and (3) refund of 0.10 DKK/kWh CO2 tax. Furthermore, individual persons who participate in wind energy co-operatives can own up to 20,000 kWh/year worth of shares in the co-operatives, of which the first DKK3000/yr of income is tax-free (and the remainder taxed at a 60% rate). To the extent that the wind power purchase contracts increase the cost of electricity, these costs are passed on to utility ratepayers. Lastly, any grid reinforcement which may be required as a result of non-utility wind power installations are paid for by the utilities. Utility-owned wind power projects can only obtain refunds of the CO2 tax. Denmark’s success in wind energy can be credited to their emphasis on local project ownership through co-operatives, which has made it possible for local populations to economically benefit from wind energy. This has also help to reduce local opposition to wind energy development. The introduction of a market for green certificates was decided by Parliament in March 1999, subsequently followed by law in June 1999. Neither the certificates nor the market has yet been established. It is planned to start issuing the certificates by January 2001, and create the market by 2003. The system will cover electricity produced by wind turbines, different types of biomass, solar PV, geothermal plants, and hydro less than 10 MW. The government guarantees that the value of the certificates shall be between 0.1 and 0.27 DKK/kWh (1 ZAR = 1.2 DKK). 147 Consumers are obliged to purchase a certain amount of certificates. If they do not or cannot, they will have to pay a penalty of 0.27 DKK/kWh. Government will regularly announce RE-quotas, where all consumers will be obliged to purchase an increasing share of electricity from renewable energy. By setting a high initial target (20%), the government ensures that the value of certificates in the beginning will be close to 0.27 DKK/kWh. 7.4.2. Germany Germany has become the country with the largest installed wind energy capacity in the world. Three primary components have been responsible for this growth: guaranteed power purchase contracts, generous per-kW payments, and highly favourable financing terms. The Renewable Energy Feed-In Tariff (REFIT) contained within Germany’s Electricity Feed Law (EFL) provides the guaranteed power purchase contract component. The REFIT specifies the price at which German utilities must purchase all power from renewable generators; and this price is tied to the residential electricity tariff. Wind generators receive a payment of 90% of the residential tariff, amounting to a payment of 0.1721 DM/kWh in 1996. At the May 1998 exchange rate of 1.76 DM / US$, this would be equivalent to 0.098 US$/kWh, approximately 10% higher than the payment for wind provided in Denmark. The extra costs of purchasing this wind power compared to conventional electricity are passed on to electricity customers of the local purchasing utility, causing higher electricity prices in areas with substantial wind energy development. This is changing, however, to uniform funding by consumers throughout the country to reduce regional funding inequities. The second component comes in the form of an investment subsidy of DM 200/kW for each project. The maximum subsidy is DM 100,000 for project smaller than 1 MW, and DM 150,000 for projects larger than 1 MW. The last component is that below-market loans are available from the Deutsche Ausgleichsbank (DtA) that have a fixed interest rate of 1 – 2 % below commercial rates and a maximum repayment grace period of 5 years to ease cash flow constraints during a project’s initial years. Such loans can cover approximately 75% of total project costs. Furthermore, another 17 - 20 % can be loaned from local banks and grants, thus reducing investor equity requirements to only 5 – 8 % of the total project costs. Although Germany’s program has successfully promoted a large growth in the country’s wind energy capacity, the level of subsidies has been higher than what could be justifiable on the basis of avoided costs or environmental benefits. One important component that is lacking and is important to the long-term development of renewable resources is pressure for project developers to reduce costs. Green electricity as a marketing product has been introduced on a voluntary basis. It is not yet a success; by February 2000 less than 0.1% of all customers were purchasing green electricity. Grid companies are obliged to buy RE electricity. Approximately 15 new green power trading and supply companies have been set up. Solar PV dominates the market. 148 Additional information can be found at http://www.dewi.de/. 7.4.3. India India has been supporting renewable energy development since the late 1980s through the Ministry of Non-Conventional Energy Sources (MNES) and interested state governments. MNES’s homepage is at: http://www.renewingindia.org/organisations/MNES/html/mnes-main.htm . Similar to the previously discussed European countries, India’s efforts to develop grid-connected renewable electricity have been focused primarily on wind, though biomass-based cogeneration has begun receiving significant attention more recently. General information on India’s renewable energy programs can be found at the following Internet website: http://www.renewingindia.org/. Indian wind policy has been successful in creating a domestic market for private development of wind power, which now accounts for the vast majority of the country’s installed wind energy capacity of more than 900 MW. India’s success can be credited to the following three incentive mechanisms: guaranteed power purchase agreements, tax incentives, and concessional loans. Power purchase agreements allow the wind power developer in India to “wheel” the generated electricity by using the utility grid as a means to store wind energy for use at another location or time. For example, the developer can use its generated wind power by wheeling it through the grid, and draw the same