3. Totalization
Skill Check
Questions: Loss Adjustments
1. The defined meter point is:
a) The location of the meter
b) A virtual point used as the customer’s account
c) Always located at the high side of the power transformers
d) The point of connection where energy flows into and out of the IESO-controlled
grid
2. Select the correct statement:
a) The Ontario Energy Board (OEB) approves and publishes each LDC’s TLF.
b) The distribution loss factor is submitted at the time of metering installation
registration, and cannot be changed
c) Site-specific loss adjustments are made to adjust for the location of an embedded
connection point in relation to the defined meter point
Revised: July 2012
Revenue Metering
Public