KANAL BANJIR TIMUR
SEMARANG
PROJECT AREA (1/2)
Feasibility Study:
① East Floodway (BKT)
including D/D for the
Downstream Reach
3
Majapahit Bridge - Estuary
Master Plan Study:
Babon River
② Penggaron/
③ Dombo Sayung River
④ Dolok River
2
Majapahit
Bridge
1
Candi River
Name
BKT
- Candi
- Bajak
- Kedung Mundu
Babon
Dombo-Sayung
Dolok
Penngaron
Kebon batur canal
River length
(km)
14.6
2.7
3.4
8.1
17.0
19.0
30.4
19.8
3.8
Bajak River
Pucanggading Weir
Kedung Mundu
River
4
Pucanggading
2
PROJECT AREA (2/2)
Penggaron
River
East
Floodway
Babon River
DomboSayung
River
Detail Of Pucang Gading Weir
3
EXISTING CONDITION (1/6)
Gergaji Weir
Pecanggading Weir
Babon River
DomboSayung River
Babon River
BKT
Inlet Gate of BKT
Penggaron River
DomboSayung
River
Pucanggading: Inlet Gate of the BKT and Overflow Weirs of
4
the Babon and Dombo-Sayung Rivers
EXISTING CONDITION (2/6)
JEMBATAN MAJAPAHIT
Mid-stream Reach
JEMBATAN KALIGAWE
Downstream Reach
Downstream Reach
BKT: Mid-stream and Downstream Reaches
EXISTING CONDITION (3/6)
Mid-stream Reach
Downstream Reach at
Pantura Road
Babon River: Mid-stream and Downstream Reaches
6
EXISTING CONDITION (4/6)
Mid-stream Reach
Downstream Reach at
Pantura Road
7
Dombo-Sayung River: Mid-stream and Downstream Reaches
EXISTING CONDITION (5/6)
Dolok River
Kebon Batur Canal
Dolok River
Mid-stream Reach
Upstream Reach
at Bifurcation to
Kebon Batur
Canal
To Dolok River
Downstream Reach
near Pantura Road
Palayaran Canal along
Pantura Road
Dolok River: Upstream to Downstream Reach
8
EXISTING CONDITION (6/6)
Inlet Gate at the
Bifurcation from the
Dolok River
Downstream
Reach Near
Penggaron River
Kebon Batur Canal: Upstream to Downstream Reaches9
BASIC CONCEPTS
I. River System Principle: Treatment of floods within
each river system as much as possible.
1) Penggaron River System
BKT, Babon, Dombo-Sayung River System
2) Dolok River System
3) Kebon Batur Canal: Stop Inter-basin Flood Transfer
 To close the inlet sluice gate during floods after
completion of the future river improvement of the
Dolok River.
 To open the inlet sluice gate in normal period for
water use and environment.
II. Design Scale: 50-year Return Period of Flood
10
N
Jawa Sea
Dombo-Sayung
River
Dolok
River
East Floodway
(BKT)
Babon
River
BKT
Candi
River
Bajak
River
Penggaron River System:
 Utilize the Natural
Retarding Basin as it is.
 River Improvements of
the BKT, Babon and
Dombo-Sayung Rivers.
Dolok River System:
 Existing River
 Close the Inlet Gate of
the Kebon Batur Canal
during floods
Legend:
Kudung
Mundu
River
Close gate
during
floods
Pecanggading
Penggaron
River
KubonBatur Canal
Barang Weir
River
Major Road
Railway
Existing Overflow Weir
Existing Gated Weir
Natural Retarding
Basin
River Improvement
Penggaron RS_Alt-1: River Improvements
N
Jawa Sea
Dombo-Sayung
River
Dolok
River
East Floodway
(BKT)
Babon
River
Candi
River
Legend:
River
Major Road
Railway
Existing Overflow Weir
Existing Gated Weir
Natural Retarding
Basin
River Improvement
BKT
Bajak
River
Close gate
during
floods
Kudung
Mundu
River
Pecanggading
Penggaron
River
KubonBatur Canal
260
Barang Weir
Design Discharge of 50
Year Return Period
(m3/s)
Penggaron RS_Alt-1: Design Discharge
12
N
Jawa Sea
Dombo-Sayung
River
Dolok
River
East Floodway
(BKT)
Babon
River
BKT
Candi
River
Bajak
River
Penggaron River System:
 Strengthening of the
Retarding Basin.