amount of power from the grid at its own industrial facility located at another geographic location. Other possibilities is that the developer can wheel the power to a third party consumer, or sell the power to the state utility. The developer can also distribute the wind power to the grid at the time of generation, and claim it back later in the year during the lowwind season. The conditions for wheeling wind power generally vary from state to state. The central government also offers tax incentives in order to encourage wind power development. Wind power developer enjoy the following tax benefits: Five-year tax holidays on revenue from sales of electricity; Accelerated depreciation of 100% on investment in equipment for the first year; Excise duty and sales tax exemptions for wind turbines; Import duties on a variety of components waived. Lastly, the government created the Indian Renewable Energy Development Agency (IREDA) in 1987 to provide assistance in obtaining loans from the World Bank, the Asian Development Bank, and the Danish International Development Agency (DANIDA). IREDA offers favourable loan conditions for investment in all forms of renewable energy. Additional information on IREDA can be found at the following Internet website: http://www.renewingindia.org/organisations/IREDA/html/iredamain.htm. 149 7.4.4. Netherlands Although the Netherlands has traditionally been one of the world leaders in wind energy, the Dutch government continues to seek policy mechanisms that encourage more renewable energy development. Over the past few years, several marketoriented mechanisms were adopted, including Green Funds, the Accelerated Depreciation on Environmental Investments Scheme (VAMIL), a regulating energy tax, and Green Labels. Several banks established the Green Funds program in 1995 to allow the public to invest at an average interest rate of 4% per year. This interest is tax-free for investors. The bank is then obligated to invest at least 70% of the capital in the Green Fund on environment-friendly projects, which includes most renewable energy technologies. The VAMIL allows environmental investments such as renewable energy technologies to be depreciated more rapidly, thus reducing taxable income at the beginning of projects and thus improving cash flow. The regulating energy tax was introduced in 1996 to stimulate households and small businesses to increase their energy efficiency; highly efficient consumers can avoid paying the tax if their electricity consumption is less than 800 kWh per year and gas consumption is less than 800 m3 per year. This tax also supports renewable energy because the revenue collected on electricity generated by renewable energy projects is paid to the generator rather than to the government. The latest and perhaps most radical development is that, as part of the liberalisation process and as part of the MAP 2000 covenant between the government and utilities to increase renewable electricity’s market share, a tradable “green labels” market has started as of January 1998 (Windpower Monthly, 1997). Under current laws, local energy distribution companies (LEDCs) must purchase renewable electricity from independent power generators at a price determined based on the current market price of electricity (currently around 0.08 NLG/kWh) and the Regulating Energy Tax refund (approx. 0.03 NLG/kWh). However, under the new program, in addition, the LEDCs must issue green labels to the renewable generator based on the number of renewable kWh sold to the grid (one green label represents 10,000 kWh of renewable electricity). The renewable generator can then sell these green labels on an open market to distribution utilities who will all be required to own a certain quota of green labels as part of their agreement with the government. Let us take wind energy as an example and assume current production costs of approximately 0.16 NLG/kWh and current payments from utilities of approximately 0.11 NLG/kWh (0.08 market electricity price plus 0.03 Regulating Energy Tax refund). The renewable generator would have to sell its green labels for at least 0.05 NLG/kWh to realise a profit (Windpower Monthly, 1998b). Utilities can fulfil their renewables quota commitments in three ways: by developing their own renewable power plants, by negotiating bilateral agreements with independent producers, or by purchasing green labels on the open market. This mechanism is similar to the Renewables Portfolio Standard (RPS) mechanism being contemplated in the USA and essentially reserves a certain percentage of the 150 electricity market for renewable energy within an otherwise liberalised market. However, unlike the RPS, the Dutch green labels scheme guarantees that all renewable generators can sell power to the grid at an assured price, thus removing some of the market uncertainty of the RPS but simultaneously perhaps reducing the economic incentive to reduce renewable energy costs. The Dutch policy mechanisms such as the Green Funds and Green Labels programs represent creative new initiatives, although the overall effort has its drawbacks. For example, Dutch wind energy activity has dropped off drastically since previous subsidies were eliminated in the effort to take a more market-oriented approach in supporting renewable energy. Inadequate co-ordination to address local planning concerns also has led to wind turbine siting difficulties similar to the UK experience. The Web site for Dutch Green Financing Schemes: http://www.novem.org/netherl/green.htm The green electricity monitor is the WWF Netherlands branch known in Dutch as the Wereld Natuur Fonds. http://www.wnf.nl/home.cfm (in Dutch) 7.4.5. Spain A fixed premium price is paid to all renewable generators. This has resulted in a rapid increase in installed renewable energy generation capacity and in the establishment of strong manufacturing industries. 