More Grads Earning More Money
More Grads Earning More Money
November 4, 2016
COLLEGE WEST RESIDENCE
RENEWAL PROJECT
More Grads Earning More Money
PROJECT SUMMARY
 $38M project to completely renew suites and amenity spaces
in College West, Levels 3 - 6
 Upgrading of critical systems
 New finishes and furnishings throughout
 New roof
 New exterior windows within the renovation area
More Grads Earning More Money
PROJECT SCHEDULE
 Start: November 2016
 Completion: March 2018
 Schedule influences include the loss of revenue for 2+
years and the need to be complete prior to the 2018
Congress of the Humanities and Social Science
CW Residence Renewal Project
More Grads Earning More Money
PROJECT IMPACTS - EXTERIOR
More Grads Earning More Money
PROJECTS IMPACTS – EXTERIOR
 Construction fencing west of building, restricted area
 Sidewalk closure
 Increased traffic including large equipment, occasional road
closures as required.
 Parking implications
 Relocated bike racks, DSA
 Minimal impact on loading dock
\
More Grads Earning More Money
PROJECT IMPACTS – INTERIOR





Noise
Dust
Utility disruptions
Increased foot traffic in building
Need to access occupied space to work (Science, ESL)
More Grads Earning More Money
WORKING IN OCCUPIED SPACE
 All interruptions will be coordinated by Project Manager and
advance notice will be provided.
 Contractor must take necessary precautions to protect
contents of individual offices.
 After hours work when possible. Alternate space to work may
also be an option
More Grads Earning More Money
EFFORTS TO MINIMIZE DISRUPTION





Working Group established in July 2016
Relocating classes for January 2017
Adjustments to class schedules
After hours work
Commitment to clear and constant communication
throughout the course of the project
More Grads Earning More Money
HAZARDOUS MATERIALS




Asbestos containing material (ACM)
Typical for a structure of this age
Full abatement prior to new construction
Strict compliance with industry and regulatory best
practice safety protocols
 More information available on HR website or by
contacting our Industrial Safety Consultant (5487)
More Grads Earning More Money
ISSUES OR CONCERNS?
 For all safety concerns, please call Work Control (4039)
 Faculty of Science, call Lee Aument (4144) or Vincent
Ignatiuk (4769)
 English as a Second Language, call Wendy Preikchat (4093)
 All others, call Paula Matz (2221)
\
More Grads Earning More Money
INFORMATION
For more information about this project, please contact
Paula Matz @ 2221 or [email protected]
Future updates will be posted to the Associate VicePresident (Academic and Research) webpage
\
More Grads Earning More Money
QUESTIONS?
\