 River Improvements of
the BKT, Babon and
Dombo-Sayung Rivers.
Dolok River System:
 Existing River
 Close the Inlet Gate of
the Kebon Batur Canal
during floods
Legend:
Kudung
Mundu
River
Close gate
during
floods
Pecanggading
Penggaron
River
KubonBatur Canal
Barang Weir
River
Major Road
Railway
Existing Overflow Weir
Existing Gated Weir
Strengthening of the
Retarding Basin
River Improvement
Penggaron RS_Alt-2: River Improvements and Strengthening of the Retarding Basin
N
Jawa Sea
Dombo-Sayung
River
Dolok
River
East Floodway
(BKT)
Babon
River
Candi
River
Note:
Design discharge of BKT_Alt-2 is
set at the same discharge of the
Alt-1 for conservative
consideration. This is because,
although the simulated discharge
of Alt-2 in the mid-stream to
downstream reaches is smaller than
that of Alt-1, timing of joining the
discharge from the tributaries
cannot be fixed like simulation.
Legend:
River
Major Road
Railway
Existing Overflow Weir
Existing Gated Weir
Natural Retarding
Basin
River Improvement
BKT
Bajak
River
Close gate
during
floods
Kudung
Mundu
River
Pecanggading
Penggaron
River
KubonBatur Canal
260
Barang Weir
Design Discharge of 50
Year Return Period
(m3/s)
Penggaron RS_Alt-2: Design Discharge
14
Alternative-1
Upstream of retarding area
Penggaron River Discharge
Downstream of retarding area
700
Q:660 m3/s
Discharge (m3/s)
600
Effect of Natural
Retarding Basin
V=1.15MCM
500
400
Q:530 m3/s
300
200
100
Alternative-2
0:00
23:00
22:00
21:00
20:00
19:00
18:00
17:00
16:00
15:00
14:00
13:00
12:00
11:00
10:00
9:00
8:00
7:00
6:00
5:00
4:00
3:00
2:00
1:00
0:00
0
Upstream of retarding area
Penggaron River Discharge
Downstream of retarding area
700
Q:660 m3/s
500
Effect of
Strengthening the
Retarding Basin
V=3.67MCM
400
300
200
Q:390 m3/s
100
0:00
23:00
22:00
21:00
20:00
19:00
18:00
17:00
16:00
15:00
14:00
13:00
12:00
11:00
10:00
9:00
8:00
7:00
6:00
5:00
4:00
3:00
2:00
1:00
0
0:00
Discharge (m3/s)
600
Effect of the
Retarding
Basin in the
Penggaron
River
BKT: Design Profile, Cross Sections and HWL
16
BKT: Construction Cost (Preliminary Draft)
No
Item
Mid-Stream to
Downstream Reach
Upstream Reach
(River Mouth to
(Majapahit Bridge to the
Majapahit Bridge)
Inlet Gate at
Pucanggading)
Total
(Mil. Rp.)
241.952
4.131
9.678
(Mil. Rp.)
197.961
263.317
7.918
(Mil. Rp.)
439.913
267.448
17.597
1
2
3
Main Civil Work
Compensation Cost
Engineering Cost (4%)
4
Total
(Include compensation cost)
255.761
469.196
724.958
5
Total
(exclude compensation cost)
251.630
205.879
457.510
Notes: 1) Cost of Main Civil Works does not include the cost for reconstruction of bridge.
The cost of reconstruction of bridge will be included in the final cost.
2) Engineering cost = 4% of (Cost of Main Civil Works)
17
Implementation Program (Preliminary Draft)
Year
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
Project
1. East Floodway (BKT)
1-1 Downstream Reach (From River Mouth to Majapahit Bridge)
1) Detailed Design
2) Requesting for Budget
3) Procurement of Consultant
4) Procurement of Contractor
5) Land Acquisition and Relocation of Houses
6) Preparation of Disposal Site
7) Construction
1-2 Mid-stream to Upstream Reach (From Majapahit Bridge to the Inlet Gate)
1) Detailed Design
2) Requesting for Budget
3) Procurement of Consultant
4) Procurement of Contractor
5) Land Acquisition and Relocation of Houses
6) Preparation of Disposal Site
7) Construction
18