7.4.6. Sweden The government of Sweden has offered capital cost subsidies in order to encourage renewable energy development since 1991. Its new energy law (effective February 1998) provides subsidies as a percentage of capital costs as follows: 30% for biomassbased cogeneration, 15% for wind, and 15% for small hydro. In addition to capital cost subsidies, small renewable energy projects also receive guaranteed power purchase contracts with local utilities. The new energy law requires local distribution utilities to purchase all electricity generated by projects of less than 1,500 kW within their service territories. The small generator is paid the residential tariff plus a credit for reduced transmission and distribution losses minus reasonable costs for utility administration and profit. 7.4.7. United Kingdom (UK) The UK introduced its Non Fossil Fuel Obligation (NFFO) program in 1990 to promote renewable energy technologies. Under the NFFO, a certain portion of the electricity market is set aside to be supplied by renewable technologies. Developers submit bids for proposed projects within each technology category such as biomass, wind, etc., and the projects with the lowest per-kWh price are awarded power purchase contracts. The regional utilities are obligated to purchase power from NFFO-awarded generators at a premium price. The difference between the premium price and the average monthly power pool purchasing price is subsidised through the Fossil Fuel Levy as administered by the Non-Fossil Purchasing Agency. 151 The NFFO is one of the few successful working models for providing stable renewable energy contracts within a privatised competitive electricity industry structure. However, it is not without its faults and controversies. Some important lessons learned from the NFFO are: Small renewable energy projects have difficulties in attracting financing despite the existence of the NFFO; The NFFO start-stop auction process led to projects being developed quickly with limited public planning input. The lack of co-ordination between the NFFO and local planning authorities sometimes led to local public opposition, especially in the cases where wind farms were developed in scenic areas; The competitive nature of the NFFO is useful for stimulating technological innovation and cost reduction; In the case of the NFFO, production incentives paid on a per-kWh basis have been shown to be more effective than cost-based incentives. The latest status of the NFFO issues is that a number of generators who received support under NFFO 1 and 2 have had to make the transition to the open market at the beginning of this year. The Renewable Generators Consortium was formed with the support of the Department of Trade and Industry's Renewable Energy Programme in order to help this transition process. The roles of the Consortium were: (i) to give power suppliers the opportunity to purchase renewable power in geographical and technological blocks; (ii) to act as a single negotiating point of contact which both reduced negotiating costs and offset the oligopoly power of the large suppliers; (iii) to allow more sophisticated trading opportunities than could be secured through over 100 separate bilateral deals. The Consortium has 116 members, out of the total of 146 generators who received support under NFFO1 and 2. Consortium members account for 312 MW of capacity, out of a total of 326 MW implemented under NFFO1-2, and a total of about 600 MW implemented so far from all rounds of NFFO. (NOTE: it is important to distinguish between the capacity ordered and the capacity up and running. Although NFFO tries to support projects, which stand a good chance of going ahead, some projects, which are accepted under NFFO, never get implemented due, for example, to problems with securing planning permission etc. The figures quoted in literature usually represent the orders rather than the actual implemented projects.) The RGC has successfully negotiated offers from one or more of nine large suppliers for all 116 members, to purchase their output at a premium price. Presumably the suppliers think that they can recoup this premium through 'green power' pricing contracts with end-users, or maybe simply regard having some renewables generation in their portfolios as a way of 'future-proofing' themselves against the possibility e.g. of a carbon tax. As of July 1998, 40 of the 116 generators had actually accepted the offers made, although the expectation was that many more would do so. The 40 offers so far accepted represent 120 MW of generating capacity. 152 The government is very excited at the success of the RGC in negotiating these agreements as it clearly demonstrates the possibility of generators to make the transition from a protected niche into the open market. However, it must be remembered that the first two orders of NFFO paid a much higher premium to generators than subsequent orders, part of the reason for which was to ensure that they could pay off all the capital costs before the NFFO contract period finished. It remains to be seen whether projects under later rounds of NFFO will find the transition to open market as smooth, although we will have to wait until 2009-2012 to find out as the contracts were for a period of fifteen years. The contact details: Christine Mitchell, Energy Technology Support Unit, Harwell, Oxfordshire, OX11 0RA (Tel. +44 1235 433 240). Catherine Mitchell, Science Policy Research Unit, University of Sussex, Brighton, BN1 9RF (Tel. +44 1273 686 758, Fax +44 1273 685 865) NFFO information can be found at: http://www.dti.gov.uk/NewReview/nr38/html/generator.html. 153 8. RECOMMENDATIONS Based on the research undertaken, a number of recommendations were developed. There are five areas according to which the recommendations can be grouped. A short overview of the recommendations in the respective areas is given here. The recommendations are outlined in more detail below. Policy and legislation – immediate initiatives Recommendation no. 1: Renewable energy IPP set-aside programme Recommendation