Utility Scale PV Solar Site Specification/Audit Form
Date: December 2014
Solar Photovoltaic Ground Mounted System
Site Worksheet
Site Specifications to Consider:
a. Site dependent variables
i.
avoid tree lines or shading obstructions (southern, eastern/western boundaries)
ii. location of inverter can vary depending on interconnection point, type of inverters used and
shape of parcel being considered
iii. topography, which is geography dependent, would prefer flat or sloped to south or southwest
(typical tolerances for pier foundations is approximately 7-8% percent east to west)
iv. subsurface, which is also geography dependent, keep in mind that approximately 600 piers +/pending site specific geotech report and pile pull test results (c channel) driven into the ground
6 to 12 feet are needed for a 1 MW system
v. surrounding terrain assumptions (tree clearing, setbacks, ROW/easements, access to site, POCC
location, fencing requirements)
b. Ground coverage ratio can be affected, depending on site specific factors (e.g., more tilt requiring
greater row to row spacing, , off axis orientation to due south, shading obstructions, shape of
parcel) can increase acreage or decrease ground coverage ratio
Project Name:
Date
Completed By:
Phone/email
Alternate Contact:
Phone/email
Coop Information and Location Information
Coop/Organization
Street Address
City
State/Zip
,
Project Summary
Goals
AC Capacity
Requirement (kW)
1
Site Information
Street Address:
City:
State:
Zip Code:
Parcel Size (acres):
Site Description:
Minimum Size Requirements subject to site specific factors:
250 kW (1.5 acres)
500 kW (3 acres)
1 MW (6 acres)
Include: Utility information including power pole location, distance to 3-phase,
XFMR locations, other utility info including manholes, wells, storm drains;
access/egress, steep slopes/ inclines, cleared/vegetation, wet and dry locations,
rocky soils, site obstructions, indications of previous use, security concerns.
Sandy Gravel or Gravel
Sand or silty sand
Clayey sand or clayey gravel
Clay, Sandy Clay, Silty Clay
Clayey Silt, Silt and Sandy Silt
Soil Type:
Other notes/description:
Surrounding Area: Urban
Suburban
If close to water, miles from shoreline:
Is site fenced/secure: Yes
½ mi from open water
No
Access/Egress Info:
Available access for delivery truck w/ 53ft trailer: Yes
If yes, is it: Paved
Hard-packed Gravel
Other
No
Is site inside flood plain: 1% Annual FP? Yes
0.2% Annual-FP? Yes
No
No
Additional Notes:
Example: setbacks, tree screening/landscaping requirements, fire access requirements, mph wind rating,
snow load requirements
Site Ownership/Usage
Ownership of site:
Is the site currently registered as a single parcel?
2
Clean title? Yes
No
Current distribution and/or substation circuit requirements for reverse power or max capacity:
Utility ROW or Easements present on-site:
Current Zoning:
Has the property been surveyed in the past 10 years?
Is the plat available?
What county is the parcel located in?
Is the property located inside any city or town limit? If so, which town/city?
Is the property located in any city or town’s Extra Territorial Jurisdiction? Which town/city?
Have wetlands ever been delineated in the area subject to development?
Are there any regulatory issues (ie: zoning, environmental contamination, wetlands, wetlands, streams,
environmental, historic, endangered species)?
Yes
No
If Yes, describe?
Additional Notes: Adjacent property notes, Zoning contacts, Surveyor Contact, Plat registration info, etc.
Electrical Details
Electric Provider
Peak
months/days/hrs
Existing Service XFMR
kVA (if applicable)
Facility Peak kW
Existing Service to site
Single
3-Phase
Interconnection
Voltage
120V
208V
240V
277V
480V
12.47kV
13.8kV
20.6kV
27.6kV
34.5kV
Other
Interconnection Obstacles
3
Other Information
Information to be provided with sighting form:
Digital pictures/video of site with map references
and of probable interconnection point
Google Earth aerial images
GIS Image
FEMA Mapping for any property within flood zones
Tax parcel number
Tax parcel map
(If possible) topographic map and tax map with adjacent lots
Boring test data (geotech) if existing or new data is available