Proposal Note 205
Temporary Sediment and Erosion Controls with Prices - 2/12/03
General:
Proposal Note 205 provides the unit prices to be used in conjunction with Supplemental
Specifications 832 and 833.
Further, this proposal note explains Item 832 Lump Sum Erosion Control which is found in
the quantity pages and defines Item 832 Storm Water Pollution Prevention Plan.
Item 832 Lump Sum Erosion Control:
The bidder will note that a fixed amount has been established by the Department for this
item. The fixed amount is a lump sum that shall be included in the bidder’s total bid amount
for this project.
The fixed amount entered by the Department for this item is an estimate of the total cost of
the Temporary Erosion Control Best Management Practices work required to be performed
for this project.
Item 832 Storm Water Pollution Prevention Plan:
The bidder will note that this item must be bid by the bidder as an as Each Item. The amount
entered by the bidder must reflect the cost of this item, in addition to overhead and profit, to
the bidder when performing this item. In the event that no Storm Water Pollution Prevention
Plan is required, the bidder shall bid $1.00 in order to avoid a blank bid. An entry of zero
dollars is not acceptable to the Department. When a Storm Water Pollution Prevention Plan
is found not to be required, the Department shall non-perform this item. This item is exempt
from the non-performance table found in Section 104.02 of the Construction And Material
Specifications.
The Department will make payment to the Contractor after the plan has been reviewed. Only
one Storm Water Pollution Prevention Plan shall be submitted by the Contractor for each
project awarded. All work required by this proposal note and the Supplemental
Specifications 832 and 833 shall be contained in that plan. Revisions to the plan may be
made by the successful Contractor. Those revisions made, but not caused by the Department,
shall be the financial responsibility of the Contractor. Those revisions to the accepted Storm
Water Pollution Prevention Plan caused by the Department will be paid by the Department
as part of the revised work.
Items to be Included in Total Bid Amount:
Both, Item 832 Lump Sum Erosion Control and Item 832 Storm Water Pollution Prevention
Plan shall be added to the bidder’s total bid amount in order to produce a total project bid
amount.
Erosion Control Item Unit Prices:
Listed below are the Erosion Control Item unit prices. The payment due for the properly
installed Erosion Control Items will be calculated using these unit prices times the properly
installed Erosion Control Item unit. Then these amounts will be deducted from the lump
sum fixed amount provided by the Department in the bid proposal for Item 832 Lump Sum
Erosion Control. When the temporary Sediment and Erosion Control Best Management
Practices work exceeds the fixed amount provided by the Department, the remaining work
required by this item still will be paid by the Department pursuant to the below listed unit
prices. These prices are fixed for the duration of this project. Additionally, all Temporary
Erosion Control Best Management Practices will be performed at these below listed unit
prices.
English Temporary Sediment and Erosion Control Prices
Item
Unit
Description
Prices
832
832
832
832
Square Yard
Foot
Cubic Yard
Foot
Construction Seeding and Mulching
Slope Drains
Sediment Basins and Dams
Perimeter Filter Fabric Fence
$0.46
$7.00
$2.80
$1.70
832
832
832
832
832
832
832
Foot
Foot
Foot
Cubic Yard
Square Yard
Square Yard
Cubic Yard
$4.50
$4.00
$8.00
$1.50
$1.10
$1.00
$32.00
832
Cubic Yard
832
832
Cubic Yard
Foot
Bale Filter Dike
Filter Fabric Ditch Check
Inlet Protection
Dikes
Construction Ditch Protection
Construction Slope Protection
Rock Channel Protection Type C or D with
Filter
Rock Channel Protection Type C or D without
Filter
Sediment Removal
Construction Fence
$30.00
$2.80
$3.80
Metric Temporary Sediment and Erosion Control Prices
Item
Unit
Description
Prices
832
832
832
832
Square Meter
Meter
Cubic Meter
Meter
Construction Seeding and Mulching
Slope Drains
Sediment Basins and Dams
Perimeter Filter Fabric Fence
$0.46
$21.00
$2.80
$5.10
832
832
832
832
832
Meter
Meter
Meter
Cubic Meter
Square Meter
Bale Filter Dike
Filter Fabric Ditch Check
Inlet Protection
Dikes
Construction Ditch Protection
$4.50
$12.00
$24.00
$1.50
$1.10
832
832
832
832
832
Square Meter Construction Slope Protection
Cubic Meter Rock Channel Protection Type C or D with
Filter
Cubic Meter Rock Channel Protection Type C or D without
Filter
Cubic Meter Sediment Removal
Meter
Construction Fence
$1.00
$32.00
$30.00
$2.80
$11.40
Designer Note:
This PN Note, SS 832, and SS 833 replaces 2002 CMS 207 or SS 877.
Provide this proposal note on all plans that have Project Identified earth-disturbing activities, as
defined as, any activity that exposes bare ground or an erodible material to storm water and anywhere
CMS Item 659 Seeding, SS 870 Seeding, CMS Item 660 Sodding, or SS 870 Sodding is being
furnished.
Delete all 2002 CMS 207 Items and all SS 877 Items
Provide SS 832 and SS 833 with this proposal note.
Provide under the Erosion Control Heading the following Reference Items:
Item 832 Lump Sum Erosion Control.
Item 832 Each Storm Water Pollution Prevention Plan.
Provide a encumbered dollar value to be placed in the proposal for the Item: 832 Lump Sum Erosion
Control. This amount should only be provided in the C2 Estimate and in the Special Considerations
Field on the Plan Package Submittal Form and not in the plans.
For additional guidance see the NPDES Construction Permit Implementation Plan flowchart on the
Office on Production website.