no. 2: Interim power purchase regulation Policy and legislation – longer term initiatives Recommendation no. 3: Power purchase regulation Recommendation no. 4: IRP inclusion of RE IPPs Recommendation no. 5: Electricity information Recommendation no. 6: Capacity development, government Recommendation no. 7: Capacity development, civil society Regulation - tariffs and grid connection Recommendation no. 8: Transparent licensing Recommendation no. 9: Technical grid connection code Recommendation no. 10: Renewable energy tariff structure Support activities Recommendation no.11: Long term barrier removal Recommendation no.12: Investment capital for renewable energy Recommendation no.13: Green power marketing Demonstration activities Recommendation no.14: Darling wind farm Recommendation no.15: Mini-hydro Recommendation no.16: Cogeneration in sugar industry Recommendation no.17: Cogeneration in wood industry 154 Next Steps The next steps would be to obtain acceptance of the recommendations by government and the key stakeholders and on implementation of accepted recommendations. Approved recommendations will have to be prioritised and an action plan developed for each recommendation higher up in the list such that individuals can be identified and empowered (given the time and money) to deliver on the recommendations by an agreed time. In view of the industry restructuring activities that is happening, it will be most appropriate to incorporate the requirements for renewable energy and energy efficiency in the new licences and to develop the tariffs and frameworks as part of restructuring. This will, however, only happen with clear instructions and policies from government. The present proposals should be integrated with the planned use of renewable generation in hybrid-off-grid systems. These plans are already at an advanced stage. 8.1. Policy and legislation – immediate initiatives 8.1.1. Recommendation 1: Renewable energy IPP set-aside programme Through a cabinet memorandum set aside approximately 200 MW of generation capacity for a transparent solicitation procedure to select the most competitive renewable energy projects to test and expand the prospects for the development of renewable energy IPPs in South Africa. Eskom Distribution and/or the future REDs shall be obliged to purchase the electricity generated. Award of a power purchase agreement shall be an integral part of winning the bid. Eskom may be enabled to establish a fraction of the set-side itself, but independent power producers should establish most of the capacity. Justification: Bulk generation of renewable energy is the fastest growing energy sector internationally. Already today many exporting South African companies have come under pressure from their overseas clients regarding environmental issues. Export driven economic development objectives make it imperative for South Africa to join this trend. In order for South Africa not to "miss the boat", it should speed up the integration of these technologies into the generation system. It is important to note that it is not primarily the technological development that is of concern, but the development and implementation of adequate legislative and regulatory frameworks. A wind farm can be built from scratch within a period of less than half a year, as opposed to building a single new coal-fired power station which can take up to a decade. As South Africa 155 considers reduction goals for greenhouse gas emission, it will be important to anticipate likely technologies to identify and pursue. This fits within the current discussions on Clean Development Mechanism approaches. If South Africa waits, it will be too late to only then start developing and implementing relevant regulation. The set-aside programme will effectively become a catalyst to solve a range of issues related to the market penetration of IPPs and thus the forthcoming restructuring of the electricity supply industry. With the current structure of the electricity supply industry, the most of appropriate purchaser of the electricity generated by the renewable IPPs appears to be Eskom Transmission. . Eskom Transmission has three major functions: 1) Operation of Eskom’s internal pool, 2) owner of the network, and 3) international trading. The purchase of renewable energy generated electricity appears to be comply appropriately with the international trading function. The Regional Electricity Distributors should be given the right to purchase some of the renewable energy generated electricity in their respective areas, and also to establish own renewable energy capacity within a reasonable limit. As part of the bidding requirements, special priority can be given to projects with high employment potential, high rural development potential etc. Supporting Information: The proposed demonstration programme on a limited scale can be done without neither setting unwarranted precedents nor changing the current cost of electricity. Eskom Transmission may have to purchase some of the electricity at a price, which is higher than the long run marginal costs of alternative capacity (coal or nuclear). However, the impact on the electricity tariff would be negligible. As a conservative estimate, if 200 MW of renewable energy IPPs would receive an incremental tariff of 6 ZAR cents/kWh (4000 hours operational hours per year), this would add up to 48 million ZAR per year. It is suggested that electricity consumers cover these costs. In that case, the average electricity tariff would have to increase by 0.03 ZAR cents/kWh. To ensure sufficient diversity of the programme, the projects may be grouped in separate categories, so that no one technology will eclipse others. There is some overlap between this recommendation and recommendations 14-17, in particular the already endorsed National Darling Wind Farm Demonstration Project. However, the set-aside is much broader in scope, as the set-aside: will be more diversified thereby forming a more sound experience upon which to base the long-term development; will mobilise a much larger number of stakeholders (project developers, investors, financing institutions); 156 will get a higher international profile than a single project demonstrating a technology. The preparation and implementation of the Darling project will, however, in many ways create substantial input for the set-aside programme. 