Download POCPA2012

Survey
yes no Was this document useful for you?
   Thank you for your participation!

* Your assessment is very important for improving the workof artificial intelligence, which forms the content of this project

Document related concepts

Wireless power transfer wikipedia , lookup

Audio power wikipedia , lookup

Electric power system wikipedia , lookup

Electrification wikipedia , lookup

Mains electricity wikipedia , lookup

Power over Ethernet wikipedia , lookup

Solar micro-inverter wikipedia , lookup

Opto-isolator wikipedia , lookup

Alternating current wikipedia , lookup

Power engineering wikipedia , lookup

Metadyne wikipedia , lookup

Amtrak's 25 Hz traction power system wikipedia , lookup

Buck converter wikipedia , lookup

Power electronics wikipedia , lookup

Pulse-width modulation wikipedia , lookup

Rectiverter wikipedia , lookup

Switched-mode power supply wikipedia , lookup

AC adapter wikipedia , lookup

Fault tolerance wikipedia , lookup

Transcript
Commissioning & Status of ALBA
Power Supplies
Roberto Petrocelli
POCPA 2012
 ALBA overview and commissioning
 ALBA Power Converters

Booster Power Converters

Storage Ring Power Converters
 Tools for the day to day business
 Maintenance schedule
 Conclusions
POCPA 2012
Synchrotron Light Source in Cerdanyola del Vallès
(Barcelona, Spain)
POCPA 2012
ALBA accelerators
LINAC
100 Mev
BOOSTER
100 MeV – 3 GeV
STORAGE RING
3 GeV
POCPA 2012
COMMISSIONING SCHEDULE
Booster commissioning in parallel to SR installation
SR commissioning (1st phase)
Installation Insertion Devices: SCW and IVUs
2010
March-June 2011
Summer 2011
SR commissioning with all IDs restarted
Sept 2011
Beam for beamlines commissioning
Oct 2011
First external users
May 2012
POCPA 2012
BOOSTER COMMISSIONING
POCPA 2012
SR COMMISSIONING
16 March: Beam Accumulated
1.5 mA stored
Acummulation
Current SR
Current Booster
POCPA 2012
1st synchrotron light
outside the tunnel
POCPA 2012
Once the MPS (to protect the machine) was operational…
POCPA 2012
LIGHT from APPLE-II UNDULATOR
Beam Image at Fluorescent Screen on the FE
• Screen @ 9.35m from source (middle of straight section)
• Source  APPLEII undulator EU62
• Stored current I=0.8mA
Minimum gap (15.5mm):
Horizontal mode (K=5.2)
Circular mode (K=3.0)
Vertical mode (K=3.7)
POCPA 2012
EMITTANCE
Emittance [nm·rad]
Coupling
Nominal
Measured
4.3
4.7
<1%
0.50 %
POCPA 2012
ORBIT STABILITY
1week data
1shift (8h) data
SLOW ORBIT FEEDBACK
RUNNING 0.3 Hz
88 BPMs
88 CORH & 88 CORV
FAST ORBIT FEEDBACK
UNDER DEVELOPMENT
POCPA 2012
2012 In Operation
 Beam-Line Users since May
 24 Hour operation
 2 injections.
 Expected 2000 hours for Beam Lines
and 1200 for Machine studies
POCPA 2012
Magnet Power supplies at ALBA
Distribution of Power Supplies
in the Service Area
POCPA 2012
Range of Magnet Power Supplies
SR-PC-BEND
BO-PC-BEND
SR-PC-SEXT
BO-PC-QUAD
800
LT-PC-CORR
600
(+/-2V-+/-2A)
BO-PC-CORR
400
(+/-12V-+/-6A)
200
0
-1000
-200
output current
-800
-600
-400
-400
-200
0
200
output voltage
-600
400
600
800
1000
-800
POCPA 2012
BOOSTER PCs
POCPA 2012
Major Incidences with main BO PS
15
date
PS
failure
action
1
06.11.09
Bend 2
Buck module failure
Sent to the factory for repair
2
15.12.09
Bend 2
Buck module failure
Sent to the factory for repair
3
23.03.10
Bend 2
Buck module failure
Sent to the factory for repair
4
21.06.10
Bend 2
Phase detector
Repaired at ALBA
5
25.07.10
Bend 2
Buck and 2Q module failure
Sent to the factory for repair
A capacitor on PWM that controls the switching frequency could drift and produce a double pulse.
It was replaced on all control boards
6
14.09.10
Bend 1
Auxiliary power supply
Replaced
7
15.11.10
QV02
PWM board failure
Repaired at ALBA
8
24.01.11
QS180
PWM board failure
Repaired at ALBA
9
24.01.11
Bend 1 & 2
Auxiliary power supplies
Replaced
10
27.04.11
Bend 1
2Q module failure
Repaired at ALBA by Bruker
11
29.04.11
Bend 2
2Q module failure
Repaired at ALBA by Bruker
3rd to 7th of May - Bruker slowed the start and stop procedures
12
16.05.11
QH02
Snubber resistor failure
Repaired at ALBA
13
23.05.11
Bend 1
Buck module failure
Sent to the factory for repair
14
20.04.12
Bend 1
2Q module failure failure
Replaced by spare module
POCPA 2012
Major Incidences with main BO PS
Noise in Buck Module of BO_Bend_01
Buck input current
POCPA 2012
SR PCs
POCPA 2012
 7 incidences with SR Quad (200A x15V).
POCPA 2012
TOOLS FOR DAY TO DAY BUSINESS
 PS Logbook
 PS database
 TRAINING OF OPERATORS
POCPA 2012
PS Logbook
POCPA 2012
2012 MAINTENANCE SCHEDULE
 5 WEEKS FOR MAINTENANCE ( distributed along the year)
 MAIN TASKS WE DO
 Connection Checks
 Rotate Spare Power Supplies
 Check calibration in Booster and SR Bendings.
 Perform annual test required by authorities ( CSN )
POCPA 2012
2012 MAINTENANCE
Terminal not Crimped
POCPA 2012
2012 MAINTENANCE
Fan out of order
POCPA 2012
STATISTICS
Operation for users
POCPA 2012
Next Steps
 Fast Orbit Feedback.
 Project of Power supplies for future upgrades.
POCPA 2012
Conclusions
 It is not realistic to expect to find all the
problems during FAT, SAT and commissioning.
POCPA 2012
Thank You !
Questions ?