8.1.2. Recommendation 2: Interim power purchase regulation Develop an interim regulation regarding conditions for the grid-connection of power from small and distributed generators to facilitate the implementation of the set-aside programme (recommendation 1). Justification: When it comes to the determination of fair grid-access conditions around the world it has almost invariably been the case that conflicts have arisen between power utilities on the one hand and distributed power generators on the other. The distributed generators on their side claim that the power they provide represents a value in terms of avoided costs to the power system, which they should be accounted for. The power utilities on their side tend to look upon distributed generators as a very uncertain business. There is therefore a need for a neutral body to regulate and intermediate the area on grounds of generally accepted criteria. The establishment of the REDs will result in the establishment of network service providers as opposed to the present utilities that own generation. The REDs will be obliged in its network licence to provide a regulated network service to all users of the network (including independent generators). The network prices for putting energy into the network (and to take it out) will have to be developed and must receive priority by the REDs. Supporting information: Some key issues that should be addressed by the regulation are: How to determine the avoided energy costs and the avoided capital costs. The avoided energy cost is not an immediate issue, given Rec. 1. If the RED (or Eskom Distribution) is obliged to purchase, there will be less pressure to develop these rates, but it is essential that it be developed. How to share the connection costs. How to cover the costs of eventual increased fault level in the local distribution system. How to determine the eventual reinforcement of the local grid, and how to cover the costs. How to determine the change of energy losses imposed by the new generator. How to meet distribution and/or transmission constraints. 157 8.2. Policy and legislation – longer term initiatives 8.2.1. Recommendation 3: Power purchase regulation. On the basis of the interim power purchase regulation (cf. recommendation 2) a regulation regarding conditions for power purchase from small and distributed generators beyond the set-aside programme should be developed. Justification: There is a need for an interim power purchase regulation right from the beginning of the set-aside programme. During the programme several experiences will be gained, and the interim regulation would therefore need to be amended to facilitate the further development of IPPs after completion of the set-aside programme. It may likely be appropriate to establish a standard price for the purchase of renewable energy based on the avoided cost plus a premium to allow for externalities, as is the case in other countries (see recommendation 10). 8.2.2. Recommendation 4: IRP inclusion of renewable energy IPPs Create a long-term plan for the inclusion of renewable energy IPPs into the electricity system. The plan should be based on an Integrated Resource Planning framework that explicitly considers environmental, social, and economic costs and benefits of resource alternatives. Justification: International experience is indicating that renewable energy without any doubt constitutes an important part of the energy mix in the future. However, as with any technology, the start-up and phasing in difficulties have to be overcome. Medium to long term national energy planning needs to consider the inclusion of renewable energy into the national energy mix. To achieve this, energy modelling and forecasting activities should provide concrete estimates of the target renewable energy capacity, considering macroeconomic, social, and environmental costs and factors. The integrated resource plan should be a comprehensive plan comparing the advantages and drawbacks of on-grid and off-grid solutions, emphasising the potential of renewable energy to nourish rural development. Government policy regarding the desired share of renewable energy or subsidy for externalities would have to be developed. The REDs will be required through their license to present a plan of their electricity purchases, energy efficiency and demand management interventions. Their tariff plan, for NER approval, will have to be linked to their resource plans and the resource plans will have to take government policies into account. 158 Supporting Information: The DME is presently undertaking such an exercise with the overall Integrated Energy Planning framework, as stipulated in the Energy White Paper. It is important to use the existing stakeholder forum (IEP steering committee) to ensure that Renewable Energy is being allocated a realistic and appropriate share. 8.2.3. Recommendation 5: Electricity information Make all essential power sector data publicly available (e.g. generation costs, future investments, and external impacts) through a central electricity information service. Justification: Project identification, planning, feasibility studies and the securing of finance for IPPs are significantly constrained by the lack of sufficient and reliable information. Potential investors are hesitant, if the framework for their decision making is not clear. Comprehensive and detailed information about cost structures, tariffs, growth forecasts, and development programmes etc. in the industry must therefore be publicly available. The public awareness of energy issues in general, renewable power producers and energy economy and energy environment issues would be systematically improved through a public involvement initiative. Some elements of this are in place already through participation of non-government organisations in various review and policy panels. The efforts would benefit from broadening the knowledge of a wider group. The initiative needs to be well co-ordinated to ensure data is relevant and that proprietary information is respected. The envisaged IRP process will provide for an information depository together with checks and balances to ensure that data is relevant. Supporting Information: Government is presently in the process of addressing this issue by creating adequate legislation based on international experience. Most countries have energy information agencies reporting to government that are mandated to undertake this task. As an example, the Thailand National Energy Policy Office publishes substantial information on its web site (www.nepo.go.th). In Europe and the US similar activities and organisations exist. 8.2.4. Recommendation 6: Capacity development, government Sustainable capacity development within DME and NER seems to be a crucial precondition for the longer-term success of renewable energy in the country. Other relevant government and non-governmental institutions may also need strengthening in this field. 159 Justification: The imminent changes to the structure and governance of the electricity sector places large demands on DME and NER. Furthermore, DME’s capacity to facilitate and support the development of renewable energy is fairly limited, due to the fact that renewable energy is a new policy issue in South Africa. Supporting Information: There is a significant amount of international assistance and also domestic expertise available that should be utilised and co-ordinated. This is already happening, such as evident in this project. 8.2.5. Recommendation 7: Capacity development, civil society Develop mechanisms to support potential owners of renewable energy IPPs and organisations promoting renewable energy. Justification: Traditional power plant operators are usually big corporations. They are very experienced and they can afford to acquire extra technical, economic, financial, and legal expertise. Small owners often cannot afford to acquire much expertise. By taking up a strong international IPP developer or utility as partner renewable energy independent power producers can compete on equal footing. The policy choice as to whether to provide additional support is in some cases related to whether the government wants small local enterprises to be able to enter this market or whether they want to leave it nearly exclusively to international joint ventures. It is clear in either case that renewable energy independent power producers can be successful if the competition with conventional generation is open, fair, and accounts for all the costs. The support would primarily be technical, legal, and commercial assistance to trade associations (associations of sugar millers, wood industries etc.), NGOs and institutions. The IRP framework (recommendation no. 4) and project-licensing framework are interlinked. The industry structure has a fundamental impact on how generation will be licensed, as will the formation of the REDs. Progress will be dependent on the vision for the ESI and the associated government policies. 8.3. Regulation – tariffs and grid connection 8.3.1. Recommendation 8: Transparent licensing. Develop transparent and accountable licensing conditions together with more consistent IPP license procedures. 160 Justification: In order for RE IPPs to plan and to make viable investments, the playing field needs to be well defined and prepared. To this end, licensing procedures must be published and should address the detailed information requirements that RE IPPs have. Supporting Information: The licensing frameworks must be aligned with the overall energy policy and legislation that is available. In particular, the outcome of the Integrated Energy Planning and Integrated Resource Planning activities that are presently undertaken should enable the NER to develop and publish adequate IPP licensing frameworks. The licensing procedures are very much in line with the Environmental Impact Assessment under the jurisdiction of the Department of Environmental Affairs and Tourism (DEAT). Liaison with DEAT would therefore be beneficial. 8.3.2. Recommendation 9: Technical grid connection code Establish a national grid connection code, which specifies connection requirements appropriate to the size and other characteristics of the resource and does not impose inordinate financial or technical burdens. This includes synchronisation conditions and rules for sharing the connection installation costs. Justification: Grid connection barriers are often described by utilities as technical and safety issues not subject to policy solutions. However there remain significant obstacles to smaller resources, even though technical solutions to legitimate safety and operational issues have already been successfully implemented around the world. Technical requirements for grid connection should be adequately structured according to power generator capacity, voltage, and location. Small power plants should and can have simpler grid connection specifications than large power plants. Supporting Information: Many countries have now developed grid codes that include appropriately reduced requirements for smaller resources. IEEE (the international Institute of Electrical and Electronic Engineering) established a standard (no 929) for grid connection. The standard actually applies to the inverter, a device that adapts the voltage and frequency of the IPP generator to the standard AC power transmission network. Inverters are used for distributed generation systems such as fuel cells and micro hydro-turbines, and many of the interconnection measures from IEEE 929 can be adapted for these other technologies. An IEEE working group is currently drafting IEEE SCC21 P1547 relating directly to technical grid connection requirements for distributed energy systems. The final IEEE draft will be available in early 2001. 161 Eskom is currently developing a grid code for the transmission network (above 132 kV). A grid code for the distribution systems may probably be developed from this code. 8.3.3. Recommendation 10: Renewable energy tariff structure To ensure a development of renewable energy IPPs beyond the set-aside programme, end-user tariffs should be set which reflect the following conditions: The avoided-cost principle should reflect the long run marginal cost of electricity, not only the short run marginal cost. IPPs situated close to loads should be credited for avoided line losses. This is in line with the transmission network charges of the proposed wholesale electricitypricing system (WEPS) as outlined in section 6.3.1 on transmission costs. Tariffs should be based on full cost accounting. Tariffs should include environmental externalities. In case this results in overrecovering of the expenses, the surplus income can be transferred to environmental mitigation measures. Third party access to the transmission system and the distribution systems should involve reasonable wheeling and banking tariffs defined by NER14. Justification: For non-utility generation, the tariffs shall be approved “on the basis of full avoided costs” (White Paper of Energy Policy for the Republic of South Africa 1998). The paper further noted “By including environmental costs into the pricing structure for further development of renewable and environmentally benign generation technologies such as hydro, wind, solar thermal, and waste incineration will also be encouraged”. Supporting Information: The following were stipulated in the energy white paper as requirements to be taken into account in developing a wholesale electricity pricing system (WEPS): A level playing field for generators and distributors/customers Cost reflectivity Transparent subsidies Improved efficiency in supply and usage Open access to the transmission system The enabling of competition 14 Wheeling is the transfer of electricity via the grid from a generating resource to a customer. Wheeling tarrifs recognise that transmission line is a common carrier, open for access by multiple electricity buyers and sellers. Banking is the storage of intermittent electricity for resale at a later time. Depending upon the dispatch flexibility of other system resources, banking can be agreed to occur over hours, days, weeks, or months. 162 8.4. Support activities 8.4.1. Recommendation 11: Long term barrier removal. In parallel with the recommendations in the areas of demonstration and regulation, and based on the experiences from the concrete projects, proper long-term and general solutions to mitigate all essential barriers shall be systematically identified and implemented in order to further nourish the development of renewable IPPs. Justification: The national electricity landscape is changing. However, since existing players enjoy a great number of advantages over new market entrants, pro-active steps aiming at the removal of barriers are necessary to ensure a level playing field. This could be achieved through appropriate legislation that forces the transformation process to include the needs of future market players. An important part of the activities would be to investigate and implement mechanisms to ensure as a minimum an equal level playing field for central power plants and IPPs. For example, new resources should be selected based upon least-cost principles, which explicitly value and quantify the total cost of resource options including environmental externalities. Long term barrier removal has high priority in the current reform debates. Supporting Information: The country has recently embarked on a reform of the electricity sector, which involves restructuring of the distribution industry as a first step. As the issues relevant to RE IPP are addressed with in these activities, these needs of RE IPP need to have particular attention so as not to be overlooked. 8.4.2. Recommendation 12: Investment capital for renewable energy The availability and accessibility of investment capital for small project developers should be improved. Innovative ways of accessing low-cost finance should be made available to IPPs. Several options have been developed internationally. A project should be launched to investigate such options and come up with recommendations in this area. Justification: Traditional power utilities, by virtue of being well established, usually have ready access to cheap finance (low interest, long maturity), whereas typical renewable energy owners only can obtain much more expensive finance. 163 Supporting Information: There are many meaningful avenues to increase the availability of financial resources for investments in renewable energy. The various types of capital that can be targeted for investments include equity capital, debt/loan capital, credit enhancements, grants, risk guarantee schemes as well as any operationally feasible combination of these sources. A survey should address the real risks (or the perceived risk by the lenders and/or investors) associated with investments in renewable and develop the most appropriate mechanism to underwrite these risks. Issues like contingent grant and/or loan financing, portfolio diversification, performance contracting, risk sharing arrangements, risk insurance premiums and collateral requirements (hardware, fixed assets) need to be addressed in the financial risk mitigation strategy to be developed. 8.4.3. Recommendation 13: Green power marketing Allow a “Green Power” option to cover the incremental costs of renewable energy power producers. The best option for a “green power” based electricity sale, within the time frame considered for this project, would be to recruit from industrial customers. Justification: The first glimmer of demand for green energy has already emerged in South Africa. The demand is stemming from several sectors of the market. Private enterprises. There is increased international demand for environmentally friendly products. South African enterprises seeking international markets for their goods are increasingly asked to take actions towards reducing the environmental impacts of their manufacturing processes. The ISO 14000 certification initiative is evidence of this trend. Local authorities. If the power is generated locally, it may carry employment benefits and thereby reduce the demand for other job creation programmes. In addition, various electricity generation sources do have distinct direct employment and spin-off characteristics. Households. There are consumer segments concerned about the environment and willing to pay an increased tariff for green energy, electricity from more benign resources such as wind, solar, etc. Many of the aspects are already being developed in anticipation of an electricity market that allows energy trading. Small players will be able to participate in the markets by allowing the aggregation of small generation and aggregation of loads to make use of the opportunities available to large players. Supporting Information: This can be done under the current regulatory and legal environment. The renewable power producer would negotiate a PPA with a specific customer. The NER would approve the Green Power tariff on the basis that it serves a legitimate public purpose. The following steps would be required to develop a contractual system: 164 Identify a producer of green electricity and sign a supply contract. Identify an industrial user which would be willing to buy green energy Negotiate and sign a power purchase agreement (PPA) at a mutually acceptable tariff. Submit the tariff to the NER for approval. Submit the PPA to the NER for approval. Negotiate a wheeling charge with Eskom and/or the local distributor through the NER for the transmission of the power. Develop and implement an electricity metering system to control and audit the generation and consumption of the green energy. In a later stage a more market-based system can be developed, i.e. a multiple-supplier multiple-customer retail market based e.g. on green certificates as in some European countries. 8.5. Demonstration activities A small number of national demonstration projects should be launched as real-life case studies to identify and mitigate barriers that may hinder the establishment of renewable power producers. 8.5.1. Recommendation 14: The Darling Wind Farm Implement the Darling Wind Farm demonstration project. Justification: The Darling Wind Farm has already been adopted by Government as a National Demonstration Project for both wind energy and independent power producers. It will be a useful source to identify barriers that may hinder the establishment of renewable power producers. The Darling project will therefore create a basis for the development of long-term solutions for renewable energy IPPs. Supporting Information: The general issues that will be addressed in preparing the Darling project are: Key technical aspects of grid connection Availability and accessibility of investment capital, incl. strategies to mitigate the financial risk in renewable energy projects Financial inter-mediation Full cost accounting IPP licenses Commercial requirements for grid connection, incl. potential power sales channels and power purchase, power wheeling and power banking agreements. 165 Mechanisms to cover incremental costs of commercial wind farms, incl. clean development mechanisms (CDM) and green power market Environmental impact assessment It is however important to note that progress in the Darling project should not be made subject to the other advances as outlined in this report. It is more envisaged that the Darling project should move ahead into the "unknown" so that the issues can be addressed on a reactive rather than proactive basis. If the Darling project has to wait for the establishment of the appropriate regulation, and the regulation needs experience from the Darling project, the process will be unnecessarily prolonged. 8.5.2. Recommendation 15: Mini-hydro Establish a mini-hydro power plant as a national demonstration project. Justification: This would most probably be a competitive project. Creating awareness will result in more viable projects beings identified. Supporting information: The Bethlehem project would be a proper candidate. 8.5.3. Recommendation 16: Cogeneration in sugar industry. Establish a combined heat and power plant in a sugar industry using bagasse as fuel as a national demonstration project. Justification: South Africa has a considerable potential for generating electricity from bagasse. Most sugar industries are already generating electricity for their own use, however using fairly inefficient equipment. By introducing modern high-efficient equipment the industries could generate much more electricity, more than they need themselves. Access to the grid and fair power purchase agreements are therefore prerequisites. The project should start with determining grid access conditions and a fair purchase price. 8.5.4. Recommendation 17: Cogeneration in wood/pulp industry A combined heat and power plant in a wood or pulp/paper industry using wood residues as fuel as a national demonstration project. . 166 Justification: South Africa has a considerable potential for generating electricity from residues from the wood and pulp industries. Currently, almost all industries use their wastes as boiler fuel for steam generation, while some also practice cogeneration, however with fairly inefficient equipment. By introducing modern high-efficient equipment the industries could generate much more electricity, more than they need themselves. Access to the grid and fair power purchase agreements are therefore prerequisites. 167